1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Residential Complex M2K Victoria Gardens
(b)Name of the Company / Organisation NEGOLICE INDIA LIMITED
(c)Registered Address E-34, 2nd Floor, Connaught Circus, New Delhi,,Central,Delhi-110001
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant SatishPal Singh
(b)Designation (Owner/ Partner/ CEO) VicePresident
(c)Address E-34, 2nd Floor, Connaught Circus, New Delhi,,Pahar Ganj,Central,Delhi-110001
(d)Pin code 110001
(e)E-mail rajesh.kumar@m2kindia.com
(f)STD Code. 11(f)Telephone No. 48486000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(b) Townships and Area Development projects.
Minor Activity8(b) Townships and Area Development projects.
(b)Category B1
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/DL/MIS/170497/2019
(d)Master Proposal Number(Single Window) SW/170495/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Azadpur, Delhi
(b)Pincode 110052
(c)Bounded Latitudes (North)
From
Degree 3177264.75
Minutes
Second
From
Degree 3177476.81
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 712604.63
Minutes
Second
From
Degree 712845.69
Minutes
Second
(e)Survey of India Topo Sheet No. H43X2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 220
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1.45
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Delhi
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number F. No. 21-99/2020-IA.III
(c)Date of Issue of TOR 01 Jan 1900
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 26 Nov 2020
(c)Date of Issue of EC 13 Jan 2021
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As per EIA Notification 2006 and its amendment, all building construction projects are exempted from public hearing
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. 4-294/07/651
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Oct 23 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Total Plot are1.837274401.8372744Hectares(ha)OthersNA
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)No. of Apartments476150488-
(2.)EWS Units270155287-
(3.)No. of blocks718-
(4.)Ground Coverage (m2)5504.02586.846090.86
(5.)FAR (Proposed in m2)57871.2928939.9386811.215-
(6.)FAR ( Proposed for EWS in m2)8382.054639.63213021.682
(7.)Built-up Area (m2)100352.0272503.59172855.618-
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 13 Feb 2017
(iv)Valid Upto 30 Sep 2020
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 85
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.74
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.85
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.065
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)..0OthersNA-OthersNA0 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2019 To 31 Dec 2019
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube320193.6305.6100
(2.)PM2.5Micro Gram per Meter Cube124.185.6118.260
(3.)SO2Micro Gram per Meter Cube20.89.219.880
(4.)NOxMicro Gram per Meter Cube67.527.057.980
(5.)OthersCOMili Gram per Meter Cube2.00.81.72
    14.2.     No. of Ground Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.57.16.58.5
(2.)Heavy MetalsSeleniummg/l0.010.010.010.01
(3.)Total Hardnessmg/l460180200200
(4.)TSSmg/l12.08.400
(5.)Fluoridemg/l1.00.21.01.0
(6.)Chloridesmg/l350.080.0250.0250.0
(7.)TDSmg/l1204219.3500500
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.26.8E
(2.)BODmg/l2412E
(3.)OthersTSSmg/l11014.8E
(4.)DOmg/l4.23.2E
(5.)CODmg/l17632E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))63.654.865
(2.)Leq(Night)A-weighted decibels(dB(A))58.945.155
    14.5.     No. of Soil Sample Monitored locations : 7
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityMillisiemens per Centimetre412.6280.3
(2.)K(Potassium)Milligram per Kilogram61.232.6
(3.)N(Nitrogen)Milligram per Kilogram75.661.6
(4.)pH8.17.6
(5.)P(Phosphorus)Milligram per Kilogram15.212.2
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 16.32 To 2.23
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.32 To 17.1
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersDJB Supply3061.0Copy of Permission LetterPipelineOtherspipelinebill no. 1237031096220 Aug 2020310
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic,flushing,cooling,pool,filterbackwash382460STPReuse within the Plant & Recycling,Green Belt Renewal Plant,Otherslosses of 39 KLD178204
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 382
(b)Total Discharged Water (Kilolitre per Day) 204
(c)Total Reused Water (Kilolitre per Day) 178
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Bio degradable wasteMunicipal Solid Waste313Tons0.9RoadOthersOrganic waste converter
(2.)Plastic wastePlastic Waste104Tons1.0RoadAuthorized Recyclers
(3.)Non-biodegradable wasteMunicipal Solid Waste105Tons1.0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube16.40.90.0816.4980
