Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Development of LNG Terminal at Hazira, District Surat, Gujarat
(b)Name of the Company / Organisation ESSAR BULK TERMINAL LIMITED
(c)Registered Address 27th km, Surat Hazira Road, Hazira, Surat,,Chandigarh,Gujarat-394270
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant DAS SUBHAS
(b)Designation (Owner/ Partner/ CEO) CHIEF EXECUTIVE OFFICER
(c)Address 27th km, Surat Hazira Road, Hazira, Surat,,,Chandigarh,Gujarat-394270
(d)Pin code 394270
(e)E-mail Manoj.Sharma@essarport.co.in
(f)STD Code. 0(f)Telephone No. 6682171
(g)Fax No. 02616685544
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(e) Ports, Harbours
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/MIS/511/2011
(d)Master Proposal Number(Single Window) SW/172348/2020
(e)EAC concerned (for category A Projects only) INFRA-1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Not applicable (Project located mainly in water an
(b)Pincode 394270
(c)Bounded Latitudes (North)
From
Degree 21.079939
Minutes
Second
From
Degree 21.085536
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.656665
Minutes
Second
From
Degree 72.656779
Minutes
Second
(e)Survey of India Topo Sheet No. F43M12 and F43M16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 4.2
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 11-46/2011-IA.III
(c)Date of Issue of TOR 26 Sep 2011
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 06 Nov 2012
(c)Date of Issue of EC 06 May 2014
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :13 Aug 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :19 Sep 2019
Distance of Public Hearing Venue from the Proposed Project :2.5
Passenger Ferry Terminal Building, Essar Bulk Terminal Limited, 27th km, Surat – Hazira Road, Hazira Taluka Choryasi, District Surat, Gujarat.
State :Gujarat
District :Surat
Tehsil :Chorasi
Village :Hazira
173Corporate Environmental Responsibility (CER), Job Opportunities, Greenbelt Development, Regarding existing road towards Hazira Village, Regarding fishing activity & fishermenDistrict Collector
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. File no:6-6/2015(ENV)/173 dated 18.03.2019
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jul 20 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Liquefied Natural Gas (LNG)066OthersMMTPA (Million Metric Tonne Per Annum)Road,OthersSea and Pipeline
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)LNG Terminal0Land based Storage Unit, FSU and RULand based Storage Unit, FSU and RUNot a processing unit. Transit storage terminal
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 20 Oct 2015
(iv)Valid Upto 29 Jul 2020
(v)File No. AWH-73836
(vi)Application No. Inward Number 175928, dated 29.05.2020
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 2000
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 10
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.2325
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)0000Tons per AnnumNAOthersNA0 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 16 Oct 2017 To 15 Jan 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube1183198NAAQM
(2.)OthersO3Micro Gram per Meter Cube23.26.519NAAQM
(3.)PM2.5Micro Gram per Meter Cube581048NAAQM
(4.)SO2Micro Gram per Meter Cube134.211NAAQM
(5.)NOxMicro Gram per Meter Cube2212.720NAAQM
    14.2.     No. of Ground Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHOthers-8.157.148.58.5
(2.)TDSmg/l76204565002000
(3.)Total Hardnessmg/l1840130300600
(4.)Heavy MetalsCoppermg/l0.000.000.051.5
(5.)Fluoridemg/l1.330.241.01.5
(6.)Heavy MetalsManganesemg/l0.000.000.10.3
(7.)Chloridesmg/l32971392501000
(8.)TSSNA0.000.0000
(9.)Heavy MetalsIronmg/l0.110.090.31
    14.3.     No. of Surface Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODNA725C
(2.)DONA4.63.8C
(3.)BODNA2312C
(4.)pHNA8.337.42C
    14.4.     No. of Ambient Noise monitoring locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))66.454.8CPCB
(2.)Leq(Night)A-weighted decibels(dB(A))56.943.7CPCB
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH9.267.84
(2.)Electric ConductivityOthersMicro mho per cm0.650.32
(3.)N(Nitrogen)Percent0.110.06
(4.)K(Potassium)Othersgm/kg0.440.15
(5.)P(Phosphorus)Kilogram per hectare%0.060.02
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 4
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 4
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersExisting Power Plant547Copy of Permission LetterPipelineOthersPipelineNot Applicable11 Sep 201754
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic (on board FSU)44STPOthersUsed for landscaping40
(2.)Washing and Cleaning (On-board FSU)200Bilge water sent outsideOthersto authorized vendor020
(3.)Steam Turbine0.50.5STPOthersused for Landscaping0.50
(4.)Domestic (LNG Terminal Area)99STPOthersused for Landscaping90
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 33.5
(b)Total Discharged Water (Kilolitre per Day) 20
(c)Total Reused Water (Kilolitre per Day) 13.5
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5Kilolitre250RoadAuthorized Recyclers
(2.)Discarded Containers/Barrels/LinersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)300Tons250RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Cargo residue, sludge oil and washing waterHazardous Waste (as per Hazardous and Other Waste Management rules 2016)300Kilolitre250RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)Waste OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15Kilolitre250RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5NA0.000.00.10
(2.)PM10Microgram per Meter Cube951.740.0995.1100
(3.)NOxMicrogram per Meter Cube16.91.740.5517.4680
(4.)SO2Microgram per Meter Cube8.91.740.339.2480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 15.7
(b)Source Neighboring Power Plant
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) NA
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 17
    Total Land (ha.) 17
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 393.8
(b)Waste/Barren Land (ha.) 4727.1
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 3906.6
(e)Settlements (ha.) 429.6
(f)Industrial (ha.) 1875.0
(g)Forest (ha.) 70.9
(h)Mangroves (ha.) 541.9
(i)Marine Area (ha.) 16832.7
(j)Others (ha.) : Salt pan, Grass land, Jetty, Beach, Scrub, Airport 4776.4
    Total (ha.) 33554.0000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt5
(2.)Main Plant0.395Equipment (RU, BOG Compressors & facility)
(3.)OthersSTP, Tank farms, Utility, Road etc.9.005STP,Tank farms, Utility, Road etc.
