Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion / Modernization of existing facilities of Godawari Power and Ispat Ltd.& subsequent Merger of various ECs
(b)Name of the Company / Organisation Godawari Power and Ispat Ltd
(c)Registered Address Plot No. 428/2, Phase-I, Industrial Area, Siltara, Raipur - 493111 (Chhattisgarh) ,Plot No. 428/2, Phase-I, Industrial Area, Siltara, Raipur - 493111 (Chhattisgarh) ,Raipur,Chhattisgarh-492001
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sanjay Srivastava
(b)Designation (Owner/ Partner/ CEO) Associate Vice President
(c)Address Plot No. 428/2, Phase-I, Industrial Area, Siltara, Raipur - 493111 (Chhattisgarh),,,Raipur,Chhattisgarh-493111
(d)Pin code 493111
(e)E-mail tonmoy.bose@hiragroup.com
(f)STD Code. 771(f)Telephone No. 4082333
(g)Fax No. 4082234
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/CG/IND/23490/2014
(d)Master Proposal Number(Single Window) SW/172771/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. 428/2, Phase-I
(b)Pincode 493211
(c)Bounded Latitudes (North)
From
Degree 212224.9
Minutes
Second
From
Degree 212238.7
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 814030.8
Minutes
Second
From
Degree 814113.0
Minutes
Second
(e)Survey of India Topo Sheet No. 64/G11, 64 G/15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 282
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4.5
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Chhattisgarh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)ChhattisgarhRaipurRaipur
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/216/2014-IA-II(I)
(c)Date of Issue of TOR 05 Nov 2014
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 30 Oct 2015
(c)Date of Issue of EC 07 Apr 2016
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :17 Jan 2020
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :17 Feb 2020
Distance of Public Hearing Venue from the Proposed Project :0.5
Tanda Ground (Adjacent to Project Site), Siltara Industrial Area Phase – I, Raipur (C.G.)
State :Chhattisgarh
District :Raipur
Tehsil :Raipur
Village :Tanda
400Employment, Development of Roads, Development of Education for Youth, Health Facilities, Pollution Control DevicesOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. EC-999/RON/209-NGP/7176
(iv)Status of Compliance Partially Complied
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 8 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Iron Ore Benificiation Plant100000022840003284000Tons per Annum(TPA)Road
(2.)Iron Ore Pelletization and coal gasification plant21000003000002400000Tons per Annum(TPA)Road,Rail
(3.)Steel Billets (SMS)400000300000700000Tons per Annum(TPA)Road
(4.)Power Plant73073Mega Watt(MW)OthersTransmission Line
(5.)HB Wire00100000100000Tons per Annum(TPA)Road
(6.)Replacement of Arc Furnace to Induction Furnace0050005000Tons per Annum(TPA)Road
(7.)Slag Crushing Plant00175000175000Tons per Annum(TPA)Road
(8.)Mineral Grinding Plant00200000200000Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Power Generation (AFBC/WHRB & Biomass Power Plant)73MW (28 MW+ 25 MW + 20 MW)Modernization by Installation of efficient TG set73 MW (48 MW + 25 MW)Replacement of three existing turbine with one new energy efficient Turbine of 48 MW
(2.)Oxygen Plant1200000 Nm3No change1200000 Nm3Operational
(3.)Nitrogen Plant4500000 Nm3No change4500000 Nm3Operational
(4.)Fly Ash Brick Plant16500000 Nos.No change16500000 Nos.Operation Discontinued
(5.)Steel Billet400000 TPAModernization and capacity enhancement700000 TPA (7Tx10, 12T x6, 15Tx6 & 30 Tx4)SMS is in operation to manufacture 400000 TPA Billets.
(6.)Ferro Alloys or Pig Iron16500 TPA or 33000 TPANo change16500 TPA or 33000 TPAOperational
(7.)H. B. Wire100000 TPA100000 TPA200000 TPAOperational
(8.)Oxygen Plant1200000 Nm3No change1200000 Nm3Operational
(9.)Iron Ore Beneficiation plant1000000 TPACapacity enhancement3284000 TPA1.0 MTPA Iron Ore Beneficiation Operational
(10.)Rolling Mill400000 TPANo change400000 TPAOperational
(11.)Arc Furnace5000 TPAProposed (To be revised to Induction Furnace)5000 TPANew Unit
(12.)Slag Crushing Plant-Proposed175000 TPANew Unit
(13.)Mineral Grinding Plant-Proposed200000 TPANew Unit
(14.)Iron Ore Pelletization Plants2100000 TPAProposed enhancement in production capacity2400000 TPA2.1MTPA Iron Ore Pelletization Plant with 60000Nm3/hr Coal gasifier plant.
