Form-1
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
1. Basic Informations
Project Name Proposed Expansion Bulk Drug and Bulk Drugs Intermediates manufacturing unit M/s. Prayosha Healthcare Pvt. ltd. Unit-1 Company/Organisation Name M/S. PRAYOSHA HEALTHCARE PVT. LTD.
Registered Address Plot no.6208/6209, GIDC Ankleshwar, Dist:Bharuch, Gujarat Gujarat 393002 Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Tushar Bhai Patel
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Plot no.6208/6209, GIDC Ankleshwar, Dist:Bharuch, Gujarat,Bharuch,Gujarat-393002
(d)Pin code 393002
(e)E-mail prayosha_6209@yahoo.com
(f)Telephone No. 22446949
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(f)-API
(b)Minor Project/Activity5(f)-API
(c)Category B2
(d)Proposal Number IA/GJ/IND2/175327/2020
(e)Master Proposal Number(Single Window) SW/175324/2020
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type(New/Expansion/Modernization) Expansion
4.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
5.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(c)Reason -1
(d)Supporting Document Copy of Supporting Document

Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No Proposed expansion is within Existing Premises.
1.2 Clearance of existing land, vegetation and buildings? Yes Minor site clearance activities shall be carried out to clear shrubs and weed.
1.3 Creation of new land uses? No --
1.4 Pre-construction investigations e.g. bore houses, soil testing? No --
1.5 Construction works? Yes Plant layout is attached as Annexure-1.
1.6 Demolition works? No --
1.7 Temporary sites used for construction works or housing of construction workers? No --
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations Yes Plant layout is attached as Annexure-1.
1.9 Underground works including mining or tunneling? No --
1.10 Reclamation works? No --
1.11 Dredging? No --
1.12 Offshore structures? No --
1.13 Production and manufacturing processes? Yes List of Products is attached as Annexure-2 and manufacturing process is attached as Annexure-3.
1.14 Facilities for storage of goods or materials? Yes Dedicated storage area for storage of Raw Materials and finished products, solvents, etc. shall be provided.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Details of proposed Effluent Treatment Plant are attached as Annexure-5. Details of Hazardous waste generation and disposal is attached as Annexure-6.
1.16 Facilities for long term housing of operational workers? No --
1.17 New road, rail or sea traffic during construction or operation? No --
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No --
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No --
1.20 New or diverted transmission lines or pipelines? No --
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No --
1.22 Stream crossings? No --
1.23 Abstraction or transfers of water from ground or surface waters? Yes No ground water shall be used. The requirement of raw water shall be met through GIDC Water Supply.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No --
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Transportation of personnel, raw material and products will be primarily by road only.
1.26 Long-term dismantling or decommissioning or restoration works? No --
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No --
1.28 Influx of people to an area in either temporarily or permanently? Yes Direct/Indirect employment shall be provided for proposed expansion operation.
1.29 Introduction of alien species? No -
1.30 Loss of native species or genetic diversity? No --
1.31 Any other actions? No --
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No --
2.2 Water (expected source & competing users) unit: KLD Yes Water requirement will meet through GIDC Water supply. Water balance is given as Annexure-4.
2.3 Minerals (MT) No --
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Company shall use Sand, Stone, Cement and Structural Steel for Construction as required.
2.5 Forests and timber (source – MT) No --
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes Power requirement: Existing: Power required from DGVCL is 200 KVA. Total after Proposed Expansion: Power required from DGVCL will be 300 KVA. DG Set (320 KVA) will be kept for emergency power back-up. Fuel Requirement: Existing Natural Gas = 300 m3/Day Diesel: 120 Lit/Day Proposed Natural Gas = 1600 m3/Day or Briquettes of Bio-Coal: 9.6 MT/Day Diesel: 120 Lit/Day
2.7 Any other natural resources (use appropriate standard units) No --
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes Please refer Annexure-7.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No --
3.3 Affect the welfare of people e.g. by changing living conditions? No --
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No --
3.5 Any other causes No --
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No --
4.2 Municipal waste (domestic and or commercial wastes) No --
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Please refer Annexure-6.
4.4 Other industrial process wastes Yes Please refer Annexure-6.
4.5 Surplus product No --
4.6 Sewage sludge or other sludge from effluent treatment Yes Please refer Annexure-6.
4.7 Construction or demolition wastes Yes Construction waste shall be utilized for leveling, land filling in the premises.
