1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/AP/MIS/41309/2016    ii. MoEFCC File No. : 11-10/2016-IA-III    iii.Short narrative of the project: Golden sands Beachfront Resorts    iv. Project Sector : INFRA-2    v. Company/Proponent : GOLDEN SANDS BEACH FRONT RESORTS
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.Andhra PradeshGunturBapatla
 
   vii.Date of TOR Granted N/A viii.TOR letter issued by Ministry: N/A ix.Date of Submission for EC: 18 Jan 2016 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 18 Jan 2016   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: NIL
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAThe project was considered by the EAC in its meeting held on 28-29 January, 2016. During appraisal of the proposal, the Committee noted that the parking space that is being provided is far short of expected tourist influx in the area. Hence, the parking plan needs revision. Keeping in view the proximity to the sea and the land contours the building plans may also need modification in respect of plinth level keeping the safety requirements. The PP agreed to re-submit the plan. The PP will also clarify the entry and exit from any State and National Highways so that traffic access is not affected. The proposal was deferred for want of inputs as explained above. 22 Feb 2016
2. ADS LetterTotal Parking Space has been increased from 598.41 Sqm to 1071.27 Sqm in which 40 car parking slots and 50 two wheeler parking slots have been provided. Revised Layout and building plan enclosed as Annexure-1 .The National Highway no NH-214A connecting Kathipudi to Ongole is sitauated at a distance of 10.5 km towards NW and no State Highway is existing near the proposed site. District Road connecting Karamchedu to vaderevu is sitauated at a distance of 3.2km 02 Mar 2016
3.NAThe project was considered in 157th EAC Meeting. The minutes of the meeting may seen at environmentclearance.nic.in. In this connection it is requested to submit the requisite information as sought by the EAC. However, the project was also listed in 158th EAC Meeting. Minutes of the meeting is awaited. 02 May 2016
4. ADS LetterDear sir Here we are uploading Clarification Sought in 157th EAC Meeting held on 28th March 2016 . This has reference of 3.10 of Minutes of the 158th meeting of Expert Appraisal Committee for Projects related to Infrastructure Development, Coastal Regulation Zone, We have observed a typographical error in 5th Point of 3.10.3 “All waste (liquid and solid) arising from the proposed development will be disposed off as per the norms prescribed by Tamil Nadu State Pollution Control Board. There shall not be any disposal in to the sea/coastal water bodies.” Actually the project is proposed in Adavi Village, Bapatla Mandal of Guntur District of Andhra Pradesh State. Hence we request you to change the term “Tamilanadu State Pollution Control Board” with “Andhra Pradesh StatePollution Control Board”. 19 Oct 2016
4. Accredited Consultant Details
   i. Accreditation status : No    ii. Reason for not hiring the Consultant : This is small project and already got the clearance from APCZMA. Staff in the proponent has knowledge about the CRZ regulations and EC guidelines for this kind of project.
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : YAGANTI    ii. Designation : CHAIRMAN & MANAGING DIRECTOR    iii. Name of Company(Applicant Name should not be given here) : GOLDEN SANDS BEACH FRONT RESORTS    iv. Address : 5-88-1,3 LANE , LAKSHMIPURAM ,GUNTUR v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL