Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Inclusion of Forest Land in the Environment and CRZ clearance for development of Multi Cargo Port with supporting utilities and infrastructure facilities at Village Hazira, Taluka Choryasi, District Surat, Gujarat by M/s Adani Hazira Port Private Limited
(b)Name of the Company / Organisation Adani Hazira Port Pvt. Ltd.
(c)Registered Address NIL
(d)Legal Status of the Company NIL
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Shalin M Shah
(b)Designation (Owner/ Partner/ CEO) Head - Environment
(c)Address 01st Floor, Infrastructure House, Nr. Mithakhali Circle, Navrangpura, Ahmedabad.,,Ahmadabad City,Ahmedabad,Gujarat-380009
(d)Pin code 380009
(e)E-mail hse@adani.com
(f)STD Code. 0(f)Telephone No. 25557362
(g)Fax No. 255 5560
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(e) Ports, Harbours
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/MIS/428/2010
(d)Master Proposal Number(Single Window) SW/161375/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Hazira Village Survey No. 179 ,434, 318, 306/A/1;
(b)Pincode 394270
(c)Bounded Latitudes (North)
From
Degree 21.085317
Minutes
Second
From
Degree 21.128267
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.638097
Minutes
Second
From
Degree 72.642222
Minutes
Second
(e)Survey of India Topo Sheet No. 46-C/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 14
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratSuratChorasiHazira
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 11-150/2010-IA.III
(c)Date of Issue of TOR 07 Apr 2011
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 11 May 2012
(c)Date of Issue of EC 03 May 2013
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The public hearing was conducted on 14.08.2012 for the master plan for Development of Multi Cargo Port at Hazira including forest lands but the EC was granted excluding the forest lands.
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. File No: 6-11/2013(ENV)/1038
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Oct 24 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Cargo Handling Capacity84084OthersMMTPARoad,Rail,Conveyor Belt
(2.)Port Area496.63301.0199797.6499Hectares(ha)Road,Rail,Conveyor Belt
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Cargo Handling Capacity84 MMTPA0 MMTPA84 MMTPANo increase in cargo handling capacity after expansion
(2.)Port Area496.63 Ha301.0199 Ha797.6499 Ha
(3.)Reclamation - North Side225.30 ha0225.30 haNo increase in the reclamation on the north side after expansion
(4.)Reclamation - South Side84 ha084 haNo increase in the reclamation on the south side after expansion
(5.)Berths12 Nos0 Nos12No increase in the number of berths after expansion
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 17 Jul 2017
(iv)Valid Upto 12 Jul 2022
(v)File No. GPCB/CCA-SRT-1314(8)/ID-35352/528583
(vi)Application No. AW-104319
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 1800
(b) Funds Allocated for Environment Management (Capital) (in Crores) 20.26
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 4.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.20
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 8.5
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 8.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)STONES4.5OthersMMTChikliRoad100 Open MarketCopy of Linkage
(2.)Sand1.5OthersMMTDredging / RajpardiRoad110 Open MarketCopy of Linkage
(3.)Soil/Gravel2.5OthersMMTChikliRoad100 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 20 Dec 2018 To 07 Mar 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube95.569.394.98100
(2.)PM2.5Micro Gram per Meter Cube45.822.745.3860
(3.)SO2Micro Gram per Meter Cube20.98.320.6580
(4.)NOxMicro Gram per Meter Cube25.812.125.5380
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)pHNA7.857.306.58.5
(3.)TDSmg/l6704805002000
(4.)Total Hardnessmg/l240.04210.12200600
(5.)Fluoridemg/l1.40.6211.5
(6.)Heavy MetalsIronmg/l0.30.250.30.3
(7.)Chloridesmg/l44.1532.42501000
    14.3.     No. of Surface Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l00A
(2.)BODmg/l00A
(3.)CODmg/l00A
(4.)pHNA00A
    14.4.     No. of Ambient Noise monitoring locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))53.8047.3870
(2.)Leq(Day)A-weighted decibels(dB(A))68.1363.1075
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.157.8
(2.)P(Phosphorus)Milligram per Kilogram23.2114.28
(3.)K(Potassium)Milligram per Kilogram183.03125