4.8 Redundant machinery or equipment No --
4.9 Contaminated soils or other materials No --
4.10 Agricultural wastes No --
4.11 Other solid wastes Yes Please refer Annexure-6.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Please refer Annexure-8
5.2 Emissions from production processes Yes Please refer Annexure-8
5.3 Emissions from materials handling including storage or transport Yes All liquid raw materials shall be procured in tankers and shall be transferred through a closed circuit pipe lines. Solid raw materials shall be charged through close pipeline into reactors and the dust collection hopper shall be connected to a bag filter and ID fan.
5.4 Emissions from construction activities including plant and equipment Yes During construction work, only dust contamination will be there & water sprinklers shall be utilized whenever necessary.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dust from drying will be collected in to dust collector through cyclone separator & recovered powder will be recycled back to process. Air Handling Unit will be provided where ever applicable.
5.6 Emissions from incineration of waste No --
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No --
5.8 Emissions from any other sources Yes Please refer Annexure-8
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Use of PPE like ear plugs and ear muffs will be made compulsory near the high noise generating machines. Proper and timely oiling, lubrication and preventive maintenance will be carried out for the machineries & equipments to reduce noise generation. D.G. Set will be installed in a closed room and provided with acoustic enclosure.
6.2 From industrial or similar processes Yes All machinery / equipment shall be well maintained, shall be proper foundation with anti vibrating pads wherever applicable and noise levels within permissible limits. Acoustic enclosures shall be provided for DG set.
6.3 From construction or demolition No --
6.4 From blasting or piling No --
6.5 From construction or operational traffic No --
6.6 From lighting or cooling systems No --
6.7 From any other sources No --
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes All raw materials shall be stored separately in designated storage area and safely. Dyke walls shall be provided around raw materials storage tanks for containing any liquid spillage. Other materials shall be stored in bags / drums on pallets with concrete flooring and no spillage is likely to occur. Please refer Annexure-7.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes Sewage shall be treated in STP Plant.
7.3 By deposition of pollutants emitted to air into the land or into water No --
7.4 From any other sources No --
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No -
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes The risk assessment will be carried out and all mitigate measures shall be taken to avoid accidents. Please refer Annexure-7
8.2 From any other causes No --
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No --
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Site is having the entire required infrastructure. Existing road infrastructure & power supply are to be utilized. Local people will be employed and no housing is required. Please refer Annexure-9.
9.2 Lead to after-use of the site, which could have an impact on the environment No --
9.3 Set a precedent for later developments No --
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No --
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Proposed expansion project site is within the GIDC, Ankleshwar.
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes River Narmada = 9 kms
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No --
4 Inland, coastal, marine or underground waters No --
5 State, National boundaries No --
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes Public transportation
7 Defence installations Yes Ankleshwar
8 Densely populated or built-up area Yes Ankleshwar City around 0.5 km from the proposed project site.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No --
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No --
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) Yes Ankleshwar
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No --
Document to be attached
1. Upload a copy of PFR Uploaded a copy of PFR.
2. Upload a copy of EMP Uploaded a copy of EMP.
3. Upload Scanned copy of covering letter. Uploaded Scanned copy of covering letter..
4. Upload Additional attached if any(Single PDF) Uploaded Additional attached if any(Single PDF).
5. Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)29/09/20201. This is an expansion proposal accordingly, the PP shall submit the certified compliance report to the conditions of CTO from the SPCB. 2. Based on the information submitted by PP it is Category B2 project. It is not clear why PP has applied at Central Level on Parivesh Portal. 3. Moreover, some of the products are API Intermediate, However, the Notification dated 27.03.2020 is only for API. Please recheck your products mentioned in the application. 4. Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted. 5. All old CTOs not uploaded to verify the violation, if any done by PP. 6. Details of earlier production capacity needs to be authenticated and uploaded to check the violation, if any. 7. Please check your proposal once again and submit the above mentioned information. It is also mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance and accordingly the PP/Consultant are kindly requested to revise the application and resubmit the same.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantTushar Bhai Patel
DesignationDirector
Name of Company (Applicant Name should not be given here)M/S. PRAYOSHA HEALTHCARE PVT. LTD.
AddressPlot no.6208/6209, GIDC Ankleshwar, Dist:Bharuch, Gujarat
Print