Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Integrated Logistics Park “Welspun One Logistic Park- Bhiwandi”
(b)Name of the Company / Organisation DBG ESTATES PRIVATE LIMITED
(c)Registered Address DBG Estates Private Limited, 7th Floor, Welspun House, Kamala Mills Compound, Senapati Bapat Marg, Lower Parel, Mumbai.,,Mumbai City,Maharashtra-400013
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sanjeev Arjun Jhurani
(b)Designation (Owner/ Partner/ CEO) Vice President
(c)Address 4th Floor, Welspun House, Kamala Mills Compound, Senapati Bapat Marg, Lower Parel, Mumbai-400013,,Andheri,Mumbai City,Maharashtra-400013
(d)Pin code 400013
(e)E-mail sanjeev_jhurani@welspun.com
(f)STD Code. 22(f)Telephone No. 66135804
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(b) Townships and Area Development projects.
Minor Activity8(b) Townships and Area Development projects.
(b)Category B1
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/MH/MIS/176254/2020
(d)Master Proposal Number(Single Window) SW/176248/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Bapgaon village: Survey No. 36/1/A, 36/1/B, 36/2/A
(b)Pincode 421302
(c)Bounded Latitudes (North)
From
Degree 2132615.79
Minutes
Second
From
Degree 2133625.19
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 304182.95
Minutes
Second
From
Degree 305262.86
Minutes
Second
(e)Survey of India Topo Sheet No. E43B3 (47E/3)
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 10
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.07
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number SIA/MH/NCP/52875/2020
(c)Date of Apply of TOR 15 Apr 2020
(d)Date of Issue of TOR / Standard ToR 26 Jun 2020
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As per EIA Notification 2006, all building and construction project are exempted from PH
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)DG set18*500 kVA
(2.)STP180 KLD Combined capacity
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Plot area44.83HectaresOthersNA
(2.)Built Up Area36.95HectaresOthersNA
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 02 Sep 2020
(iv)Valid Upto 02 Sep 2020
(v)File No. -
(vi)Application No. -
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 550
(b) Funds Allocated for Environment Management (Capital) (in Crores) 5.18
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 5.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.52
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Building & Construction material -Cement, sand, aggregate, wood, etc.0Tons per Annumopen marketRoad10 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2019 To 29 Feb 2020
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube79.961.279.8100
(2.)PM2.5Micro Gram per Meter Cube57.340.256.860
(3.)SO2Micro Gram per Meter Cube37.82037.480
(4.)OthersCOMili Gram per Meter Cube2.10.41.92
(5.)NOxMicro Gram per Meter Cube44.822.943.680
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.67.46.58.5
(2.)Chloridesmg/l94.679.62501000
(3.)TSSmg/l0000
(4.)TDSmg/l4644125002000
(5.)Heavy MetalsNimg/l0.00.00.020
(6.)Total Hardnessmg/l198.6156.9200600
(7.)Fluoridemg/l0.210.0211.5
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA87D
(2.)DOmg/l4.13.8D
(3.)BODmg/l21.316.9E
(4.)CODmg/l68.552.3E
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))52.851.255-65
(2.)Leq(Night)A-weighted decibels(dB(A))42.341.744-55
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.47
(2.)P(Phosphorus)Milligram per Kilogram224.5131.45
(3.)N(Nitrogen)Milligram per Kilogram546.7327.9
(4.)K(Potassium)Milligram per Kilogram377.48216.32
(5.)Electric ConductivityMillisiemens per Centimetre0.380.13
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.50 To 14.60
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.20 To 6.90
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGram Panchayat2671.0Copy of Permission LetterPipelineOthersPipeline-13 Feb 2020300
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic use170180STPReuse within the Plant & Recycling170
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 170
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 170
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Biodegradable wasteMunicipal Solid Waste98.55Tons0OthersWithin siteOthersOrganic Waste converter
(2.)Non Biodegradable wasteMunicipal Solid Waste74.1Tons5RoadAuthorized Recyclers
(3.)Recycled wastePlastic Waste73.73Tons5RoadAuthorized Recyclers
