1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Proposed Synthetic Organic Manufacturing Plant at Additional Patalganga MIDC, Plot No. E-127, Tal.- Khalapur, Dist.- Raigad, Maharashtra by “SMT Organic Chemicals Pvt. Ltd.” | (b)Name of the Company / Organisation | SMT ORGANICS CHEMICAL PRIVATE LIMITED | (c)Registered Address | A-204, Amar Gian Complex, LBS Marg Khopat,Thane West,Thane,Maharashtra-400601 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Ashok Saraf | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Plot No. E-127, Additional Patalganga MIDC,Taluka Khalapur Dist. Raigad,Khalapur,Raigad,Maharashtra-410220 | (d)Pin code | 410220 | (e)E-mail | smtorganics@gmail.com | (f)STD Code. | 22(f)Telephone No. | 41128000 | (g)Fax No. | 21720036 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/MH/IND2/53584/2016 | (d)Master Proposal Number(Single Window) | SW/167822/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | E-127, Additional Patalganga MIDC, Tal. Khalapur, | (b)Pincode | 410220 | (c)Bounded Latitudes (North) | | From | | Degree | 18.854501 | Minutes | | Second | | From | | Degree | 18.855331 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 73.162466 | Minutes | | Second | | From | | Degree | 73.162702 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 47F1, 47F5 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 30 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.95 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Raigad | Khalapur | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | J-11011/145/2016- IA II(I) | (b)Date of Apply of TOR | 09 May 2016 | (c)Date of Issue of TOR / Standard ToR | 11 May 2017 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | The project is in MIDC Area | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Plot Area | 3997.00 | sq.m. | (2.) | Explosive Yard | 389.75 | sq.m. | (3.) | Total Built up area | 1266.30 | sq.m. | (4.) | Green Belt Area (33% of Total Plot Area) | 1320.00 | sq.m. | (5.) | Net Plot Area | 3607.25 | sq.m. | (6.) | Parking Area | 384.79 | sq.m. | (7.) | Open Area | 636.16 | sq.m. | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Formaldehyde (37% to 55% Concentration) and | 36000 | Tons per Annum | | Road | | (2.) | Phenol Formaldehyde Liquid resin | 86747 | Tons per Annum | | Road | | (3.) | Phenol Formaldehyde Powder resin | 43374 | Tons per Annum | | Road | | (4.) | Urea Formaldehyde and Melamine Formaldehyde Liquid Resin | 31304 | Tons per Annum | | Road | | (5.) | Urea Formaldehyde and Melamine Formaldehyde Powder Resin | 15652 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 01 Aug 2020 | (iv)Valid Upto | 31 Jul 2021 | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 15.5 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 1.43 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.31 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.22 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | a)Protected areas notified under the wildlife (Protection) Act, 1972 | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 360187 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 360187 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Urea | 23882 | Tons per Annum | | Local Market | Road | | 40 | Open Market | | Copy of Linkage | (2.) | MF resin liquid | 31304 | Tons per Annum | | Pipe line | Pipe Conveyor | | 40 | Open Market | | Copy of Linkage | (3.) | Methanol | 45010 | Tons per Annum | | Local Market | Road | | 40 | Open Market | | Copy of Linkage | (4.) | Caustic Soda | 14659 | Tons per Annum | | Local Market | Road | | 40 | Open Market | | Copy of Linkage | (5.) | Formic Acid | 6 | Tons per Annum | | Local Market | Road | | 40 | Open Market | | Copy of Linkage | (6.) | Phenol | 18390 | Tons per Annum | | Local Market | Road | | 40 | Open Market | | Copy of Linkage | (7.) | Formaldehyde | 72000 | Tons per Annum | | Pipe line from Formaldehyde plant | Pipe Conveyor | | 40 | Fuel Supply Agreement | | Copy of Linkage | (8.) | Melamine | 25043 | Tons per Annum | | Local Market | Road | | 40 | Open Market | | Copy of Linkage | (9.) | UF resin liquid | 31304 | Tons per Annum | | Pipe line | Pipe Conveyor | | 40 | Open Market | | Copy of Linkage | (10.) | Phenol Formaldehyde Resin | 98589 | Tons per Annum | | Local Market | Road | | 40 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2019 