(15.)Sponge Iron650000 TPANo change650000 TPA (1 x 350 TPD & 3 x 500 TPD Kilns)Plant is in operation for 495000 TPA, Applied for amendment in consent for 650000 TPA to CECB,Raipur
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 16 Jan 2020
(iv)Valid Upto 31 Oct 2020
(v)File No. 9249/TS/CECB/2020
(vi)Application No. 3339842
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 1988.87
(b) Funds Allocated for Environment Management (Capital) (in Crores) 3.4
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 4.0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.63
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3200000
(b)Existing quantity of raw material/fuel 1000000
(c)Total quantity of raw material/fuel 4200000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Silico Manganese10480Tons per AnnumOwn Source/ open marketRoad50 Open MarketCopy of Linkage
(2.)Ferro Manganese16.5Tons per AnnumPurchase from Open marketRoad300 Open MarketCopy of Linkage
(3.)Inoculants3.3Tons per AnnumPurchase from Open marketRoad300 Open MarketCopy of Linkage
(4.)Iron Ore Fines and Mill scale2496000Tons per AnnumOwn source or out sourceRoad160 OthersCaptive minesCopy of Linkage
(5.)Coal Dust15Tons per AnnumOwn Source/open marketRoad50 OthersOwn Source/ Open MarketCopy of Linkage
(6.)Iron Ore Fines (DRY including Return Fines) and Mill scale2288000Tons per AnnumOwn source/Out SourceRoad160 OthersCaptive Mines/Open marketCopy of Linkage
(7.)Sponge Iron760960Tons per AnnumOwn source / Purchase from Open marketRoad50 OthersInhouse & Open MarketCopy of Linkage
(8.)Coal for Sponge Iron650000Tons per AnnumPurchase from Open marketRoad,Rail200 OthersLinkage/ e-auction & open marketCopy of Linkage
(9.)Dolomite for Ferro Alloys/Pig Iron495Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(10.)Electrode Paste495Tons per AnnumPurchase from Open marketRoad300 Open MarketCopy of Linkage
(11.)Lime & Gypsum15000Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(12.)Steel Billets425500Tons per Annum--Others--0 Others--Copy of Linkage
(13.)Scrap92030Tons per AnnumPurchase from Open market/imported scrapRoad,Rail500 Open MarketCopy of Linkage
(14.)Coal113225Tons per AnnumCoal india and its subsidiaries/open marketRoad,Rail200 LinkageCopy of Linkage
(15.)Rice Husk167111Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(16.)Quartz1320Tons per AnnumPurchase from Open marketRoad500 Open MarketCopy of Linkage
(17.)Crushed Iron Ore3284000Tons per AnnumCaptive Mines & Open MarketRoad160 CaptiveCopy of Linkage
(18.)High Mn Slag6600Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(19.)Bentonite2.5Tons per AnnumPurchase from Open marketRoad1000 Open MarketCopy of Linkage
(20.)Lime Stone / Dolomite35200Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(21.)Fly ash70000Tons per AnnumOwn SourceRoad,Others--0 CaptiveCopy of Linkage
(22.)Dolomite19500Tons per AnnumPurchase from Open MarketRoad100 Open MarketCopy of Linkage
(23.)Coke/Steam coal9900Tons per AnnumPurchase from Open marketRoad500 Open MarketCopy of Linkage
(24.)PELLET942500Tons per AnnumOwn SourceOthers--0 CaptiveCopy of Linkage
(25.)Lime5954Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(26.)Calcined Lime5954Tons per AnnumOpen MarketRoad100 Open MarketCopy of Linkage
(27.)Manganese ore34650Tons per AnnumPurchase from MOIL / open market and importedRoad,Rail350 Open MarketCopy of Linkage
(28.)MS Item165Tons per AnnumPurchase from Open marketRoad500 Open MarketCopy of Linkage
(29.)Sand8000Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(30.)Bentonite/ Binder24000Tons per AnnumPurchase from Open marketRoad1000 Open MarketCopy of Linkage
(31.)Dolochar2678Tons per AnnumOwn SourceOthers--0 CaptiveCopy of Linkage
(32.)LDO2300OthersKillo LitersPurchase from Open marketRoad50 Open MarketCopy of Linkage
(33.)Coal for gasification system286364Tons per AnnumCoal india and its subsidiaries/open marketRoad,Rail160 Open MarketCopy of Linkage
