Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) PROPOSED EXPANSION OF SPECIALITY CHEMICALS, AGROCHEMICALS, AGROCHEMICAL INTERMEDIATES IN EXISTING UNIT(2500 MT/Month)
(b)Name of the Company / Organisation Hemani Intermediates Pvt. Ltd.
(c)Registered Address Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Bharuch,Madhya Pradesh-393002
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant D N Rai
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Vagra,Bharuch,Madhya Pradesh-393002
(d)Pin code 393002
(e)E-mail hr3.1@hemanigroup.com
(f)STD Code. 0(f)Telephone No. 626 195
(g)Fax No. 650 627
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/62687/2017
(d)Master Proposal Number(Single Window) SW/164221/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. 3208, Ankleshwar Industrial Area, Dist: B
(b)Pincode 393002
(c)Bounded Latitudes (North)
From
Degree 73.028
Minutes
Second
From
Degree 73.029
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 21.623
Minutes
Second
From
Degree 21.625
Minutes
Second
(e)Survey of India Topo Sheet No. F43N2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 21
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 10
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratBharuchAnklesvar
(2.)GujaratBharuchAnklesvar
(3.)OrissaSundargarhHemgirSiarmal,Tumulia
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number IA-J-11011/111/2017-IA-II(I)]
(c)Date of Issue of TOR 31 May 2017
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 07 Dec 2017
(c)Date of Issue of EC 15 Mar 2018
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Located In GIDC Area, Ankleshwar
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on
(iii)Letter No. IA-J-11011/111/2017-IA-II(I)
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Apr 20 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Meta Phenoxy Benzaldehyde600006000Tons per Annum(TPA)Road
(2.)1R Trans CMA Synthetic60000600Tons per Annum(TPA)Road
(3.)Diflubenzron036003600Tons per Annum(TPA)Road
(4.)4- Fluoro Meta Phenoxy Benzaldehyde012001200Tons per Annum(TPA)Road
(5.)chlorantraniliprole036003600Tons per Annum(TPA)Road
(6.)Methyl Chloride01200012000Tons per Annum(TPA)Road
(7.)Lambda cyhalothrin36024002760Tons per Annum(TPA)Road
(8.)Diflubenil018001800Tons per Annum(TPA)Road
(9.)Diflubam018001800Tons per Annum(TPA)Road
(10.)Lambda Acid036003600Tons per Annum(TPA)Road
(11.)Insecticides - Liquid based products (Formulation)360003600Tons per Annum(TPA)Road
(12.)Herbicides- Liquid based products (Formulation)2400002400Tons per Annum(TPA)Road
(13.)Fungicides - Liquid based products (Formulation)240002400Tons per Annum(TPA)Road
(14.)1R Trans CMA Synthetic - Catalyst1200120Tons per Annum(TPA)Road
(15.)Poly alluminium chloride03789637896Tons per Annum(TPA)Road
(16.)Bromo Nitro Benzene30000300Tons per Annum(TPA)Road
(17.)Meta Bromo Anisole3000300Tons per Annum(TPA)Road
(18.)Bifenthrin Technical0024002400Tons per Annum(TPA)Road
(19.)Profenophos024002400Tons per Annum(TPA)Road
(20.)Meta Phenoxy Benzaldehyde Alcohol120001200Tons per Annum(TPA)Road
(21.)Dichlobenil060006000Tons per Annum(TPA)Road
(22.)Bifenthrin Alcohol012001200Tons per Annum(TPA)Road
(23.)Insecticides - Solid based products (Formulation)120001200Tons per Annum(TPA)Road
(24.)Herbicides - Solid based products (Formulation)1200001200Tons per Annum(TPA)Road
(25.)Fungicides - Solid based products(Formulation)120001200Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Filter Press(24”× 24”)1Nos01Nos
(2.)Steam Boiler(25TPH)01Nos1Nos
(3.)Drawing Vessels(40KL)1Nos3Nos4Nos
(4.)Solvent Storage Tank(20KL)01Nos1Nos
(5.)Air Compressor(10CFM)1Nos1Nos2Nos
(6.)Steam Boiler(17 TPH)2Nos02Nos
(7.)Weight Balance(100Kg)1Nos1Nos2Nos
(8.)Thermopack Boiler(4Lac Kcal)01Nos1Nos
(9.)Weight Balance(1000Kg)01Nos1Nos
(10.)Stainless Steel 316 and 316L Reactor(10KL)04Nos4Nos
(11.)Ball Mill(5KL)1Nos1Nos2Nos
(12.)HCL Tank (15KL)1Nos2Nos3Nos
(13.)Blender(30KL)1Nos1Nos2Nos
(14.)Glass line reactor(15KL)1Nos7Nos8Nos
(15.)Drawing Scrubber Vessel(15KL)1Nos01 Nos
(16.)Caustic Storage Tank(20KL)01Nos1Nos
(17.)Filter Press(48”× 48”)2Nos10Nos12Nos
(18.)Distillation Vessel(30 KL)1Nos5Nos6Nos
(19.)Vinyl ester lining(5KL)1Nos3Nos4Nos
(20.)Cooling Tower(250TR)1Nos1Nos2Nos
(21.)Reslurry Vessel(15KL)02 Nos2Nos
(22.)Thermopack Boiler(6Lac Kcal)2Nos02Nos
(23.)Separator(800 Lts)1Nos8Nos9Nos
(24.)Spin Flash Dryer(500 Kg/Hr)02Nos2Nos
(25.)Condenser(50 SPM)1Nos5Nos6Nos
(26.)Receiver Tank(10KL)1Nos8Nos9Nos
