Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Development of Vadodara Mumbai Expressway (Phase-II) from km.26.320 to km.104.700 (km.390.864 of NH-8) of Main Expressway in the State of Maharashtra
(b)Name of the Company / Organisation National Highways Authority of India
(c)Registered Address G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,South West,Delhi-110075
(d)Legal Status of the Company Central Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dr Biswajit Mukhopadhyay
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address G-5 & 6, Sector-10, Dwarka, New DElhi-110075,G-5 & 6, Sector-10, Dwarka, New DElhi-110075,,New Delhi,Delhi-110075
(d)Pin code 110075
(e)E-mail biswajit@nhai.org
(f)STD Code. 11(f)Telephone No. 25074200
(g)Fax No. 25093543
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(f) Highways
Minor Activity
(b)Category A
(c)Proposal Number IA/MH/MIS/156726/2020
(d)Master Proposal Number(Single Window) SW/156718/2020
(e)EAC concerned (for category A Projects only) INFRA-1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. List attached in additional details
(b)Pincode 401404
(c)Bounded Latitudes (North)
From
Degree 19.484741
Minutes
Second
From
Degree 20.156165
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.850189
Minutes
Second
From
Degree 72.924489
Minutes
Second
(e)Survey of India Topo Sheet No. 46D16, 47A13, 47A14, 47A15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 113
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :09 Jan 2020
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :11 Feb 2020
Distance of Public Hearing Venue from the Proposed Project :0.9
Gram Panchayat Office, Dahisar Turfe Manor village
State :Maharashtra
District :Palghar
Tehsil :Palghar
Village :Dahisar Turfe Manor
204Land acquisition and environmental impactsOthersAddl. District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)N/AN/A
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)78.11878.11KilometersRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 7010
(b) Funds Allocated for Environment Management (Capital) (in Crores) 66.42
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 35.05
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.5
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 40000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 40000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel40000OthersKLLocal Petrol PumpRoad20 Open MarketCopy of Linkage
(2.)Aggregate3072000OthersCumApproved QuarryRoad3.3 Open MarketCopy of Linkage
(3.)Bituminous Concrete4138OthersCumLocal TradersRoad20 Open MarketCopy of Linkage
(4.)Steel78641OthersMTLocal TradersRoad20 Open MarketCopy of Linkage
(5.)Bitumen1004OthersMTRefineryRoad100 Open MarketCopy of Linkage
(6.)Cement807000OthersMTLocal TradersRoad20 Open MarketCopy of Linkage
(7.)Coarse Sand2050000OthersCumApproved QuarryRoad0.5 OthersNo linkageCopy of Linkage
(8.)Fly Ash10932287OthersCumGIPCL, SuratOthersCovered dumper212 OthersNo linkageCopy of Linkage
(9.)Emulsion130OthersMTRefineryRoad100 Open MarketCopy of Linkage
(10.)Water8571Kilo Litre per DayTanker/Ground & Surface waterOthersTanker15 OthersNo linkageCopy of Linkage
(11.)Borrow Earth7253703OthersCumApproved Borrow AreaRoad2.0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 06 Mar 2017 To 30 May 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube23.814.722.860
(2.)SO2Micro Gram per Meter Cube9.85.99.880
(3.)NOxMicro Gram per Meter Cube25.614.823.880
(4.)OthersCOMili Gram per Meter Cube0.320.190.34
(5.)PM10Micro Gram per Meter Cube62.942.660.1100
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHOthersN/A7.96.876.58.5
(2.)Total Hardnessmg/l192.34151.5200600
(3.)TSSmg/l0000
(4.)Chloridesmg/l106.3991.462501000
(5.)OthersCalcium as Camg/l57.1833.1375200
(6.)Fluoridemg/l0.620.2111.5
(7.)TDSmg/l4223465002000
(8.)Heavy MetalsLead (as Pb)mg/l0.00.00.010.01
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.46.1C
(2.)BODmg/l8.42.32C
(3.)pHOthersN/A7.857.24C
(4.)CODmg/l110.97.84C
(5.)OthersTotal ColiformOthersMPN/100 ml272C
(6.)OthersFluoride as Fmg/l0.740.56C
(7.)OthersIron as Femg/l0.490.33C
    14.4.     No. of Ambient Noise monitoring locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))57.539.755
(2.)Leq(Night)A-weighted decibels(dB(A))48.736.445
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.07.5
(2.)P(Phosphorus)Kilogram per hectare18.760.34
(3.)N(Nitrogen)Kilogram per hectare409.76103.48
(4.)K(Potassium)Kilogram per hectare508.05260
(5.)Electric ConductivityOthersMhos/cm2950290
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface10000.0 Not Appliacble modeOthersTankerIntake WellNA09 Jun 20200
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)NA00-OthersNA00
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Solid WasteMunicipal Solid Waste27Tons2.0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)Others(Specify)COMicrogram per Meter Cube3200.01643854000
(2.)PM2.5Microgram per Meter Cube22.820022.8360