(34.)Lancing Pipe50Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(35.)Steel Scrap & Borings2511Tons per AnnumPurchase from Open marketRoad500 Open MarketCopy of Linkage
(36.)Bentonite/ Binder22000Tons per AnnumPurchase from Open market Bhuj -GujaratRoad1500 Open MarketCaptive Mines/Open MarketCopy of Linkage
(37.)Silica Sand250Tons per AnnumPurchase from Open marketRoad700 Open MarketCopy of Linkage
(38.)Limestone/Dolomite38400Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(39.)Atmospheric Air416670Others--NAOthers--0 Others--Copy of Linkage
(40.)Pig Iron & Silicon277Tons per AnnumPurchase from Open marketRoad300 Open MarketCopy of Linkage
(41.)M.S. Wire Rods20300Tons per AnnumOwn Source/ Associate unitsRoad,Others--0 Captive--Copy of Linkage
(42.)Granulated Ferro Alloys Slag7000Tons per AnnumOwn SourceOthers--0 CaptiveCopy of Linkage
(43.)Ferro Silicon Magnesium10.5Tons per AnnumOwn SourceOthers--0 CaptiveCopy of Linkage
(44.)LDO2300OthersKillo LitersPurchase from Petroleum companies/open marketRoad50 Open MarketCopy of Linkage
(45.)Following Engineering Items, Steel (Plates, Pipe, Structures etc), Bearing, Gear Box, Motor, Tools and Tackles etc2550Tons per AnnumPurchase from Open marketRoad100 Open MarketCopy of Linkage
(46.)Magnetite Ore200000Tons per AnnumOwn SourceRoad160 OthersCaptive minesCopy of Linkage
(47.)Mineral Ore200000Tons per AnnumOwn source / Purchase from Open marketRoad,Rail160 OthersCaptive mines/Open marketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 15 Mar 2019 To 15 Jun 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube82.643.480.7100
(2.)SO2Micro Gram per Meter Cube40.215.337.380
(3.)NOxMicro Gram per Meter Cube45.416.844.680
(4.)PM2.5Micro Gram per Meter Cube45.623.445.060
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l474290300600
(2.)TDSmg/l6984065002000
(3.)pHNA7.87.16.58.5
(4.)Fluoridemg/l0.60.311.5
(5.)TSSmg/l5055
(6.)Chloridesmg/l189.540.32501000
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l22.40B
(2.)BODmg/l3.60B
(3.)DOmg/l6.84.9B
(4.)pHNA7.87.4A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.741.055
(2.)Leq(Night)A-weighted decibels(dB(A))50.439.745
    14.5.     No. of Soil Sample Monitored locations : 3
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Kilogram per hectare188.145.7
(2.)pH7.26.8
(3.)Electric ConductivityOthersmmhos/cm0.350.25
(4.)N(Nitrogen)Kilogram per hectare284103.8
(5.)P(Phosphorus)Kilogram per hectare27.37.1
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10.5 To 5.2
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.8 To 7.2
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface180007Copy of Permission LetterPipelineOthersPumpingL 38553616 Aug 201918000
(2.)GroundWater1700Copy of Permission LetterPipelineOthersBorewellCGWA/NOC/IND/ORIG/2019/487526 Feb 2019479
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic136136STPGreen Belt Renewal Plant136
(2.)Industrial10351035ETPReuse within the Plant & Recycling1035
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1171
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 1171
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Mill Scale (E +P)Industrial Waste14000Tons0Conveyor BeltOthersIn house utilization
(2.)Fly Ash (E+P)Industrial Waste85071Tons80RoadOthersMoU with Cement Industry
(3.)Slag(E+P)Industrial Waste175000Tons100RoadOthersIn house utilization & MoU with Cment Industry
(4.)Ash (Slinder) (E+P)Industrial Waste88200Tons80RoadOthersUtilization for brick manufacturing & Land filling
(5.)Tar (E+P)Industrial Waste17250Kilolitre100RoadOthersIn House & Sold authorised parties
(6.)Dust Collected through Sweeping MachineIndustrial Waste182.5Tons0OthersIn houseOthersIn house in pellet Plant
(7.)Waste Refractories (E+P)Industrial Waste400Tons100RoadOthersIn house and sold to other parties
(8.)STP SludgeIndustrial Waste3.5Tons0OthersIn HouseOthersUsed as Soil conditioner on site Plantation
(9.)Electrical (E+P)Industrial Waste0.25Tons50RoadOthersSold to scrap vendors
(10.)Wood Scrap (E+P)Industrial Waste1Tons0OthersIn HouseOthersreuse in usable wooden items.
