Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s Kesar Enterprises Limited Distillery Division
(b)Name of the Company / Organisation KESAR ENTERPRISES
(c)Registered Address BAHERI, BAREILLY U.P.,,Bareilly,Uttar Pradesh-243201
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant VIKAS SHARMA
(b)Designation (Owner/ Partner/ CEO) MNE
(c)Address BAHERI , BAREILLY,,Baheri,Bareilly,Uttar Pradesh-254125
(d)Pin code 254125
(e)E-mail keasrenterprises110@gmail.com
(f)STD Code. 522(f)Telephone No. 254214
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity
(b)Category A
(c)Proposal Number IA/UP/IND2/162762/2017
(d)Master Proposal Number(Single Window) SW/162750/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 66,60,62,230,241,148,150,273,274,256,257,259M,260M
(b)Pincode 243201
(c)Bounded Latitudes (North)
From
Degree 28.4645
Minutes
Second
From
Degree 28.4745
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 79.302026
Minutes
Second
From
Degree 79.313982
Minutes
Second
(e)Survey of India Topo Sheet No. 53P/5, 53P/6, 53P/9 and 53P/10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 125
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 62
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 1547
(b)Date of Apply of TOR 01 Feb 2017
(c)Date of Issue of TOR / Standard ToR 02 Mar 2017
(d)Date of Apply of EC 03 Aug 2017
(e)Date of Issue of EC 09 Dec 2017
(f)Previous TOR Letter Copy of Previous TOR letter
(g)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :12 Feb 2020
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :13 Mar 2020
Distance of Public Hearing Venue from the Proposed Project :0
WITHIN PROPOSED PROJECT SITE
State :Uttar Pradesh
District :Bareilly
Tehsil :Baheri
Village :village Jajoonagar, Tanda,
88Issues regarding employment, rain water harvesting, ground water abstraction, control of air pollution were raised..OthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. 1
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 6 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)RS/ENA/AA4580125Kilo Litre per Day(KLD)OthersROAD
(2.)CO GENERATION OF POWER044OthersMEGAWATTOthersCABLES
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)MOLASSES BASED DISTILLERY UNIT4580125PRODUCT RS ENA AA
(2.)POWER PLANT044
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 27 Mar 2020
(iv)Valid Upto 31 Dec 2020
(v)File No. 73739/UPPCB/Bareilly(UPPCBRO)/CTO/water/B AREILLY/
(vi)Application No. 6527066
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 98.50
(b) Funds Allocated for Environment Management (Capital) (in Crores) 18
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.98
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 2
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 562.5
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 562.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Molasses562.5OthersKLDmolasses will be sources from own sugar millRoad100 Othersmolasses will be sources form own sugar unitCopy of Linkage
(2.)Bagasse100OthersTPDown sugar unitRoad1 Othersbagasse will be sourced from own sugar unitCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2019 To 31 Dec 2019
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube89.268.587.8100
(2.)SO2Micro Gram per Meter Cube14.906.9214.6280
(3.)NOxMicro Gram per Meter Cube17.5311.9216.7680
(4.)PM2.5Micro Gram per Meter Cube52.7834.8651.9160
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l474.8332.25002000
(2.)TSSmg/l0000
(3.)Chloridesmg/l28222501000
(4.)Total Hardnessmg/l260224200600
(5.)pHNA7.67.16.58.5
(6.)Heavy Metals.mg/l0000
(7.)Fluoridemg/l0.520.281.01.5
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l5.44.2E
(2.)BODmg/l12.102.4E
(3.)pHOthersph7.67.3E
(4.)CODmg/l4816E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))58.449.8INDUSTRIAL 75, RESIDENTIAL 55
(2.)Leq(Night)A-weighted decibels(dB(A))52.143.9INDUSTRIAL 70, RESIDENTIAL 45
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityMillisiemens per Centimetre280152
(2.)N(Nitrogen)Kilogram per hectare533338
(3.)P(Phosphorus)Kilogram per hectare22.812.6
(4.)pH7.97.6
(5.)K(Potassium)Kilogram per hectare269.6172.7
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.49 To 4.49
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.39 To 3.19
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4/8959/UP/IND/2020
(f)Date of Issue 02 Jun 2020
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater7700.3Copy of Permission LetterPipelineTube Well21-4/8959/UP/IND/202022 Jun 2020770
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)CONSENSATES16302000CPUOthers100% RECYCLED AND REUSE IN UNIT16300
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1630
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 1630
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)FERMENTER SLUDGEOthersSLUDGE3600Tons0OthersCONVERTED INTO MAURE WITHIN PREMISESOthersShall be used as manure along with ash.