(4.)N(Nitrogen)Milligram per Kilogram104.9171.42
(5.)Electric ConductivityMillisiemens per Centimetre0.540.32
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.48 To 17.75
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.39 To 16.55
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersOpen Market4015Copy of Permission LettermodeOthersTankersOthersNo WithdrawalAgreement01 Apr 202040
(2.)OthersTreated Wastewater from KRIBHCO200018.1Copy of Permission LetterPipelineOthersNo WithdrawalMemrandum of Understanding13 Jun 20142000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewage60.2275Primary (Grit Chamber and equalization), Secondary (MBBR), Tertiary (Sand and Carbon Filter Treatment and Sodium hypochlorite dosing)Green Belt Renewal Plant60.22
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 60.22
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 60.22
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Construction & Demolition WasteConstruction & Demolition Waste0Tons0RoadAuthorized Recyclers
(2.)Biodegradable WasteOthersBiodegradable Waste10.31Tons0OthersOrganic Waste ConverterOthersManure for Greenbelt
(3.)Non-Biodegradable WasteMunicipal Solid Waste143.07Tons0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube19.9500.5920.5580
(2.)PM10Microgram per Meter Cube82.6301.4184.04100
(3.)PM2.5Microgram per Meter Cube33.7400.2934.0460
(4.)SO2Microgram per Meter Cube14.5000.1014.6180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Not ApplicableNA00OthersNA0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2500
(b)Source Gujarat Electricity Board
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 8 DG Sets: 3 Nos of 1500 KVA, One 325 KVA, One 100
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 301.0199
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 301.0199
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1357
(b)Waste/Barren Land (ha.) 10488
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 2280
(e)Settlements (ha.) 3777.6
(f)Industrial (ha.) 2518.4
(g)Forest (ha.) 491.02
(h)Mangroves (ha.) 1234
(i)Marine Area (ha.) 25021.23
(j)Others (ha.) : None 0
    Total (ha.) 47167.2500
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt13.114
(2.)Main Plant282.906Cargo Storage Area and Associated Infrastructures
(3.)OthersParking Area5.0
Total (ha.) 301.02
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsNIL0None
(2.)ESAsHazira Mangroves7.0No mangroves will be disturbed
(3.)Wildlife CorridorsNIL0None
(4.)Critically Polluted AreaNIL0None
(5.)CorridorsNIL0None
(6.)WLSNIL0None
(7.)NPANIL0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNIL0None
(2.)Defence InstallationsNIL0None
(3.)ForestReserve Forest0Two forest land parcels of 210.1594 ha and 90.8605 ha amounting to a total area of 301.0199 Ha is proposed for diversion
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 82340
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl (Pavo cristatus)
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made INR 750000
(iii)Period of Implementation 5
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Hazira Village Pond
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 1.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 150
(c)Temporary Employment- During Construction 400
(d)Temporary Employment- During Operation 600
(e)No. of working days 330
(f)Total Manpower 1200
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt6913.1182.11
(2.)Percentage of Total Project Area13.894.3618.25
(3.)No. of Plants10350019671123171
(4.)Funds Allocated14100000210000016200000
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details
S. No.Item Details
1.
Project Details:
(a)CRZ Classification IB
(b)Location Type Non-Eroding Coast
(c)Details of Mangroves Land Involved, if Any No Mangroves Land is Involved
(d)Area of Mangroves Land (hectare) 0
(e)EIA (Terrestrial) Studies Carried Out
(i)Summary Details of EIA (Terrestrial) Studies One season terrestrial EIA study was conducted
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Terrestrial) 20 Dec 2018
(iv)Period of Study To (EIA Terrestrial) 07 Mar 2019
(f)EIA (Marine) Studies Carried Out
(i)Summary Details of EIA (Marine) Studies One season marine EIA study was carried out
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Marine) 20 Dec 2018
(iv)Period of Study to (EIA Marine) 07 Mar 2019
(g)Disaster Management Plan/National Oil Spill Disaster Contigency Plan The AHPPL already has a Disaster Management Plan a
2.