(11.)Misc waste metal (E)Industrial Waste4000Tons0OthersIn HouseOthersUse in SMS
(12.)Biodegradable Waste (E+P)Municipal Solid Waste7.0Tons0OthersIn HouseOthersComposting
(13.)tailings (E+P)Industrial Waste644000Tons100RoadOthersMoU with UltraTech Cement Ltd.
(14.)Char & Dolochar (E)Industrial Waste130000Tons7RoadOthersUse in captive power Plant
(15.)Dust from S C & ESP Dust (E)Industrial Waste91000Tons50RoadOthersBrick, Road Making, land filling
(16.)Process ETP SludgeIndustrial Waste151Tons100RoadOthersDisposal Through CTSDF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube40.20.30.1040.3180
(2.)PM10Microgram per Meter Cube82.60.30.1082.70100
(3.)NOxMicrogram per Meter Cube45.41.00.0345.4480
(4.)PM2.5Microgram per Meter Cube45.60045.6160
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Pellet Plant (0.6 MTPA)Coal603.1PM104.86
(2.)SMSElectricity302PM100.78
(3.)Pellet Plant Unit (1.5 MTPA)Coal1006.1PM1010.56
(4.)Induction Furnace (5000 TPA) ProposedElectricity302PM100.01
(5.)SMS ProposedElectricity302PM100.6
(6.)Kiln 1 (WHRB 01+ AFBC 70 TPH)Coal & Waste Gases742.2PM101.89
(7.)Ferro Alloy FurnaceCoal352PM101.36
(8.)kiln 2 (WHRB 02 + AFBC 100 TPH)Coal & Waste Gases744.2PM103.49
(9.)Kiln 3( WHRB 03 + WHRB 04)Waste gases744.2PM103.52
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 142000
(b)Source 73 MW Captive Generation 25 MW from associate conc
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) Nil
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 79.351
(c)Government Land (ha.) 14.474
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 93.825
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 24697.18
(b)Waste/Barren Land (ha.) 4143.10
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 2012.08
(e)Settlements (ha.) 6835.49
(f)Industrial (ha.) 3431.27
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : nil 0
    Total (ha.) 41119.1200
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant18.574
(2.)OthersRoads & Open Area44.288
(3.)Green belt30.963
Total (ha.) 93.825
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsNone0Nil
(2.)CorridorsNone0Nil
(3.)NPANone0Nil
(4.)Critically Polluted AreaSiltara Industrial Area0Project site is in Critically Polluted area
(5.)WLSNone0Nil
(6.)ESAsNone0Nil
(7.)Wildlife CorridorsNone0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone0Nil
(2.)ForestNone0NA
(3.)Defence InstallationsNone0Nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 93.82
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kharoon River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 4.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 1940
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 1595
(e)No. of working days 330
(f)Total Manpower 3585
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt29.701.2630.96
(2.)Percentage of Total Project Area31.651.3533
(3.)No. of Plants73439750080939
(4.)Funds Allocated65000000200000067000000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialRevenue generation in the form of GST,IT and other taxes for State and Central Government.
(2.)SocialVarious developmental activities under CER & CSR to uplift the life of local villagers.
(3.)Environmental• Green Belt development inside and Outside plant • Rain Water Harvesting
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA0101
(ii)Name of the EIA Consultant Pollution & Ecology Control Services
(iii)Address Near Dhantoli Police Station, Dhantoli, Nagpur
(iv)Mobile No. 7720076427
(v)Landline No. 0712229322
(vi)Email Id pecs_nagpur@rediffmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 15 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NADuplicate proposal. Hence, it is returned. 18 Sep 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSanjay Srivastava
DesignationAssociate Vice President
Name of Company (Applicant Name should not be given here)Godawari Power and Ispat Ltd
AddressPlot No. 428/2, Phase-I, Industrial Area, Siltara, Raipur - 493111 (Chhattisgarh)