Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Onshore Oil and Gas Development Drilling and Production Involving Onshore drilling of 179 wells, production facilities and laying of assorted oil & gas flowlines/delivery lines in District Tinsukia (Assam)
(b)Name of the Company / Organisation OIL INDIA LIMITED
(c)Registered Address OIL INDIA LIMITED DULIAJAN District : Dibrugarh ,,Dibrugarh,Assam-786602
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ajit Chandra Haloi
(b)Designation (Owner/ Partner/ CEO) CGM(HSE)
(c)Address Safety & Environment Department , Oil India Limited, Duliajan,,,Dibrugarh,Assam-786602
(d)Pin code 786602
(e)E-mail safety@oilindia.in
(f)STD Code. 374(f)Telephone No. 2800542
(g)Fax No. 03742801796
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(b) Offshore and onshore oil and gas exploration, development & production
Minor Activity8(a) Building and Construction projects
(b)Category A
(c)Proposal Number IA/AS/IND2/165606/2007
(d)Master Proposal Number(Single Window) SW/165470/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. N Hapjan Dhola - 2
(b)Pincode 786151
(c)Bounded Latitudes (North)
From
Degree 27.442856
Minutes
Second
From
Degree 27.635214
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 95.333333
Minutes
Second
From
Degree 95.533953
Minutes
Second
(e)Survey of India Topo Sheet No. 83M6, 83M7, 83M10, 83M11
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 144
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Assam
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/375/2016-IA II (I)
(c)Date of Issue of TOR 08 Sep 2017
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 07 Aug 2020
(c)Date of Issue of EC 28 Dec 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :10 Feb 2020
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :12 Mar 2020
Distance of Public Hearing Venue from the Proposed Project :1
Public/ Community Hall, Baghjan TE
State :Assam
District :Tinsukia
Tehsil :Doom Dooma
Village :Baghjan
146• Pollution control- soil, air and noise pollution; vehicular pollution, management of wastes released from drill sites etc. • Protection of DSNP and Maguri Beel areas from pollution • Plantation inOthersAdditional Deputy Commissioner
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Shillong
(iii)Letter No. RO-NE/E/IA/AS/MI/59/169-71
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 13 2016 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)179 wells and 9 production installations41179220OthersNo of wellsOthersWell Drilling
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)179 wells and 9 production installations41179220
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 16 Oct 2019
(iv)Valid Upto 15 Sep 2020
(v)File No. S&E/E/20/1613
(vi)Application No. S&E/E/20/1613
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 3500
(b) Funds Allocated for Environment Management (Capital) (in Crores) 4.41
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 8.77
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5.01
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3.5
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 3.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)diesel3.5Kilo Litre per DayLocal supplierRoad50 Othersthrough supplierCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 04 Oct 2017 To 30 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube74257260
(2.)NOxMicro Gram per Meter Cube29.612.227.9780
(3.)OthersCOMili Gram per Meter Cube0.850.150.762
(4.)PM10Micro Gram per Meter Cube13652134100
(5.)SO2Micro Gram per Meter Cube8.64.27.580
    14.2.     No. of Ground Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l27122501000
(2.)TSSOthersNot Analyzed0000
(3.)Heavy MetalsTotal Chromiummg/l0.010.010.050.05
(4.)pHOthersNo Unit7.46.56.58.5
(5.)TDSmg/l114405002000
(6.)Total Hardnessmg/l7616200600
(7.)Fluoridemg/l0.10.111.5
(8.)OthersMagnesiummg/l110.9630100
    14.3.     No. of Surface Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l22A
(2.)pHOthersNo Unit7.176.65A
(3.)DOmg/l8.87.6A
(4.)CODmg/l124A
(5.)OthersTotal ColiformOthersMPN/ 100ml17023B
    14.4.     No. of Ambient Noise monitoring locations : 24
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))47.5339.545
(2.)Leq(Day)A-weighted decibels(dB(A))58.151.155
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNo Unit6.274.94
(2.)K(Potassium)Milligram per Kilogram11513
(3.)P(Phosphorus)Milligram per Kilogram103
(4.)N(Nitrogen)Milligram per Kilogram347224
(5.)Electric ConductivityMillisiemens per Centimetre8523
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.68 To 4.5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater400Copy of Permission LettermodeOthersWell at siteOthersBore well21-4/1186/AS/MIN/202008 Jul 202040
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic wastewater88Soak PitOthersReused at Site80
(2.)Drilling and Wash wastewater13.815Effluent Treatment PlantOthersReused at Site13.80
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 21.8
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 21.8
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Drill CuttingsIndustrial Waste836Tons0OthersDisposed at HDPE lined pits within siteOthersDisposed at HDPE lined pits within site
(2.)Waste Drilling MudIndustrial Waste1920Tons0OthersDisposed at HDPE lined pits within siteOthersDisposed at HDPE lined pits within site
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube24.191.412.1336.3380
(2.)SO2Microgram per Meter Cube6.181.420.436.6280
(3.)PM10Microgram per Meter Cube89.51.40.0689.57100