Total (ha.) 14.4
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNA0-
(2.)CorridorsNA0-
(3.)WLSNA0-
(4.)NPANA0-
(5.)ESZsNA0-
(6.)Critically Polluted AreaNA0-
(7.)Wildlife CorridorsNA0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0-
(2.)ForestHazira Village1.70Reserve Forest
(3.)OthersUnprotectedDumas Village4.90Unprotected area
(4.)Defence InstallationsNA0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 195
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Pavo cristatus (Indian Peafowl) and Gyps indicus (Indian Vulture)
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made Yes
(iii)Period of Implementation 5 Years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area 4 Pond, 2 River estuary & 3 Creek
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 150
(d)Temporary Employment- During Operation 150
(e)No. of working days 350
(f)Total Manpower 400
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt4.859.8
(2.)Percentage of Total Project Area33.3334.7268.05
(3.)No. of Plants090009000
(4.)Funds Allocated024000002400000
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details
S. No.Item Details
1.
Project Details:
(a)CRZ Classification III
(b)Location Type Non-Eroding Coast
(c)Details of Mangroves Land Involved, if Any No
(d)Area of Mangroves Land (hectare) 0
(e)EIA (Terrestrial) Studies Carried Out
(i)Summary Details of EIA (Terrestrial) Studies Given as Chapter 11 in Terrestrial EIA Report
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Terrestrial) 16 Oct 2017
(iv)Period of Study To (EIA Terrestrial) 15 Jan 2018
(f)EIA (Marine) Studies Carried Out
(i)Summary Details of EIA (Marine) Studies Given as Chapter 8 in Marine EIA Report
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Marine) 01 Feb 2018
(iv)Period of Study to (EIA Marine) 28 Feb 2018
(g)Disaster Management Plan/National Oil Spill Disaster Contigency Plan Yes
2.
Description of the Project Under Consideration:
(a)Type of Project Others
(i)Agency Name for Preparing CRZ Maps Institute of Remote Sensing, Anna University (IRS)
(ii)Please Specify with salient features LNG Terminal
(iii)Uploaded relevent Document Copy of relevent Document
3.
Distance of Project (in meters) from ltl/htl to be stated :
(a)Clause of CRZ Notification Under which the Project is a Permissible/Regulated Activity III
(b)Whether CRZ Map Indicating HTL,LTL Demarcation in 1:4000 Scale Prepared? Yes
(i)Distance of Project (in meters) from HTL to be Stated 0
(ii)Uploaded Maps(Shape File) Copy of Maps
(iii)Distance of Project(in meters) from LTL to be Stated 32.17
(iv)Uploaded Maps(Shape File) Copy of Maps
(c)Whether Project Layout Superimposed on CRZ Map 1:4000 Scale ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(d)Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(e)Whether CRZ Map Indicating CRZ-I,II,III and IV Including Other Notified ESAs Prepared Yes
(i)Uploaded Maps (kml File) Copy of Maps
(f)NOC from State Pollution Control Boards Obtained No
(g)Details of Rain Water Harvesting System
4.
Recommendation of State Coastal Zone Management Authority:
(a)Copy of CZMA Copy of CZMA
(b)State the Conditions Imposed Six Specific Conditions by GCZMA, as mentioned in
(c)Social and Environmental Issues and Mitigations Measures Suggested Including but not Limited to R&R, Water, Air, Hazardous Wastes, Ecological aspects, etc. (Brief Details to be Provided) Provided in Terrestrial EIA Report
   35.   Sector Specific Details For INFRA-1
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 10
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 7
(d)Total plot area (sqm) 170000
(e)Total built up area (sqm) 2110
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? Yes
(b)Upload Shoreline Study Copy of Shoreline stuudy
(c)Type of Cargo LNG
(d)Quantity of Cargo 13
(e)Control Measures of Cargo Safety, Air pollution, spill control
(f)Dust Control Measures Water sprinkling, well maintained road and traffic
(g)Quantum 6
(h)Quantity of Dredging (Cubic meter per day) 0
(i)Type of Dredging Maintenance
(j)Disposal of Dredge Material Not applicable as dredging is not involved
(k)Details of Outfall Diffusers Not Applicable
(l)No. of Dilution Expected 0
(m)Distance at which the Outlet will Reach Ambient Parameters 0
(n)Details of Monitoring at Outfall 0
(o)Copy of NoC from PCB in case of Marine Disposal Copy of NoC
3.
Rain Water Harvesting:
(a)No. of Storage 4
(b)Capacity 500
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking parking will be provided within the promises
5.
Energy Saving Measures:
(a)Source/Mode shall be identified after energy audit
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area No impact as drainage pattern of the study area
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA0138
(ii)Name of the EIA Consultant Kadam Environmental Consultants
(iii)Address 871/B/3, GIDC Makarpura, Vadodara, India – 390 010
(iv)Mobile No. 9714861611
(v)Landline No. 2656131000
(vi)Email Id kadam@kadamenviro.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-1
(ix)Validity of Accreditation 25 May 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterRecommendation letter issued by GCZMA 15 Oct 2020
2.NAplease submit the recommendation letter issued by GCZMA. 15 Oct 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDAS SUBHAS
DesignationCHIEF EXECUTIVE OFFICER
Name of Company (Applicant Name should not be given here)ESSAR BULK TERMINAL LIMITED
Address27th km, Surat Hazira Road, Hazira, Surat