Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Improvement & Upgradation of Kathgodam - Ranibagh - Bheemtal - Khutani - Padampur - Dhanachauli - Pahadpani - Shahar Phatak - Mornola - Devidhura - Lohaghat – Pancheswar road section of SH-10 under Uttarakhand State Highway Improvement Project (USHIP)
(b)Name of the Company / Organisation PUBLIC WORKES DEPARTMENT UTTARAKHAND ADB CIRCLE PITHORAGARH
(c)Registered Address ADB Circle Office Pithoragarh, Near PWD Store,Collectorate Road, Takana,Pithoragarh,Uttarakhand-262501
(d)Legal Status of the Company State Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Arun Kumar Goyel
(b)Designation (Owner/ Partner/ CEO) SE
(c)Address ADB Circle Pithoragarh Near PWD Store,Colectorate Road, Takana,Pithoragarh,Pithoragarh,Uttarakhand-262501
(d)Pin code 262501
(e)E-mail sepmgsy@yahoo.com
(f)STD Code. 5964(f)Telephone No. 227591
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(f) Highways
Minor Activity
(b)Category A
(c)Proposal Number IA/UK/MIS/170151/2020
(d)Master Proposal Number(Single Window) SW/170131/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. The project road start at Ranibagh near Kathgodam
(b)Pincode 263126
(c)Bounded Latitudes (North)
From
Degree 29.291197
Minutes
Second
From
Degree 29.449876
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 79.545058
Minutes
Second
From
Degree 80.221027
Minutes
Second
(e)Survey of India Topo Sheet No. H44N11 and H44N15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 2150
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttarakhand
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The project proponent has applied for scoping / approval of ToR for EIA study vide letter no. 262/2019 dated 17th July 2019. MoEF&CC vide EDS dated 8th August 2019 replied, “As per EIA Notification, 2006 as amended from time to time, the all highway expansion projects in border states do not require scoping. Further such projects are exempted from public hearing. Hence, apply directly for grant of Environmental Clearance as per provisions contained in the said Notification.”
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)0N/AN/A
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)N/A0Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 1506.20
(b) Funds Allocated for Environment Management (Capital) (in Crores) 17.90
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.76
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.0388
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3280065.21
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 3280065.21
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)cement206495.26OthersMTNearby project areaRoad10 LinkageCopy of Linkage
(2.)Steel45937.63OthersMTNearby project areaRoad10 LinkageCopy of Linkage
(3.)Emulsion1386.81OthersMTNearby project areaRoad10 LinkageCopy of Linkage
(4.)Soil/Gravel1347616.16OtherscumNearby project areaRoad10 MoUCopy of Linkage
(5.)GSB287109.80OthersMTNearby project areaRoad10 LinkageCopy of Linkage
(6.)Sand403023.70OthersMTMine quarryRoad10 MoUCopy of Linkage
(7.)Bitumen8537.63OthersMTNearby project areaRoad10 LinkageCopy of Linkage
(8.)Aggregate979958.22OthersMTNearby project areaRoad10 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube16.210.214.880
(2.)PM10Micro Gram per Meter Cube70.647.168.5100
(3.)PM2.5Micro Gram per Meter Cube35.122.933.260
(4.)OthersCOMicro Gram per Meter Cube7603807584000
(5.)SO2Micro Gram per Meter Cube7.15.16.580
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l4402605002000
(2.)TSSmg/l5500
(3.)Chloridesmg/l21.920.62501000
(4.)Fluoridemg/l0.640.6011.5
(5.)Total Hardnessmg/l372223200600
(6.)Heavy MetalsFemg/l0.190.180.30.3
(7.)pHNA7.126.956.58.5
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA6.856.76C
(2.)DOmg/l6.76.5C
(3.)BODmg/l2.82.5C
(4.)CODmg/l5.55.0C
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))55.845.165
(2.)Leq(Night)A-weighted decibels(dB(A))41.136.155
    14.5.     No. of Soil Sample Monitored locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milligram per Kilogram450298
(2.)pH8.47.2
(3.)P(Phosphorus)Milligram per Kilogram321290
(4.)N(Nitrogen)Milligram per Kilogram0.410.18
(5.)Electric ConductivityOthersmicros/cm132129
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.04 To 91.43
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.64 To 88.43
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface11001Copy of Permission LetterPipelineIntake WellNA28 Aug 20200