(4.)E-WasteE Waste0.12Tons6RoadAuthorized Recyclers
(5.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1.51Kilolitre5RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube68.90.250.0169100
(2.)NOxMicrogram per Meter Cube39.40.250.640.180
(3.)PM2.5Microgram per Meter Cube530.250.0353.160
(4.)Others(Specify)COMicrogram per Meter Cube14000.2531403.12000
(5.)SO2Microgram per Meter Cube33.50.250.333.8180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)18*500 KVA DG stackHSD4.50.3PM100.017
(2.)18*500 kVA DG stackHSD4.50.3SO20.06
(3.)18*500 kVA DG stackHSD4.50.3NOx0.09
(4.)18*500 kVA DG stackHSD4.50.3OthersCO0.1
(5.)18*500 kVA DG stackHSD4.50.3OthersPM 2.50.007
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 11000
(b)Source Maharashtra State Electricity Distribution Company
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 18*500 kVA
(e)Stack Height (in m) 4.5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 44.82702
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 44.82702
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 14912.71
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1983.27
(e)Settlements (ha.) 11248.98
(f)Industrial (ha.) 0
(g)Forest (ha.) 2263.72
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : scrubland 4741.48
    Total (ha.) 35150.1600
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant22.95
(2.)Green belt8.84
(3.)Othersparking and open area8.55
Total (ha.) 40.34
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaDombivali7.37SSW direction
(2.)WLSNone0None
(3.)ESAsNone0None
(4.)Wildlife CorridorsNone0None
(5.)NPANone0None
(6.)ESZsNone0None
(7.)CorridorsNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestReserve Forest near Janval2.47NNW direction
(2.)Archaeological SitesThe Temple of Ambernath9.72SSE direction
(3.)Defence InstallationsNone0none
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 44.83
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Crocodylus palustris (Indian Crocodile), Varanus bengalensis (Common Indian Monitor), Gyps bengalensis (Indian Whitebacked Vulture), Pavo cristatus (Peafowl) and Felis silvestris ornata (Wild Cat)
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Seasonal drain
(b)Whether there is Diversion Required ? Yes
(i)Details of Diversion Required The stream/drain flows from NE-SW will be rerouted with due permission
(ii)Details of Study Conducted Yes, enclosed in EIA report
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Ulhas River
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 0.07
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 4000
(c)Temporary Employment- During Construction 300
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 4300
32.
Green Belt in Ha:
(a)Total Area of Green Belt 8.84
(b)Percentage of Total Project Area 19.72
(c)No. of Plants to be Planted 4035
(d)Funds Allocated for Plantation 17100000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialDirect and indirect Employment will be generated
(2.)EnvironmentalPlantation of trees all around the project periphery including avenue plantation will be carried out
(3.)FinancialRevenue will be generated
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 13.7
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 16
(d)Total plot area (sqm) 448270.24
(e)Total built up area (sqm) 369479
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 25
(d)Capacity 22500
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 50438.56 sqm
5.
Energy Saving Measures:
(a)Source/Mode Maharashtra State Electricity Distribution Company
(b)Percentage 37
(c)Quantity 4070
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Diversion of one seasonal stream present within t
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/ENV/ACO/20/1464 dated September 4, 2020
(ii)Name of the EIA Consultant Perfact Enviro Solutions Pvt. Ltd.
(iii)Address 5 th Floor, NN Mall, Sector – 3, Rohini, New Delhi - 110085
(iv)Mobile No. 9871591330
(v)Landline No. 0114928136
(vi)Email Id info@perfactgroup.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 03 Dec 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSanjeev Arjun Jhurani
DesignationVice President
Name of Company (Applicant Name should not be given here)DBG ESTATES PRIVATE LIMITED
AddressDBG Estates Private Limited, 7th Floor, Welspun House, Kamala Mills Compound, Senapati Bapat Marg, Lower Parel, Mumbai.