1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | PROPOSED EXPANSION OF SPECIALITY CHEMICALS, AGROCHEMICALS, AGROCHEMICAL INTERMEDIATES IN EXISTING UNIT(2500 MT/Month) | (b)Name of the Company / Organisation | Hemani Intermediates Pvt. Ltd. | (c)Registered Address | Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Bharuch,Madhya Pradesh-393002 | (d)Legal Status of the Company | Others | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | D N Rai | (b)Designation (Owner/ Partner/ CEO) | General Manager | (c)Address | Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT,Vagra,Bharuch,Madhya Pradesh-393002 | (d)Pin code | 393002 | (e)E-mail | hr3.1@hemanigroup.com | (f)STD Code. | 0(f)Telephone No. | 626 195 | (g)Fax No. | 650 627 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(b) Pesticides industry and pesticide specific intermediates (excluding formulations) 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/GJ/IND2/62687/2017 | (d)Master Proposal Number(Single Window) | SW/164221/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot No. 3208, Ankleshwar Industrial Area, Dist: B | (b)Pincode | 393002 | (c)Bounded Latitudes (North) | | From | | Degree | 73.028 | Minutes | | Second | | From | | Degree | 73.029 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 21.623 | Minutes | | Second | | From | | Degree | 21.625 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43N2 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 21 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 10 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Gujarat | Bharuch | Anklesvar | | (2.) | Gujarat | Bharuch | Anklesvar | | (3.) | Orissa | Sundargarh | Hemgir | Siarmal,Tumulia | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | IA-J-11011/111/2017-IA-II(I)] | (c)Date of Issue of TOR | 31 May 2017 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 07 Dec 2017 | (c)Date of Issue of EC | 15 Mar 2018 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | Located In GIDC Area, Ankleshwar | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | SPCB | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | | (iii)Letter No. | IA-J-11011/111/2017-IA-II(I) | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Apr 20 2020 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Meta Phenoxy Benzaldehyde | 6000 | 0 | 6000 | Tons per Annum(TPA) | | Road | | (2.) | 1R Trans CMA Synthetic | 600 | 00 | 600 | Tons per Annum(TPA) | | Road | | (3.) | Diflubenzron | 0 | 3600 | 3600 | Tons per Annum(TPA) | | Road | | (4.) | 4- Fluoro Meta Phenoxy Benzaldehyde | 0 | 1200 | 1200 | Tons per Annum(TPA) | | Road | | (5.) | chlorantraniliprole | 0 | 3600 | 3600 | Tons per Annum(TPA) | | Road | | (6.) | Methyl Chloride | 0 | 12000 | 12000 | Tons per Annum(TPA) | | Road | | (7.) | Lambda cyhalothrin | 360 | 2400 | 2760 | Tons per Annum(TPA) | | Road | | (8.) | Diflubenil | 0 | 1800 | 1800 | Tons per Annum(TPA) | | Road | | (9.) | Diflubam | 0 | 1800 | 1800 | Tons per Annum(TPA) | | Road | | (10.) | Lambda Acid | 0 | 3600 | 3600 | Tons per Annum(TPA) | | Road | | (11.) | Insecticides - Liquid based products (Formulation) | 3600 | 0 | 3600 | Tons per Annum(TPA) | | Road | | (12.) | Herbicides- Liquid based products (Formulation) | 2400 | 00 | 2400 | Tons per Annum(TPA) | | Road | | (13.) | Fungicides - Liquid based products (Formulation) | 2400 | 0 | 2400 | Tons per Annum(TPA) | | Road | | (14.) | 1R Trans CMA Synthetic - Catalyst | 120 | 0 | 120 | Tons per Annum(TPA) | | Road | | (15.) | Poly alluminium chloride | 0 | 37896 | 37896 | Tons per Annum(TPA) | | Road | | (16.) | Bromo Nitro Benzene | 300 | 00 | 300 | Tons per Annum(TPA) | | Road | | (17.) | Meta Bromo Anisole | 300 | 0 | 300 | Tons per Annum(TPA) | | Road | | (18.) | Bifenthrin Technical | 00 | 2400 | 2400 | Tons per Annum(TPA) | | Road | | (19.) | Profenophos | 0 | 2400 | 2400 | Tons per Annum(TPA) | | Road | | (20.) | Meta Phenoxy Benzaldehyde Alcohol | 1200 | 0 | 1200 | Tons per Annum(TPA) | | Road | | (21.) | Dichlobenil | 0 | 6000 | 6000 | Tons per Annum(TPA) | | Road | | (22.) | Bifenthrin Alcohol | 0 | 1200 | 1200 | Tons per Annum(TPA) | | Road | | (23.) | Insecticides - Solid based products (Formulation) | 1200 | 0 | 1200 | Tons per Annum(TPA) | | Road | | (24.) | Herbicides - Solid based products (Formulation) | 1200 | 00 | 1200 | Tons per Annum(TPA) | | Road | | (25.) | Fungicides - Solid based products(Formulation) | 1200 | 0 | 1200 | Tons per Annum(TPA) | | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Filter Press(24”× 24”) | 1Nos | 0 | 1Nos | | (2.) | Steam Boiler(25TPH) | 0 | 1Nos | 1Nos | | (3.) | Drawing Vessels(40KL) | 1Nos | 3Nos | 4Nos | | (4.) | Solvent Storage Tank(20KL) | 0 | 1Nos | 1Nos | | (5.) | Air Compressor(10CFM) | 1Nos | 1Nos | 2Nos | | (6.) | Steam Boiler(17 TPH) | 2Nos | 0 | 2Nos | | (7.) | Weight Balance(100Kg) | 1Nos | 1Nos | 2Nos | | (8.) | Thermopack Boiler(4Lac Kcal) | 0 | 1Nos | 1Nos | | (9.) | Weight Balance(1000Kg) | 0 | 1Nos | 1Nos | | (10.) | Stainless Steel 316 and 316L Reactor(10KL) | 0 | 4Nos | 4Nos | | (11.) | Ball Mill(5KL) | 1Nos | 1Nos | 2Nos | | (12.) | HCL Tank (15KL) | 1Nos | 2Nos | 3Nos | | (13.) | Blender(30KL) | 1Nos | 1Nos | 2Nos | | (14.) | Glass line reactor(15KL) | 1Nos | 7Nos | 8Nos | | (15.) | Drawing Scrubber Vessel(15KL) | 1Nos | 0 | 1 Nos | | (16.) | Caustic Storage Tank(20KL) | 0 | 1Nos | 1Nos | | (17.) | Filter Press(48”× 48”) | 2Nos | 10Nos | 12Nos | | (18.) | Distillation Vessel(30 KL) | 1Nos | 5Nos | 6Nos | | (19.) | Vinyl ester lining(5KL) | 1Nos | 3Nos | 4Nos | | (20.) | Cooling Tower(250TR) | 1Nos | 1Nos | 2Nos | | (21.) | Reslurry Vessel(15KL) | 0 | 2 Nos | 2Nos | | (22.) | Thermopack Boiler(6Lac Kcal) | 2Nos | 0 | 2Nos | | (23.) | Separator(800 Lts) | 1Nos | 8Nos | 9Nos | | (24.) | Spin Flash Dryer(500 Kg/Hr) | 0 | 2Nos | 2Nos | | (25.) | Condenser(50 SPM) | 1Nos | 5Nos | 6Nos | | (26.) | Receiver Tank(10KL) | 1Nos | 8Nos | 9Nos | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 24 Jun 2019 | (iv)Valid Upto | 06 May 2024 | (v)File No. | AWH-102463 | (vi)Application No. | 156497 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 30 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 4.470 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.66 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 5.02 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 3500 | (b)Existing quantity of raw material/fuel | 1740 | (c)Total quantity of raw material/fuel | 5240 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Pyridine | 1324.8 | Tons per Annum | | local market | Road | | 15 | Open Market | | Copy of Linkage | (2.) | Soda Ash | 3.96 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (3.) | ALCL3 | 7200 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (4.) | HCL (30%) | 5250 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (5.) | Acid Chloride | 219.96 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (6.) | Chlorine gas | 3096 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (7.) | Methanol | 210 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (8.) | Hydrogen Gas | 1560 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (9.) | Chlorine | 1590 | Tons per Annum | | local market | Road | | 5 | Open Market | | Copy of Linkage | (10.) | Lambdacyhalothric Acid | 604.8 | Tons per Annum | | local market | Road | | 15 | Open Market | | Copy of Linkage | (11.) | H2SO4 (98%) | 390 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (12.) | Benzaldehyde | 4980 | Tons per Annum | | local market | Road | | 17 | Open Market | | Copy of Linkage | (13.) | Thionyl Chloride | 111 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (14.) | Toluene | 300 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (15.) | Formic Acid | 138 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (16.) | Phenol | 4410 | Tons per Annum | | local market | Road | | 15 | Open Market | | Copy of Linkage | (17.) | Bromine | 4050 | Tons per Annum | | local market | Road | | 10 | Open Market | | Copy of Linkage | (18.) | KOH | 2700 | Tons per Annum | | local market | Road | | 15 | Open Market | | Copy of Linkage | (19.) | Acetic acid | 2004 | Tons per Annum | | local market | Road | | 15 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2019 To 31 May 2019 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 9 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | NOx | | Micro Gram per Meter Cube | 28.53 | 19.98 | 28 | 80 | (2.) | PM10 | | Micro Gram per Meter Cube | 96.12 | 76.63 | 96 | 100 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 58.10 | 45.10 | 58 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 26.72 | 16.43 | 26 | 80 | |
14.2. No. of Ground Water monitoring locations : 9 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Fluoride | | | mg/l | | 0 | 0 | 1 | 1.5 | (2.) | Chlorides | | | mg/l | | 549.76 | 62 | 250 | 1000 | (3.) | TSS | | | mg/l | | 32 | 8 | 80 | 120 | (4.) | TDS | | | mg/l | | 2160 | 182 | 500 | 2000 | (5.) | pH | | | NA | | 8.34 | 6.78 | 6.5 | 8.5 | (6.) | Heavy Metals | | Zinc | mg/l | | 0 | 0 | 5 | 15 | (7.) | Total Hardness | | | mg/l | | 866.64 | 60 | 200 | 600 | |
14.3. No. of Surface Water monitoring locations : 1 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 0 | 0 | A | (2.) | COD | | mg/l | | 2.46 | 2.46 | A | (3.) | pH | | NA | | 7.48 | 7.48 | A | (4.) | DO | | mg/l | | 5.80 | 5.80 | A | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 54 | 45 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 44 | 42 | 45 | |
14.5. No. of Soil Sample Monitored locations : 9 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | K(Potassium) | Milligram per Kilogram | | 721 | 326.9 | (2.) | pH | | | 7.99 | 7.21 | (3.) | Electric Conductivity | Millisiemens per Centimetre | | 5.08 | 1.38 | (4.) | P(Phosphorus) | Milligram per Kilogram | | 89.57 | 15.9 | (5.) | N(Nitrogen) | Milligram per Kilogram | | 164.5 | 98.5 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 20 To 30 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 20 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 2070 | 5 | Copy of Permission Letter | Pipeline | | Others | GIDC water supply | Unit has applied for the permission | 09 Jan 2019 | 2070 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic | 22 | 25 | Septic tank | Others | Septic tank | 22 | 0 | (2.) | Industrial | 1040 | 2035 | ETP, Stripper, MEE, Condenate | Others | Deep Sea disposal through GIDC Pipeline | 325 | 715 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 1062 | (b)Total Discharged Water (Kilolitre per Day) | 715 | (c)Total Reused Water (Kilolitre per Day) | 347 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Dil. HCL | Industrial Waste | | 37200 | Tons | 19 | Road | | Others | Sold out to actual end user | (2.) | Sodium romide | Industrial Waste | | 660 | Tons | 10 | Road | | Others | Sold out to actual end user | (3.) | ETP sludge and MEE Salt | Industrial Waste | | 12000 | Tons | 15 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (4.) | Nacl | Industrial Waste | | 1380 | Tons | 10 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (5.) | Aqueous sol. aluminium chloride(By product) | Industrial Waste | | 35448 | Tons | 56 | Road | | Others | Sold out to actual end user | (6.) | Cucl2 | Industrial Waste | | 8736 | Tons | 60 | Road | | Others | Sold out to actual end user | (7.) | Spent NSS | Industrial Waste | | 710.4 | Tons | 60 | Road | | Others | Sold out to actual end user | (8.) | Residue & waste | Industrial Waste | | 4764 | Tons | 20 | Road | | Others | Co processing or Incineration | (9.) | Discarded Bags | Industrial Waste | | 36 | Tons | 10 | Road | | Others | sold to authorized vendors | (10.) | Incineration Ash | Industrial Waste | | 120 | Tons | 15 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (11.) | Nacl+Cucl 80% wet | Industrial Waste | | 4800 | Tons | 60 | Road | | Others | Sold out to actual end user | (12.) | KF | Industrial Waste | | 1500 | Tons | 60 | Road | | Others | Sold out to actual end user | (13.) | Copper hydroxide | Industrial Waste | | 120 | Tons | 64 | Road | | Others | Sold out to actual end user | (14.) | Used oil | Industrial Waste | | 0.96 | Kilolitre | 70 | Road | | Others | sent to registered recycler | (15.) | Distillation Residue | Industrial Waste | | 2400 | Tons | 19 | Road | | Co-Processing | | (16.) | H2SO4(By product) | Industrial Waste | | 2424 | Tons | 60 | Road | | Others | Sold to actual end users /Reused | (17.) | Potassium chloride (20% sol.) By product | Industrial Waste | | 16200 | Tons | 60 | Road | | Others | Sold out to actual end user | (18.) | Poly aluminium chloride | Industrial Waste | | 41520 | Tons | 60 | Road | | Others | Sold out to actual end user | (19.) | Discarded container | Industrial Waste | | 4380 | Tons | 10 | Road | | Others | sold to authorized vendors | (20.) | Sodium bisulfite | Industrial Waste | | 1200 | Tons | 54 | Road | | Others | Sold out to actual end user | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | SO2 | | Microgram per Meter Cube | 26.72 | 2.73 | 0.02 | 26.75 | 80 | (2.) | PM10 | | Microgram per Meter Cube | 96.12 | 2.73 | 0.01 | 96.14 | 100 | (3.) | PM2.5 | | Microgram per Meter Cube | 58.10 | 2.73 | 0.01 | 58.12 | 60 | (4.) | NOx | | Microgram per Meter Cube | 28.53 | 2.73 | 0.0 | 28.54 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Steam Boiler(10TPH) | Coal | 50 | 1 | Others | SPM SO2 Nox | 150,262,94 | (2.) | D.G.Set(1010KVA) | Diesel | 12 | 0.2 | Others | SPM SO2 Nox | 150,262,94 | (3.) | Steam Boiler (7TPH) | Coal | 50 | 1 | Others | SPM SO2 Nox | 150,262,94 | (4.) | Incinerator-I | - | 30 | 1 | Others | SPM, HCL | 150,20 | (5.) | Thermic fluid heater(4Lac Kcal) | Natural gas | 50 | 1 | Others | SPM SO2 Nox | 150,100,94 | (6.) | Incinerator-II | -- | 30 | 1 | Others | SPM HCL | 150,20 | (7.) | D.G.Set(1010KVA) | Diesel | 12 | 0.2 | Others | SPM SO2 Nox | 150,262,94 | (8.) | Steam Boiler (25TPH) | Coal | 50 | 1 | Others | SPM SO2 Nox | 150,262,94 | (9.) | Thermic fluid heater(6Lac Kcal)-II | Natural gas | 50 | 1 | Others | SPM SO2 Nox | 150,262,94 | (10.) | Thermic fluid heater(6 lac kcal)-I | Natural gas | 50 | 1 | Others | SPM SO2 Nox | 150,262,94 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 5000 | (b)Source | DGVCL | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1010KVA | (e)Stack Height (in m) | 12 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 3.3570 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 3.3570 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 2.293 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0.1167 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0.3592 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Scrub land, Residential Area, Mud Flats | 0.38 | Total (ha.) | 3.1489 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 0.6700 | | (2.) | Main Plant | | 2.687 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | ESZs | NA | 0 | -- | (2.) | Critically Polluted Area | Ankleshvar | 4 | -- | (3.) | WLS | NA | 0 | -- | (4.) | ESAs | NA | 0 | -- | (5.) | NPA | NA | 0 | -- | (6.) | Corridors | NA | 0 | -- | (7.) | Wildlife Corridors | NA | 0 | -- | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Defence Installations | | NA | 0 | -- | (2.) | Forest | | NA | 0 | -- | (3.) | Archaeological Sites | | NA | 0 | -- | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 3.35 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | | (b)No. of Households | | (c)No. of PDFs (Project Displaced Families) | | (d)No. of PAFs (Project Affected Families) | | (e)Funds Allocated for R&R(in INR) (in Lacs) | | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Presence of 10 schedule-1 species | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 10.225 Lakh | (iii)Period of Implementation | 2 year | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 25 | (b)Permanent Employment-During Operation | 15 | (c)Temporary Employment- During Construction | 5 | (d)Temporary Employment- During Operation | 5 | (e)No. of working days | 350 | (f)Total Manpower | 50 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 0.67 | 0 | 0.67 | (2.) | Percentage of Total Project Area | 40 | 0 | 40 | (3.) | No. of Plants | 1400 | 0 | 1400 | (4.) | Funds Allocated | 4200000 | 0 | 4200000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Green Belt,
New Plantation on Barren Land | (2.) | Social | Generation of employment,
Social Economic Up Gradation | (3.) | Financial | Upgrade stander of living, Market will be uplift
Financial Up Gradation | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | Stay Order Against NABET/QCI | (ii)Name of the EIA Consultant | Aqua Air Environmental Engineers Pvt. Ltd. | (iii)Address | 403, CENTER POINT, NR. KADIWALA SCHOOL, RING ROAD, SURAT – 395002 (GUJ.) INDIA | (iv)Mobile No. | 8155016995 | (v)Landline No. | 0261246085 | (vi)Email Id | aqua_eia@yahoo.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 03 Mar 2016 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | NA |
The Committee noted that PP was absent and no documents w.r.t. presentation and others as per agenda was forwarded to the Committee and accordingly Committee could not deliberate the proposal and therefore the proposal was deferred and may be placed after the request of PP.
| 01 Sep 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | D N Rai | Designation | General Manager | Name of Company (Applicant Name should not be given here) | Hemani Intermediates Pvt. Ltd. | Address | Plot No. 3208, GIDC Estate Ankleshwar, Dist: Bharcuh, GUJARAT |
|