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 24 Jun 2019
(iv)Valid Upto 06 May 2024
(v)File No. AWH-102463
(vi)Application No. 156497
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 30
(b) Funds Allocated for Environment Management (Capital) (in Crores) 4.470
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.66
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5.02
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3500
(b)Existing quantity of raw material/fuel 1740
(c)Total quantity of raw material/fuel 5240
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Pyridine1324.8Tons per Annumlocal marketRoad15 Open MarketCopy of Linkage
(2.)Soda Ash3.96Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(3.)ALCL37200Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(4.)HCL (30%)5250Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(5.)Acid Chloride219.96Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(6.)Chlorine gas3096Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(7.)Methanol210Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(8.)Hydrogen Gas1560Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(9.)Chlorine1590Tons per Annumlocal marketRoad5 Open MarketCopy of Linkage
(10.)Lambdacyhalothric Acid604.8Tons per Annumlocal marketRoad15 Open MarketCopy of Linkage
(11.)H2SO4 (98%)390Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(12.)Benzaldehyde4980Tons per Annumlocal marketRoad17 Open MarketCopy of Linkage
(13.)Thionyl Chloride111Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(14.)Toluene300Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(15.)Formic Acid138Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(16.)Phenol4410Tons per Annumlocal marketRoad15 Open MarketCopy of Linkage
(17.)Bromine4050Tons per Annumlocal marketRoad10 Open MarketCopy of Linkage
(18.)KOH2700Tons per Annumlocal marketRoad15 Open MarketCopy of Linkage
(19.)Acetic acid2004Tons per Annumlocal marketRoad15 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube28.5319.982880
(2.)PM10Micro Gram per Meter Cube96.1276.6396100
(3.)PM2.5Micro Gram per Meter Cube58.1045.105860
(4.)SO2Micro Gram per Meter Cube26.7216.432680
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Fluoridemg/l0011.5
(2.)Chloridesmg/l549.76622501000
(3.)TSSmg/l32880120
(4.)TDSmg/l21601825002000
(5.)pHNA8.346.786.58.5
(6.)Heavy MetalsZincmg/l00515
(7.)Total Hardnessmg/l866.6460200600
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l00A
(2.)CODmg/l2.462.46A
(3.)pHNA7.487.48A
(4.)DOmg/l5.805.80A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))544555
(2.)Leq(Night)A-weighted decibels(dB(A))444245
    14.5.     No. of Soil Sample Monitored locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milligram per Kilogram721326.9
(2.)pH7.997.21
(3.)Electric ConductivityMillisiemens per Centimetre5.081.38
(4.)P(Phosphorus)Milligram per Kilogram89.5715.9
(5.)N(Nitrogen)Milligram per Kilogram164.598.5
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 30
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 20
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface20705Copy of Permission LetterPipelineOthersGIDC water supplyUnit has applied for the permission09 Jan 20192070
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic2225Septic tankOthersSeptic tank220
(2.)Industrial10402035ETP, Stripper, MEE, CondenateOthersDeep Sea disposal through GIDC Pipeline325715
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1062
(b)Total Discharged Water (Kilolitre per Day) 715
(c)Total Reused Water (Kilolitre per Day) 347
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Dil. HCLIndustrial Waste37200Tons19RoadOthersSold out to actual end user
(2.)Sodium romideIndustrial Waste660Tons10RoadOthersSold out to actual end user
(3.)ETP sludge and MEE SaltIndustrial Waste12000Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)NaclIndustrial Waste1380Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Aqueous sol. aluminium chloride(By product)Industrial Waste35448Tons56RoadOthersSold out to actual end user
(6.)Cucl2Industrial Waste8736Tons60RoadOthersSold out to actual end user
(7.)Spent NSSIndustrial Waste710.4Tons60RoadOthersSold out to actual end user
(8.)Residue & wasteIndustrial Waste4764Tons20RoadOthersCo processing or Incineration
(9.)Discarded BagsIndustrial Waste36Tons10RoadOtherssold to authorized vendors
(10.)Incineration AshIndustrial Waste120Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(11.)Nacl+Cucl 80% wetIndustrial Waste4800Tons60RoadOthersSold out to actual end user