(3.)PM10Microgram per Meter Cube60.170060.18100
(4.)NOxMicrogram per Meter Cube23.810023.8280
(5.)SO2Microgram per Meter Cube9.8009.980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)N/AN/A00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source Maharashtra State Electricity Distribution Co. Ltd
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 750
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 193.1777
(b)Private Land (ha.) 708.7364
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 901.9141
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1461.1861
(b)Waste/Barren Land (ha.) 19.2519
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 110.7939
(e)Settlements (ha.) 176.5207
(f)Industrial (ha.) 33.4404
(g)Forest (ha.) 1083.2379
(h)Mangroves (ha.) 25.835
(i)Marine Area (ha.) 0
(j)Others (ha.) : Marshy Land, Salt Pan, Mudflats 117.0591
    Total (ha.) 3027.3250
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersHighway Development901.9141
Total (ha.) 901.9141
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0None within 10 km
(2.)WLSTungareshwar Wildlife Sanctuary1.28Does not pass through the Wildlife Sanctuary
(3.)NPANA0None within 10 km
(4.)Wildlife CorridorsNA0None within 10 km
(5.)ESZsTungareshwar Wildlife Sanctuary0.46Outside ESZ boundary
(6.)CorridorsNA0None within 10 km
(7.)ESAsDahanu Taluka Ecologically Sensitive Area0.027.745 km stretch passing through Dahanu Taluka ESA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestReserved, Protected, Mangrove & Private Forest0.0Alignment passing through forest area
(2.)Archaeological SitesNone0No Archaeological sites within 10 km
(3.)Defence InstallationsNone0No Defence Installations within 10 km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Under Process(Stage-II)
(b)Legal Status of Forest Land Protected
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 88349
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 640.60
(b)Land yet to be acquired(Ha) 261.31
(c)Status of Land acquisition if not acquired Acquisition of remaining land under progress
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 51
(b)No. of Households 3110
(c)No. of PDFs (Project Displaced Families) 359
(d)No. of PAFs (Project Affected Families) 3110
(e)Funds Allocated for R&R(in INR) (in Lacs) 159400000
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Refer Section 3.14.7 of Chapter-3 and Section 9.4 of Chapter-9 of EIA report
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 1200000
(iii)Period of Implementation Pre-Construction & Construction phase
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Vaitarna River, Surya River, Jogani River, Vadvali River, Pond
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 200
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 450
(d)Temporary Employment- During Operation 100
(e)No. of working days 700
(f)Total Manpower 800
32.
Green Belt in Ha:
(a)Total Area of Green Belt 234
(b)Percentage of Total Project Area 25.94
(c)No. of Plants to be Planted 90899
(d)Funds Allocated for Plantation 231206000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details
S. No.Item Details
1.
Project Details:
(a)CRZ Classification III
(b)Location Type Low and Medium Eroding Coast
(c)Details of Mangroves Land Involved, if Any Diversion of Mangrove Forest involved
(d)Area of Mangroves Land (hectare) 3.9500
(e)EIA (Terrestrial) Studies Carried Out
(i)Summary Details of EIA (Terrestrial) Studies Please refer Section 3.14 of Chapter-3 of EIA Repo
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Terrestrial) 04 Oct 2017
(iv)Period of Study To (EIA Terrestrial) 30 Oct 2017
(f)EIA (Marine) Studies Carried Out
(i)Summary Details of EIA (Marine) Studies NA
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Marine) 31 Dec 1899
(iv)Period of Study to (EIA Marine) 31 Dec 1899
(g)Disaster Management Plan/National Oil Spill Disaster Contigency Plan Not Applicable
2.
Description of the Project Under Consideration:
(a)Type of Project Coastal Roads/Roads on Stilt
(i)Agency Name for Preparing CRZ Maps NCESS
(ii)Area of Land Reclamation 0
(iii)Estimated Quantity of Muck/Earth for Reclamation 0
(iv)Carrying Capacity of Traffic 1300
3.
Distance of Project (in meters) from ltl/htl to be stated :
(a)Clause of CRZ Notification Under which the Project is a Permissible/Regulated Activity III
(b)Whether CRZ Map Indicating HTL,LTL Demarcation in 1:4000 Scale Prepared? Yes
(i)Distance of Project (in meters) from HTL to be Stated 0
(ii)Uploaded Maps(Shape File) Copy of Maps
(iii)Distance of Project(in meters) from LTL to be Stated 0
(iv)Uploaded Maps(Shape File) Copy of Maps
(c)Whether Project Layout Superimposed on CRZ Map 1:4000 Scale ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(d)Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(e)Whether CRZ Map Indicating CRZ-I,II,III and IV Including Other Notified ESAs Prepared Yes
(i)Uploaded Maps (kml File) Copy of Maps
(f)NOC from State Pollution Control Boards Obtained No
