Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Commercial project on subdivided plot bearing CTS No. 533(pt), 533/2(pt), & 553 (pt), of village Nahur, L. B. S. Road, Mulund (W), T- Ward, Mumbai
(b)Name of the Company / Organisation KALPATARU LIMITED
(c)Registered Address NIL
(d)Legal Status of the Company NIL
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Imtiaz Kanga
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address 101, Kalpataru Syergy, Opp Grand hyatt, Santacruz east,,Kurla,Mumbai (Suburban),Maharashtra-400055
(d)Pin code 400055
(e)E-mail saurabh.sawant@kalpataru.com
(f)STD Code. 22(f)Telephone No. 30645000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(a) Building and Construction projects
Minor Activity
(b)Category B2
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/MH/MIS/174154/2020
(d)Master Proposal Number(Single Window) SW/174151/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. CTS No. 533(pt), 533/2(pt), & 553 (pt), of village
(b)Pincode 400078
(c)Bounded Latitudes (North)
From
Degree 19.16
Minutes
Second
From
Degree 19.18
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.93
Minutes
Second
From
Degree 72.96
Minutes
Second
(e)Survey of India Topo Sheet No. E43A16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 22.25
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4.00
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Not applicable
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Building construction project1B+G/S+1P/C+2- 7P+8P/S+1-24 CF1st podium is partly commercial
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Building construction project62891.56OthersSq.mOthersBuilding construction project
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 255.52
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.8883
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.55
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.1195
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 62891.56
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 62891.56
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)CONSTRUCTION MATERIAL0OthersBuilding construction projectNARoad0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 1960 To 31 May 1960
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10NA0000
(2.)PM2.5NA0000
(3.)SO2NA0000
(4.)OthersThis is an 8a B2 projectNA0000
(5.)NOxNA0000
    14.2.     No. of Ground Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSNA0000
(2.)Total HardnessNA0000
(3.)TSSNA0000
(4.)FluorideNA00000
(5.)pHNA0000
(6.)Heavy Metals0NA00000
(7.)ChloridesNA00000
(8.)OthersThis a 8(a) B2 projectNA0000
    14.3.     No. of Surface Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DONA00E
(2.)pHNA00E
(3.)OthersThis is a 8(a) B2 projectmg/l00A
(4.)BODNA000E
(5.)CODNA00E
    14.4.     No. of Ambient Noise monitoring locations : 0
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))000
(2.)Leq(Night)A-weighted decibels(dB(A))000
    14.5.     No. of Soil Sample Monitored locations : 0
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)00
(2.)K(Potassium)00
(3.)Electric Conductivity00
(4.)pH00
(5.)P(Phosphorus)00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 6 To 8
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 4 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMCGM2502.0Copy of Permission LetterPipelineOthersMCGM- municipal corporationHE/000471/2020/T/ES18 Jul 2020250
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewerage Water197220STPOthersPart reused & Part Discharge11582
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 197
(b)Total Discharged Water (Kilolitre per Day) 82
(c)Total Reused Water (Kilolitre per Day) 115
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Biodegradable wasteMunicipal Solid Waste158.77Tons0OthersIn situ treatmentOtherswill be treated on site
(2.)Non biodegradableMunicipal Solid Waste238.34Tons0Otherswill be handed over to local planning authoityOthersWill be handed over to Corporation
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2NA00010
(2.)PM10NA00010
(3.)NOxNA00010
(4.)PM2.5NA00010
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG setHSD127.000.40Others--
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 5854.73
(b)Source Adani/Tata
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 3*1500 KVA
(e)Stack Height (in m) 120
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0.5
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0.5
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Plot area 0.5
    Total (ha.) 0.5000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area0.5Total construction area 62891.56 sqm
Total (ha.) 0.5
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA0NA
(2.)CorridorsNA0NA
(3.)Wildlife CorridorsNA0NA
(4.)ESAsNA0NA
(5.)ESZsSGNP1.50Out of notified ESZ
(6.)Critically Polluted AreaNA0NA
(7.)WLSNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0NA
(2.)ForestNA00
(3.)Defence InstallationsNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 12
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 50
(e)No. of working days 6
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.12
(b)Percentage of Total Project Area 24.00
(c)No. of Plants to be Planted 57
(d)Funds Allocated for Plantation 1067000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment generation for local people
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 119.625
(b)Total No. of Flats to be Build 311
(c)No. of Buildings 1
(d)Total plot area (sqm) 5000
(e)Total built up area (sqm) 62891.56
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 4
(d)Capacity 126
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 489
5.
Energy Saving Measures:
(a)Source/Mode Solar PV Cells, LED etc
(b)Percentage 16.25
(c)Quantity 758048
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area NA
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0073
(ii)Name of the EIA Consultant Enviro Analysts and Engineers Pvt. Ltd.
(iii)Address B-1003, Enviro House, 10th Floor. Western Edge II, Western Express Highway, Borivali (E), Mumbai-400 066.
(iv)Mobile No. 9321619749
(v)Landline No. 0222541647
(vi)Email Id info@eaepl.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 09 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease attach the followings to facilitate in screening 1. Feasibility report with concept plan. 2. Proper brief summary of the project 3. Monitoring data as collected may be filled up in relevant fields. 04 Oct 2020
2.NAThe correction have been made as per the instruction received 07 Oct 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterNA 06 Feb 2021
2.NAThis has reference to your above proposal, submitted to this Ministry for grant of Environmental Clearance (EC) in terms of the provisions of the Environment Impact Assessment (EIA) Notification, 2006 under the Environment (Protection) Act, 1986. 2. Your proposal, was considered by the Expert Appraisal Committee (Infra-2) in its 56th meeting held during 21-23 October, 2020. While processing the case as per the recommendations of the EAC, it has been observed from information provided by you for the proposal that the project site in question is at distance of 3KM due south from Thane Creek Flamingo Sanctuary (TCFS). The location of TCFS has been reported as water body in the presentation made to EAC. In the application form, it has been submitted that the proposal does not attract the provision of Wildlife (Protection) Act, 1972. 3. As on date, you have not submitted copy of acknowledgement to the effect that application seeking NBWL recommendations has been submitted. This is required as per the procedure notified by the Ministry vide OM No. 22-3/2018 dated 8th August, 2019. As per the aforesaid OM, proposals involving development activity / project located within 10 kilometers of National Park/Wildlife Sanctuary, wherein final ESZ notification is not notified, prior clearance Standing Committee of the National Board for Wildlife is mandatory. In such cases, the project proponent shall submit the application simultaneously for grant of TOR/ EC as well as wildlife clearance 4. Hence, you are requested to submit the acknowledgment to the effect that application seeking recommendations of National Board of Wild Life has been submitted. 03 Jan 2021
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantImtiaz Kanga
DesignationDirector
Name of Company (Applicant Name should not be given here)KALPATARU LIMITED
Address101, kalpataru synergy, opp Grand hyatt, santacruz east