(2.)PM10Microgram per Meter Cube265.10.90.02265.13100
(3.)PM2.5Microgram per Meter Cube100.10.90.01100.1260
(4.)NOxMicrogram per Meter Cube48.90.90.0248.9380
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG set of 3(1 standby)x1500 kVA & 1x500 kVALow Sulphur diesel300.3OthersPM2.50.05
(2.)DG set of 3(1 standby)x1500 kVA & 1x500 kVALow Sulphur Diesel300.3SO20.18
(3.)DG of 3(1 standby)x1500 kVA & 1x500 kVALow Sulphur diesel300.3NOx0.28
(4.)DG set of capacity 3 (1standby)x1500 kVA & 500 kVALow Sulphur Diesel300.3PM100.05
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2568.6
(b)Source Tata Power Delhi Distribution Limited
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 3x (1 standby)1500 kVA & 1x500 kVA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 1.83727
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1.83727
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 5085.64
(b)Waste/Barren Land (ha.) 84.30
(c)Grazing/ Community Land (ha.) 220.09
(d)Surface Water Bodies (ha.) 1026.28
(e)Settlements (ha.) 24228.53
(f)Industrial (ha.) 0
(g)Forest (ha.) 1219.3
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : - 0
    Total (ha.) 31864.1400
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Othersplot area1.83727plot area
Total (ha.) 1.83727
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaWazirpur1.42SW direction from the project site
(2.)WLSNone0NA
(3.)Wildlife CorridorsNone0NA
(4.)ESZsNone0NA
(5.)NPANone0NA
(6.)ESAsNone0NA
(7.)CorridorsNone0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsIndian Air Force Head Quarter10.88SSE direction from the project site
(2.)ForestNorthern Ridge Reserve Forest4.07SEE direction from the project site
(3.)Archaeological SitesSalimgarh Fort8.1SEE direction from the project site
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 8
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.83
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Pavo cristatus
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Pond near Model Town
(ii)Direction of Water Bodies in Buffer Area North East
(iii)Distance of Water Bodies in Buffer Area 1.36
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 300
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 400
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt5472.18776.576248.75
(2.)Percentage of Total Project Area29.784.2334.010000000000005
(3.)No. of Plants57930609
(4.)Funds Allocated29010300
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment will be generated
(2.)FinancialRevenue will be generated
(3.)EnvironmentalPlantation of trees all around the project periphery including avenue plantation will be carried out
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 235
(b)Total No. of Flats to be Build 775
(c)No. of Buildings 8
(d)Total plot area (sqm) 18372.744
(e)Total built up area (sqm) 172855.618
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 3
(d)Capacity 168
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 1804
5.
Energy Saving Measures:
(a)Source/Mode LED/Solar
(b)Percentage 1
(c)Quantity 25.686
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area There will be no extraction of ground water
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Rev 04, 10th November. 2020 at S.No-120.)
(ii)Name of the EIA Consultant Perfact Enviro Solutions Pvt. Ltd.
(iii)Address 5th Floor, NN Mall, Sector 3, Rohini, New Delhi, 110085
(iv)Mobile No. 9818362330
(v)Landline No. 0114928136
(vi)Email Id info@perfactgroup.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 03 Dec 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAUpon examination of your application, following points needs to be address with relevant documents; (i) Please submit with valid accreditation certificate of EIA consultant as being found to be expired on 08.09.2020. (ii) Entries under s.no. 9 (c) of form-2 in the field titled existing configuration may be rectified by providing the data w.r.t. actual construction that has been completed as on date. (iii) Vetting of non compliance/partially compliance as given in report of Regional Office dated 20.01.2020 against the Action Taken Report of project proponent is required for disposal of show cause notice for further consideration of application. 11 Sep 2020
2.NAThe correction have been made as per the instruction received 11 Sep 2020
3.NAConsideration of application is subject to compliance of TOR’s condition no.15, which was issued on 06.08.2020. Please resubmit application upon fulfillment of the condition. 05 Oct 2020
4.NAThe correction have been made as per the instruction received 26 Nov 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSatishPal Singh
DesignationVicePresident
Name of Company (Applicant Name should not be given here)NEGOLICE INDIA LIMITED
AddressE-34, 2nd Floor, Connaught Circus, New Delhi
Print