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)NA00NAGreen Belt Renewal Plant0
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)MuckConstruction & Demolition Waste2700630Kilolitre0RoadOthersApproved muck disposal sites
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube35.102.737.8160
(2.)SO2Microgram per Meter Cube7.1007.1180
(3.)PM10Microgram per Meter Cube70.605.175.7100
(4.)NOxMicrogram per Meter Cube16.20016.2180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)N/A000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source NA
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) NA
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 126.67
(b)Private Land (ha.) 26.44
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 153.11
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 10.64
(b)Waste/Barren Land (ha.) 2.42
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0.92
(e)Settlements (ha.) 4.33
(f)Industrial (ha.) 0
(g)Forest (ha.) 126.67
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Private 8.13
    Total (ha.) 153.1100
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersRoad construction activity153.11Road construction activity
Total (ha.) 153.11
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaN/A0N/A
(2.)NPAN/A0N/A
(3.)ESAsN/A0N/A
(4.)WLSN/A0N/A
(5.)ESZsN/A0N/A
(6.)CorridorsN/A0N/A
(7.)Wildlife CorridorsN/A0N/A
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesN/A0N/A
(2.)ForestRF, Van Panchayat, Civil and Soyam0N/A
(3.)Defence InstallationsN/A0N/A
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 51955
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 153.11
(c)Status of Land acquisition if not acquired Under process
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 54
(b)No. of Households 1265
(c)No. of PDFs (Project Displaced Families) 524
(d)No. of PAFs (Project Affected Families) 1265
(e)Funds Allocated for R&R(in INR) (in Lacs) 11808
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Panthera pardus and Ursus thibetanus
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 7 Lakhs
(iii)Period of Implementation 5 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 4 rivers, 1 Lake , 4 streams
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 25
(b)Permanent Employment-During Operation 25
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 50
(e)No. of working days 365
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Total Area of Green Belt 126.67
(b)Percentage of Total Project Area 82.73
(c)No. of Plants to be Planted 126670
(d)Funds Allocated for Plantation 42687790
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 0
5.
Energy Saving Measures:
(a)Source/Mode N/A
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area 0.92 ha
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment 177.211
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
(a)Total No. of Bridges 8
(b)Total No. of ROB 0
(c)Total No. of Interchanges 0
(d)Total No. of Flyovers 0
(e)Total No. of Vehicle Underpass 0
(f)Total No. of Pedestrian Underpass 0
(g)Details of other utilities rail and road corridors 1278 cross drainage structures
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA 0157
(ii)Name of the EIA Consultant Enviro Infra Solutions Pvt. Ltd.
(iii)Address 301, 302, SRBC, Sector 9, Vasundhara, Ghaziabad - 201012 (U.P.)
(iv)Mobile No. 9818922344
(v)Landline No. 4151183
(vi)Email Id eis@enviroinfrasolutions.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 13 Nov 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NA

EAC after detailed deliberation during its 243rd meeting held during 28th – 29th September, 2020, observed that the EIA report is inadequate in various aspects like the ecology of the area, the portion of the unconnected section of road, survey of alignment etc. The committee thus deferred the proposal for want of following information

1.      A detailed study of flora and fauna along the proposed alignment to be done by reputed institute like WII or SACON or Zoological Survey of India or other such nationally reputed institutes

2.      Details about impact of road construction on landslides, natural streams, vegetation needs to be studied.

3.      Details on the impact on hydrology of the area to be undertaken by reputed institute.

14 Oct 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantArun Kumar Goyel
DesignationSE
Name of Company (Applicant Name should not be given here)PUBLIC WORKES DEPARTMENT UTTARAKHAND ADB CIRCLE PITHORAGARH
AddressADB Circle Office Pithoragarh, Near PWD Store