(4.)PM2.5Microgram per Meter Cube480048.0160
(5.)Others(Specify)Total HydrocarbonMicrogram per Meter Cube763.361.420.08763.450
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetDiesel70.3NOx1.836
(2.)DG SetDiesel70.3OthersHydrocarbon0.004
(3.)DG SetDiesel70.3PM100.007
(4.)DG SetDiesel70.3SO20.039
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1250
(b)Source Diesel Generator Set
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1250
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 600
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 600
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 7401
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1471
(e)Settlements (ha.) 6620
(f)Industrial (ha.) 64
(g)Forest (ha.) 2121
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Tea Garden, Marshy Land, Road Network, Railway Tra 21324
    Total (ha.) 39001.0000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersWells and production installation600
Total (ha.) 600
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNone10No ESA within 10 km
(2.)Wildlife CorridorsNone10No wildlife corridors within 10 km
(3.)Critically Polluted AreaNone10No critically polluted area within 10 km
(4.)CorridorsNone10No corridors within 10 km
(5.)WLSBherjan-Borajan-Padumoni1Wildlife clearance application for the wells and production facilities will be submitted
(6.)NPADibru Saikhowa National Park1Distance from nearest proposed well
(7.)ESZsDibru Saikhowa National Park0.1Distance of nearest proposed well from Notified ecosensitive zone of Dibru Saikhowa National Park
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone10No archaeological sites within 10 km
(2.)ForestDibru Saikhowa NP and Bherjan Borjan Padumoni WLS1Dibru Saikhowa NP and Bherjan Borjan Padumoni WLS located 1 km from nearest proposed well
(3.)Defence InstallationsNone10No major defense installations within 10 km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? Yes
(i)Status of NBWL NIL
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 600
(c)Status of Land acquisition if not acquired In process
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species 35 Schedule-1 species
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 1.21 crore
(iii)Period of Implementation 7 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Maguri Motapung Wetlands within the Block
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Brahmaputra River
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 0.9
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 20
(b)Permanent Employment-During Operation 40
(c)Temporary Employment- During Construction 80
(d)Temporary Employment- During Operation 40
(e)No. of working days 120
(f)Total Manpower 180
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt015.7515.75
(2.)Percentage of Total Project Area02.632.63
(3.)No. of Plants02520025200
(4.)Funds Allocated015.7515.75
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalContributing to Forest Departments habitat improvement program Capacity building of forest department staffs Awareness Generation Meetings at villages Engaging a NGO for Identification of Hoolock Gibbon and Vulture Roosting sites. Ecological survey in Maguri Beel area Plantation at DSNP through Forest Department, at abandoned drill sites, along the pipeline routes, at Tea Gardens
(2.)Social• Development activities- improvement of infrastructure in schools, road repair, provision of ambulance, fund for hospital development, fund for college development, provision of streetlights; fund for flood protection • Programs related to livelihood generation, health improvement as per OIL’s Corporate Environmental Responsibility (CER) programmes.
(3.)FinancialProvision of more royalty to Assam Government and more cess to Govt. of India Energy security for the country
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1618/RA 0055
(ii)Name of the EIA Consultant ERM India Pvt. Ltd.
(iii)Address Building 10, Tower A, 4th Floor, DLF Cyber City Gurgaon 122002
(iv)Mobile No. 9810295449
(v)Landline No. 0124411703
(vi)Email Id sushil.handa@erm.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 26 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterReply to ADS is attached 28 Oct 2020
2.NA

 

The Committee during deliberations noted that the project proponent has uploaded the certified compliance of the existing status of the EC conditions issued by the Ministry’s Regional Office vide letter dated  5th July, 2016. The certified report has very serious observations against the ongoing projects and reported serious non-compliance by the PP. It was observed by the regional office that the PP has started development and production of the wells without obtaining prior environmental clearance.  The Committee after detailed deliberations desired for following additional information/inputs in respect of the following:

(i). Action taken report on non-complied points to be forwarded by the Ministry’s Regional Office.

(ii) Justification, if any, for start of development/production of wells without prior environmental clearance.

(iii)  Details of existing NBWL permission and status of NBWL clearance for the proposed project.

(iv)Public hearing issues, response and detailed action plan

 

The proposal was therefor DEFERRED for the needful.

30 Sep 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAjit Chandra Haloi
DesignationCGM(HSE)
Name of Company (Applicant Name should not be given here)OIL INDIA LIMITED
AddressOIL INDIA LIMITED DULIAJAN District : Dibrugarh
Print