To 31 Dec 2019 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 55.7 | 31.9 | 46.3 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 23.5 | 9.4 | 18.5 | 80 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 22.8 | 10.7 | 19.6 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 20.2 | 5.7 | 15.1 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Chlorides | | | mg/l | | 59.13 | 39.42 | 250 | 1000 | (2.) | Total Hardness | | | mg/l | | 188.15 | 116.09 | 200 | 600 | (3.) | pH | | | NA | | 7.61 | 7.24 | 8.5 | 8.5 | (4.) | TSS | | | mg/l | | 0 | 0 | 500 | 2000 | (5.) | TDS | | | mg/l | | 485 | 280 | 500 | 2000 | (6.) | Fluoride | | | mg/l | | 0 | 0 | 1 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 4.9 | 4.3 | A | (2.) | pH | | NA | | 7.48 | 7.42 | E | (3.) | BOD | | mg/l | | 7 | 4 | B | (4.) | COD | | mg/l | | 31 | 17 | E | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 53.6 | 50.2 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 48.6 | 39 | 70 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 8.27 | 8.03 | (2.) | N(Nitrogen) | Kilogram per hectare | | 127.2 | 100.88 | (3.) | P(Phosphorus) | Kilogram per hectare | | 16.1 | 8.75 | (4.) | Electric Conductivity | Millisiemens per Centimetre | | 901.4 | 648.5 | (5.) | K(Potassium) | Kilogram per hectare | | 172.1 | 150.7 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 5 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2 To 5 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | MIDC Supply | 305 | 1 | Copy of Permission Letter | Pipeline | | Others | MIDC Water Supply | NA | 01 Aug 2020 | 305 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Industrial Waste Water | 17.85 | 18 | ETP cum STP followed by MEE to achieve ZLD | Reuse within the Plant & Recycling,Green Belt Renewal Plant | | 17.85 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 17.85 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 17.85 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Spent Oil/ Used Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.36 | Kilolitre | 5 | Road | | Authorized Recyclers | | (2.) | ETP Sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 600 | Tons | 27 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | Wastes/ Residue containing oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 2.4 | Tons | 5 | Road | | Authorized Recyclers | | (4.) | Spent Resin | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 36 | Kilolitre | 5 | Road | | Authorized Recyclers | | (5.) | Old Catalysts | Industrial Waste | | 0.6 | Tons | 0 | Road | | Co-Processing | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 22.8 | 0.1 | 0.00 | 22.9 | 60 | (2.) | NOx | | Microgram per Meter Cube | 23.5 | 0.1 | 0.58 | 24.09 | 80 | (3.) | PM10 | | Microgram per Meter Cube | 49.5 | 0.1 | 0.00 | 49.6 | 100 | (4.) | SO2 | | Microgram per Meter Cube | 20.2 | 0.1 | 0.43 | 20.64 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 5 TPH Boiler | Furnace Oil | 48 | 0.6 | PM10 | | 0.00078 | (2.) | DG Set (1000 kVA) | Diesel | 10 | 0.3 | PM10 | | 1.09 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1112.5 | (b)Source | MSEDCL | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 1000 kVA | (e)Stack Height (in m) | 10 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0.3997 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 0.3997 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 3450 | (b)Waste/Barren Land (ha.) | 1820 | (c)Grazing/ Community Land (ha.) | 6770 | (d)Surface Water Bodies (ha.) | 370 | (e)Settlements (ha.) | 7490 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 11500 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : NA | 0 | Total (ha.) | 31400.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Built Up Area | | 1266.3 | | (2.) | Green belt | | 1320 | | (3.) | Others | Road, Parking, Explosive Yard, etc. | 1410.7 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | Karnala Bird Sanctuary | 2.3 | Project is located at 2.3 km from Karnala Bird Sanctuary | (2.) | NPA | NA | 0 | NA | (3.) | ESAs | NA | 0 | NA | (4.) | Critically Polluted Area | NA | 0 | NA | (5.) | ESZs | NA | 0 | NA | (6.) | Corridors | NA | 0 | NA | (7.) | Wildlife Corridors | NA | 0 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NA | 0 | NA | (2.) | Forest | | Protected Forest | 2.3 | Project is located at 2.3 km from Karnala