(2.)AshOthersASH15120Tons0OthersASH IS USED WITHIN PREMISES IN GRANULATION PLANTOthersAsh generated shall be utilized as manure
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube52.50.581.0753.8560
(2.)NOxMicrogram per Meter Cube17.430.510.7718.380
(3.)PM10Microgram per Meter Cube890.411.3690.56100
(4.)SO2Microgram per Meter Cube14.50.471.5216.4280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)27 TPH slop fired boilerSLOP. BAGASSE632.5PM1030
(2.)12 TPH SLOP FIRED BOILERSLOP BAGASSE452.0PM1030
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 4000
(b)Source Co-gen Power Plant
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) NO
(e)Stack Height (in m) .
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 20.831
    Total Land (ha.) 20.831
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 26202.7
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 866
(e)Settlements (ha.) 1500
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Plantation, sandy , Scrub , Fallow 2850
    Total (ha.) 31418.7000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt7.2908
(2.)Main Plant13.54015
Total (ha.) 20.83095
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNO ESA OBSERVED IN STUDY AREA0.
(2.)Wildlife CorridorsNO WL Corridor OBSERVED IN STUDY AREA0.
(3.)CorridorsNO Corridor OBSERVED IN STUDY AREA0.
(4.)WLSNO WLS OBSERVED IN STUDY AREA0.
(5.)Critically Polluted AreaNO CPA OBSERVED IN STUDY AREA0.
(6.)NPANO NPA OBSERVED IN STUDY AREA0.
(7.)ESZsNO ESZ OBSERVED IN STUDY AREA0.
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNO ARCHAEOLOGICAL FOUND IN STUDY AREA00
(2.)ForestNO FOREST ARE FOUND IN STUDY AREA00
(3.)Defence InstallationsNO DEFENSE AREA IS FOUND0.
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 20.83
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired ALREADY AQUIRED
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area DHORA NADI
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 3.49
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 10
(e)No. of working days 360
(f)Total Manpower 25
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt6.870.427.29
(2.)Percentage of Total Project Area33235
(3.)No. of Plants8002001000
(4.)Funds Allocated102535
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialExtension of Employment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/IA0050
(ii)Name of the EIA Consultant MANOJ GARG
(iii)Address 2/261,  Vishwas Khand, Gomtinagar, Lucknow, U.P.
(iv)Mobile No. 9454721732
(v)Landline No. 0522410942
(vi)Email Id anshumaan110@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 18 Aug 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) This is an expansion proposal and as per TOR no. 3(x)(b) for expansion project, the PP shall submit the compliance report to the conditions of consents from the SPCB. However PP has not submitted the certified compliance report from SPCB as per TOR granted to PP. (S.No 9 of Form 2 has to revised and uploaded). (ii) Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2) (iii) All old CTOs not uploaded to verify the violation, if any done by PP. Please revise the form 2 at S.No. 9.1. On examination it is noted that PP has uploaded blank page in place of all CTOs. (iv) Details of earlier production capacity needs to be uploaded to check the violation, if any. (v) Public hearing proceedings has to be forwarded by the Member Secretary, SPCB, however Public Notice in both the language are also not uploaded in S No. 7.1 of Form 2. Kindly revise the application. (vi) Action Plan with budgetary provisions and time lines on the issues raised during PH has not uploaded in Form 2. Kindly upload the action plan in S.No. 7.1 of Form 2. (vii) Details of water approval has not uploaded in s no. 15 of Form 2, however only application to CGWA is uploaded. Updated status of water approval needs to be submitted (viii) PP in form 2 (S.No. 27) has not mentioned R&R NA. Please revise the form. (ix) Proposed Green belt development programe along-with time line and budgetary allocation needs to be provided (Green belt in SNo. 32 of Form 2) (x) Effluent treatment mechanism with plan for Zero Liquid Discharge for the complete plant (existing and proposed) needs to be submitted (xi) It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. 31 Aug 2020
2.NAThe correction have been made as per the instruction received 26 Sep 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVIKAS SHARMA
DesignationMNE
Name of Company (Applicant Name should not be given here)KESAR ENTERPRISES
AddressBAHERI, BAREILLY U.P.
Print