Description of the Project Under Consideration:
(a)Type of Project Others
(i)Agency Name for Preparing CRZ Maps Institute of Remote Sensing, Anna University, Chen
(ii)Please Specify with salient features Ports & Harbours
(iii)Uploaded relevent Document Copy of relevent Document
3.
Distance of Project (in meters) from ltl/htl to be stated :
(a)Clause of CRZ Notification Under which the Project is a Permissible/Regulated Activity IB
(b)Whether CRZ Map Indicating HTL,LTL Demarcation in 1:4000 Scale Prepared? Yes
(i)Distance of Project (in meters) from HTL to be Stated 0
(ii)Uploaded Maps(Shape File) Copy of Maps
(iii)Distance of Project(in meters) from LTL to be Stated 512
(iv)Uploaded Maps(Shape File) Copy of Maps
(c)Whether Project Layout Superimposed on CRZ Map 1:4000 Scale ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(d)Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(e)Whether CRZ Map Indicating CRZ-I,II,III and IV Including Other Notified ESAs Prepared Yes
(i)Uploaded Maps (kml File) Copy of Maps
(f)NOC from State Pollution Control Boards Obtained No
(g)Details of Rain Water Harvesting System
4.
Recommendation of State Coastal Zone Management Authority:
(a)Copy of CZMA Copy of CZMA
(b)State the Conditions Imposed Comply to letter no. ENV-10-2012-31-E dt 11.05.12
(c)Social and Environmental Issues and Mitigations Measures Suggested Including but not Limited to R&R, Water, Air, Hazardous Wastes, Ecological aspects, etc. (Brief Details to be Provided) The proposed forest land for diversion is not inha
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 20
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 45
(d)Total plot area (sqm) 90000
(e)Total built up area (sqm) 36000
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 2 Wheeler Parking will be 300 nos. and 4 Wheelers
5.
Energy Saving Measures:
(a)Source/Mode 39.5 MW of Solar Power & Wind Power, and CFL
(b)Percentage 5
(c)Quantity 39.5
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area The proposed development would not impact the surf
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? Yes
(b)Details of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act The applicant shall install & operate comprehensive adequate air pollution control system in order to achieve prescribed norms
(c)Uploaded Copy of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act Copy of Direction Issued
(d)Compliance status of the directions Complied
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA 0170
(ii)Name of the EIA Consultant Cholamandalam MS Risk Services Limited
(iii)Address Parry House 3rd Floor, No.2 N.S.C. Bose Road, Chennai – 600 001, Tamilnadu
(iv)Mobile No. 9940047988
(v)Landline No. 0443044562
(vi)Email Id inquiry@cholams.murugappa.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 23 May 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA1. unable open your ToR letter in Form2 application, please upload again in form2 application 2.Unable to open EC letter Please upload again in Form2 application 3.Unable to open public hearing support documents 3.Whether application was submitted under expansion proposal, copy of Tor issued for expansion including the proposed Forest land and its condition wise ToR compliance 04 Aug 2020
2.NAThe correction have been made as per the instruction received 05 Aug 2020
3.NAunable open your ToR letter in Form2 application, please upload again in form2 application 2.Unable to open EC letter Please upload again in Form2 application 3.Unable to open public hearing support documents 10 Aug 2020
4.NAThe correction have been made as per the instruction received 13 Aug 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantShalin M Shah
DesignationHead - Environment
Name of Company (Applicant Name should not be given here)Adani Hazira Port Pvt. Ltd.
Address1st Floor, Infrastructure House, Adjacent to Adani House, Near Mithakhali Circle, Navrangpura, Ahmad