EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/KA/IND2/27470/2015    ii. MoEFCC File No. : J-11011/94/2015-IA-II(I)    iii.Short narrative of the project: NSL Sugars Limited    iv. Project Sector : Industrial Projects-2    v. Company/Proponent : NSL SUGARS LIMITED
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.KarnatakaMandyaMaddur
 
vii. Uploaded EC Compliance report by rigional office of MoEFCC: NIL viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report    ix.Date of TOR Granted 29 Jul 2015 x.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 03 May 2016 x.Project Type: Expansion
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 29 Jul 2015   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAPP should provide detailed implementation plan (PERT and CPM Chart) of the existing distillery and proposed distillery unit. After deliberation, the Committee sought following additional information: i. Detailed execution schedule plan for the existing distillery (grain based) and proposed molasses based distillery. ii. Revised water requirement for sugar unit, distillery unit and cogeneration power plant. iii. Water conservation methods to reduce water requirement. iv. Scheme for treatment of spent wash. Quantity of spent wash to be used for incineration mode and bio-composting mode. The proposal was deferred till the desired information is submitted. The above information shall be provided through online with the uploading of minutes on the website. 03 Aug 2016
2. ADS LetterWE ARE HERE WITH ATTACHING REPLY TO THE CLARIFICATIONS ISSUED BY EAC 03 Aug 2016
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 121    iii. Name of Consultant: Pioneer Enviro Laboratories and Consultants Private Limited   iv. Address : Hyderabad   v. Mobile No.: 9440677333   vi. Landline No.: 04023314270   vii. Email Id: nslsugars@nslsugars.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : M.R.NAIK    ii. Designation : Sr. Vice President    iii. Name of Company(Applicant Name should not be given here) : NSL SUGARS LIMITED    iv. Address : NSL ICON | 4th Floor| # 8-2-684/2/A | Road No. 12 | Banjara Hills | Hyderabad - 500 034 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL
Print