(g)Details of Rain Water Harvesting System
4.
Recommendation of State Coastal Zone Management Authority:
(a)Copy of CZMA Copy of CZMA
(b)State the Conditions Imposed Stated
(c)Social and Environmental Issues and Mitigations Measures Suggested Including but not Limited to R&R, Water, Air, Hazardous Wastes, Ecological aspects, etc. (Brief Details to be Provided) Please refer Chapter-4 of EIA Report
   35.   Sector Specific Details For INFRA-1
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 4
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking NA
5.
Energy Saving Measures:
(a)Source/Mode N/A
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Refer Section 4.3 of Chapter-4 of EIA Report
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment 78.118
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
(a)Total No. of Bridges 37
(b)Total No. of ROB 0
(c)Total No. of Interchanges 2
(d)Total No. of Flyovers 4
(e)Total No. of Vehicle Underpass 33
(f)Total No. of Pedestrian Underpass 50
(g)Details of other utilities rail and road corridors NA
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court High Courts
(c)Name of the Sub Court Bombay
(d)Case No. WP 13561 & 13544 / 2018
(e)Orders/Directions of the court ,if any and its relevance with the proposed project The hearing is in progress. Last date of hearing 1
(f)Case Details Filed by the project affected persons regarding la
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0089
(ii)Name of the EIA Consultant Intercontinental Consultants and Technocrats Pvt L
(iii)Address A-8 Green Park, New Delhi - 16
(iv)Mobile No. 9811820828
(v)Landline No. 40863000
(vi)Email Id aseem@ictonline.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-1
(ix)Validity of Accreditation 02 Sep 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease upload the ToR 15 Jul 2020
2.NAThe correction have been made as per the instruction received 15 Jul 2020
3.NAProvide following documents/information/clarifications: (i) Copy of documents in support of the competence/authority is outdated that was submitted in response of EDS dated 11.08.2018. Submit the latest document. (ii) Please clarify that why the TOR is not mandatory for submission of this application as mentioned in column 6 of Form-2 of this application. (iii) Baseline data was collected between March 2017 and May 2017, i.e., more than 3 years old. EIA/EMP report to be revised for incorporating fresh baseline data. (iv) Traffic baseline data is more than 4 years old (data collection between 24 Feb - 7 March 2016) and Traffic survey locations map was prepared in year 2016. EIA/EMP report to be revised for incorporating fresh baseline data and maps related to traffic studies. (v) It is mentioned that period of marine study was done on 3-4 April, 2017, however, no report has been uploaded. Instead in the relevant column, it is mentioned as Not Applicable. Please furnish clarification for contradictory statement. (vi) Copy of recommendation letter from MCZMA is not submitted. Please upload the same. (vii) As per minutes of MCZMA meeting, the length of the proposed alignment is 78.118, however, as per this EC+CRZ application length is 78.380. Please clarify in this regard. (viii) CRZ Maps as desired in Column 35.3 of Form-2 application are not uploaded. (ix) Copy of court order is not uploaded properly. 16 Jul 2020
4.NAThe correction have been made as per the instruction received 16 Jul 2020
5.NAEDS reply to be mentioned in Form2 application only and not as additional document 16 Jul 2020
6.NAThe correction have been made as per the instruction received 16 Jul 2020
7.NACRZ maps not displaying 16 Jul 2020
8.NAThe correction have been made as per the instruction received 17 Jul 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterRecommendation if Maharashtra Coastal Zone Management Authority is enclosed 07 Sep 2020
2.NA

The EAC, after examining the documents submitted by proponent and noted that the proponent does not have the approval of the State Coastal Zone Management Authority and therefore 2020, deferred the proposal for further consideration.

04 Sep 2020
3. ADS Reply LetterIt is expected that letter of recommendation shall be issued by the MCZMA in few days. 14 Aug 2020
4.NA

It was committed by the project proponent that letter of recommendations by the Maharashtra Coastal Zone Management Authority for this project will be submitted before finalisation of the Minutes. However, proponent could not submit the recommendation letter.

In view of this, The EAC, after detailed deliberation during 239th meeting on 29th July, 2020, deferred the proposal for want of recommendation letter by Maharashtra Coastal Zone Management in respect of this project.

08 Aug 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDr Biswajit Mukhopadhyay
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)National Highways Authority of India
AddressG-5 & 6, Sector-10, Dwarka, New DElhi-110075
Print