Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Redevelopment of existing chawls and Construction of Sale Residential cum Commercial Complex on plot bearing S. No. 98/4, 99/2 at village Katemanivali, Tal. Kalyan, District Thane. by M/s. Yash Realty
(b)Name of the Company / Organisation M/S YASH REALTY
(c)Registered Address 101, Khushi Heights, Near Nitinraj Hotel, Katemanivali, Kalyan,Thane, Maharashtra,Thane,Maharashtra-431306
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Yashwant Sitaprasad Yadav
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address 101, Khushi Heights, Near Nitinraj Hotel, Katemanivali Road, Kalyan,,Thane Maharashtra,Kalyan,Thane,Maharashtra-421306
(d)Pin code 421306
(e)E-mail yashrealty06@gmail.com
(f)STD Code. 0(f)Telephone No.
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(a) Building and Construction projects
Minor Activity
(b)Category B2
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/MH/MIS/175103/2020
(d)Master Proposal Number(Single Window) SW/175085/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. S. No. 98/4, 99/2
(b)Pincode 421306
(c)Bounded Latitudes (North)
From
Degree 191355.16
Minutes
Second
From
Degree 19141.46
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 73843.41
Minutes
Second
From
Degree 73845.26
Minutes
Second
(e)Survey of India Topo Sheet No. Reg. No. 3956-104 D96
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 8.84
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.02
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Not Applicable as it is 8A B2 project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Sale bldg No.2 (Residential &comm.)Stilt (pt.)+gr.(pt.)+15 floorsRes.102, Shops: 18,
(2.)ClubhouseGr.+1st floor
(3.)Sale bldg No.1 (Residential &comm.)Stilt (pt.)+gr.(pt.) + 1st podium+14 floorsRes.84, Shops: 10,
(4.)Sale bldg No.3 (Residential &comm.)Stilt (pt.)+gr.(pt.) +5 floors(pt.)Res.: 14, Shops: 7,
(5.)Tenant Building No.4 (Residential &comm.)Stilt (pt.)+gr.(pt.)+ 20 Floors.Res.: 62, Mhada: 34 Shops: 12,
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Residential Project with shops22592.46OthersSq.mRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 36.46
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.10
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.36
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.21
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Building & Construction material -Cement, sand, aggregate, wood, etc.0OthersNANARoad0 MoUNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 25 Sep 2020 To 25 Sep 2020
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5NA0000
(2.)PM10NA0000
(3.)SO2NA0000
(4.)NOxNA0000
    14.2.     No. of Ground Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)FluorideNA0000
(2.)TSSNA0000
(3.)ChloridesNA0000
(4.)Heavy MetalsNANA0000
(5.)pHNA0000
(6.)TDSNA0000
(7.)Total HardnessNA0000
    14.3.     No. of Surface Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DONA00A
(2.)BODNA00A
(3.)pHNA00A
(4.)CODNA00A
    14.4.     No. of Ambient Noise monitoring locations : 0
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))000
(2.)Leq(Night)A-weighted decibels(dB(A))000
    14.5.     No. of Soil Sample Monitored locations : 0
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH00
(2.)K(Potassium)00
(3.)Electric Conductivity00
(4.)N(Nitrogen)00
(5.)P(Phosphorus)00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 5.0 To 8.0
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.0 To 7.0
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersKDMC Municipal Water supply2110Copy of Permission LetterPipelineOthersKDMC Municipal Water SupplyLetter is not yet obtained25 Sep 2020136
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic193200STP Of capacity 200 KLD with MBBR TechnologyReuse within the Plant & Recycling,Green Belt Renewal Plant,OthersSewer Line75118
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 193
(b)Total Discharged Water (Kilolitre per Day) 118
(c)Total Reused Water (Kilolitre per Day) 75
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)OtherE Waste0.07Tons0RoadAuthorized Recyclers
(2.)Biodegradable wasteMunicipal Solid Waste0.46Tons0OthersTreated at Site onlyOthersTreated in Organic Waste Composter (OWC)
(3.)Non Biodegradable wasteMunicipal Solid Waste0.32Tons0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5NA00010
(2.)PM10NA00010
(3.)SO2NA00010
(4.)NOxNA00010
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)attached to 250 KVA DG SetHSD (45 Lit/Hr)4.220.19PM100.109
(2.)attached to 250 KVA DG SetHSD (45lits/Hr)4.220.19NOx3.0
(3.)attached to 250 KVA DG SetHSD (45 Lit/Hr)4.220.19SO20.18
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2009.29
(b)Source MSEDCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1 DG Set of 250 kVA
(e)Stack Height (in m) 4.22
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 1.06
    Total Land (ha.) 1.06
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Redevelopment Project 1.06
    Total (ha.) 1.0600
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area1.06
Total (ha.) 1.06
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNA0NA
(2.)ESZsNA0NA
(3.)CorridorsNA0NA
(4.)Wildlife CorridorsNA0NA
(5.)WLSNA0NA
(6.)NPANA0NA
(7.)Critically Polluted AreaNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsOrdnance Factory Ambernath3.30It is as per Survey of Site and its surrounding
(2.)Archaeological SitesDurgadi Fort3.09Heritage site
(3.)ForestNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 13
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Natural Nalla
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 0.02
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 100
(b)Permanent Employment-During Operation 10
(c)Temporary Employment- During Construction 34
(d)Temporary Employment- During Operation 6
(e)No. of working days 6
(f)Total Manpower 150
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.09
(b)Percentage of Total Project Area 8.49
(c)No. of Plants to be Planted 109
(d)Funds Allocated for Plantation 7.10
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThere are 50 existing Chawls dwellers on plot. All are getting rehoused on the same plot. Their health, hygiene and living standards will increase and encroachment on existing plot for development of reservations will be opened up.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 62.65
(b)Total No. of Flats to be Build 296
(c)No. of Buildings 4
(d)Total plot area (sqm) 10690
(e)Total built up area (sqm) 22952.46
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 1
(b)Capacity 82
(c)No. of Recharge Pits 7
(d)Capacity 56.09
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 70 no. of parking provided for cars, Same car park
5.
Energy Saving Measures:
(a)Source/Mode by Conventional and Renewable Energy
(b)Percentage 23.7
(c)Quantity 402388
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area No alteration of natural drainage system is propos
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA066
(ii)Name of the EIA Consultant MANTRAS GREEN RESOURCES LTD.
(iii)Address Hall No.1, First Floor, NICE Sankul, Plot No. A-9, Opp.-Nashik Merchant Co-op Bank Ltd., ITI Signal, MIDC Satpur, Nasik-07
(iv)Mobile No. 9867851056
(v)Landline No. 2532355665
(vi)Email Id vaishaliharshal@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 29 Sep 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantYashwant Sitaprasad Yadav
DesignationPartner
Name of Company (Applicant Name should not be given here)M/S YASH REALTY
Address101, Khushi Heights, Near Nitinraj Hotel, Katemanivali, Kalyan
Print