Bird Sanctuary | (3.) | Defence Installations | | NA | 0 | NA | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0.39 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Not Applicable as land is already in possession | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | | (b)No. of Households | | (c)No. of PDFs (Project Displaced Families) | | (d)No. of PAFs (Project Affected Families) | | (e)Funds Allocated for R&R(in INR) (in Lacs) | | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Leopard, Monitor Lizard, Indian Python, Indian Peacock and Mouse Deer. | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 10 lakh | (iii)Period of Implementation | 2 years | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 50 | (b)Permanent Employment-During Operation | 20 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 365 | (f)Total Manpower | 70 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.14 | (b)Percentage of Total Project Area | 35.03 | (c)No. of Plants to be Planted | 213 | (d)Funds Allocated for Plantation | 2000000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | The proposed project is expected to yield a positive impact on the surrounding environment. It will help in sustainable development of this area including further development of physical Infrastructural facilities. It will recharge the groundwater by rain-harvesting, the road structure will be repaired, massive greening drive will improve the aesthetics and generally the land prices will go up. The road connectivity will get improved due to the industry. This improved physical infrastructure wil | (2.) | Social | Project will definitely open an avenue for the young generation of our nation by generating employment to more than 50 local rural persons in construction phase and around 20 local persons in operation phase. Company will be hiring the local residents nearby project site for employment, as per their competency. This will create employment to these people and thereby will improve their living standard. The proposed project is already located in MIDC area so area development will be as per MIDC, w | (3.) | Financial | The industry is established in the rural region of the state. The establishment of industry will provide direct and indirect employment. Major part of these labors will be mainly from local villagers who are expected to engage themselves both in agriculture and project activities. This will enhance their income and lead to overall economic growth of the area. It helps to sustain the development of this area including further development of physical infrastructural facilities. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/RA 0075 | (ii)Name of the EIA Consultant | MITCON Consultancy & Engineering Services Ltd. | (iii)Address | Environment Management and Engineering Division, Agriculture College Campus, Shivajinagar, Pune 411005. | (iv)Mobile No. | 9665043400 | (v)Landline No. | 0206628940 | (vi)Email Id | eme@mitconindia.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 22 Sep 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | 1. Details of NBWL Clearance has not mentioned in the Form 2 as the WLS is 2.3 km from proposed Unit.
2. Details of plant facility as per Form-2 of S. No. 7not uploaded, Request to upload the same in Form 2 w.r.t. industrial Estate document.
3. Details of documents related to PH exemption as per Form-2 of S. No. 8 not mentioned, Request to upload the same in Form 2.
4.
5. PP in form 2 (S.No. 26) has not adequately mentioned the details of Land acquisition. Everything mentioned Zero. Please provide the details of land and usage.
6. PP in form 2 (S.No. 27) has not adequately mentioned the details of R&R. Everything mentioned NA.
7. Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2)
8. PP submitted very less incremental value for PM10 & PM2.5 &SOx., please check. Air Quality Impact Prediction mentioned (18.1 of form 2) is inadequate kindly check and correct it accordingly.
9. It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. | 29 Sep 2020 | 2. | NA | The correction have been made as per the instruction received | 08 Oct 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Ashok Saraf | Designation | Director | Name of Company (Applicant Name should not be given here) | SMT ORGANICS CHEMICAL PRIVATE LIMITED | Address | A-204, Amar Gian Complex, LBS Marg Khopat |
|