(12.)KFIndustrial Waste1500Tons60RoadOthersSold out to actual end user
(13.)Copper hydroxideIndustrial Waste120Tons64RoadOthersSold out to actual end user
(14.)Used oilIndustrial Waste0.96Kilolitre70RoadOtherssent to registered recycler
(15.)Distillation ResidueIndustrial Waste2400Tons19RoadCo-Processing
(16.)H2SO4(By product)Industrial Waste2424Tons60RoadOthersSold to actual end users /Reused
(17.)Potassium chloride (20% sol.) By productIndustrial Waste16200Tons60RoadOthersSold out to actual end user
(18.)Poly aluminium chlorideIndustrial Waste41520Tons60RoadOthersSold out to actual end user
(19.)Discarded containerIndustrial Waste4380Tons10RoadOtherssold to authorized vendors
(20.)Sodium bisulfiteIndustrial Waste1200Tons54RoadOthersSold out to actual end user
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube26.722.730.0226.7580
(2.)PM10Microgram per Meter Cube96.122.730.0196.14100
(3.)PM2.5Microgram per Meter Cube58.102.730.0158.1260
(4.)NOxMicrogram per Meter Cube28.532.730.028.5480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Steam Boiler(10TPH)Coal501OthersSPM SO2 Nox150,262,94
(2.)D.G.Set(1010KVA)Diesel120.2OthersSPM SO2 Nox150,262,94
(3.)Steam Boiler (7TPH)Coal501OthersSPM SO2 Nox150,262,94
(4.)Incinerator-I-301OthersSPM, HCL150,20
(5.)Thermic fluid heater(4Lac Kcal)Natural gas501OthersSPM SO2 Nox150,100,94
(6.)Incinerator-II--301OthersSPM HCL150,20
(7.)D.G.Set(1010KVA)Diesel120.2OthersSPM SO2 Nox150,262,94
(8.)Steam Boiler (25TPH)Coal501OthersSPM SO2 Nox150,262,94
(9.)Thermic fluid heater(6Lac Kcal)-IINatural gas501OthersSPM SO2 Nox150,262,94
(10.)Thermic fluid heater(6 lac kcal)-INatural gas501OthersSPM SO2 Nox150,262,94
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 5000
(b)Source DGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1010KVA
(e)Stack Height (in m) 12
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 3.3570
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 3.3570
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 2.293
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0.1167
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0.3592
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Scrub land, Residential Area, Mud Flats 0.38
    Total (ha.) 3.1489
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt0.6700
(2.)Main Plant2.687
Total (ha.) 3.357
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsNA0--
(2.)Critically Polluted AreaAnkleshvar4--
(3.)WLSNA0--
(4.)ESAsNA0--
(5.)NPANA0--
(6.)CorridorsNA0--
(7.)Wildlife CorridorsNA0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNA0--
(2.)ForestNA0--
(3.)Archaeological SitesNA0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 3.35
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Presence of 10 schedule-1 species
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 10.225 Lakh
(iii)Period of Implementation 2 year
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 25
(b)Permanent Employment-During Operation 15
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 5
(e)No. of working days 350
(f)Total Manpower 50
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt0.6700.67
(2.)Percentage of Total Project Area40040
(3.)No. of Plants140001400
(4.)Funds Allocated420000004200000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreen Belt, New Plantation on Barren Land
(2.)SocialGeneration of employment, Social Economic Up Gradation
(3.)FinancialUpgrade stander of living, Market will be uplift Financial Up Gradation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay Order Against NABET/QCI
(ii)Name of the EIA Consultant Aqua Air Environmental Engineers Pvt. Ltd.
(iii)Address 403, CENTER POINT, NR. KADIWALA SCHOOL, RING ROAD, SURAT – 395002 (GUJ.) INDIA
(iv)Mobile No. 8155016995
(v)Landline No. 0261246085
(vi)Email Id aqua_eia@yahoo.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 03 Mar 2016
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NA

 

The Committee noted that PP was absent and no documents w.r.t. presentation and others as per agenda was forwarded to the Committee and accordingly Committee could not deliberate the proposal and therefore the proposal was deferred and may be placed after the request of PP.

01 Sep 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantD N Rai
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)Hemani Intermediates Pvt. Ltd.
AddressPlot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT
Print