1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | EXPANSION AND CHANGE IN PRODUCT MIX | (b)Name of the Company / Organisation | SANSKAR CHEMICALS AND DRUGS PRIVATE LIMITED | (c)Registered Address | S.F. No. 457/3A, 457/3C, 457/4A, 457/4C, 457/4C (Part), Ammoor village,,12/5 (part), Chettithangal Village, Wallajah Taluk,Vellore,Tamil Nadu-632403 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Dinesh Kumar R | (b)Designation (Owner/ Partner/ CEO) | Owner | (c)Address | S.F. No. 457/3A, 457/3c, 457/4A, 457/4C, 457/4C part, Ammoor Village,12/5 part, Chettithangal village, wallajah Taluk,Wallajah,Vellore,Tamil Nadu-632403 | (d)Pin code | 632403 | (e)E-mail | karthik@sanskarchemicals.com | (f)STD Code. | 44(f)Telephone No. | 00000000 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/TN/IND2/155475/2018 | (d)Master Proposal Number(Single Window) | SW/155468/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | S.F. No. 457/3A, 457/3C, 457/4A, 457/4C, 457/4C (P | (b)Pincode | 632403 | (c)Bounded Latitudes (North) | | From | | Degree | 12.963459 | Minutes | | Second | | From | | Degree | 12.964466 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 79.342512 | Minutes | | Second | | From | | Degree | 79.342714 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 57 O/8 and 57 P/5 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 180 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 5.06 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Tamil Nadu | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | IA-J-11011/361/2018-IA-II(I) | (b)Date of Apply of TOR | 15 Nov 2018 | (c)Date of Issue of TOR / Standard ToR | 18 Dec 2018 | (d)Date of Apply of EC | 01 Jan 2006 | (e)Date of Issue of EC | 02 Jan 2006 | (f)Previous TOR Letter | Copy of Previous TOR letter | (g)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 02 Jan 2020 | Distance of Public Hearing Venue from the Proposed Project : | 1.5 |
| TSR Mahal | State : | Tamil Nadu | District : | Vellore | Tehsil : | Wallajah | Village : | Ammoor |
| 132 | Issue related to Air, water pollution and improper activities industries in Ranipet area. the proponent will allot 16 Lakhs as a budget for PH issue | Others | District Revenue Officer | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Chennai | (iii)Letter No. | Nil | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jun 26 2020 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Basic Chromium Sulphate | 90 | -90 | 0 | Others | MT/Month | Road | | (2.) | Sitagliptin | 0 | 1 | 1 | Others | MT/Month | Road | | (3.) | IsoPropyl Bromide | 0 | 10 | 10 | Others | MT/month | Road | | (4.) | Linagliptin | 0 | 0.15 | 0.15 | Others | MT/Month | Road | | (5.) | Vildagliptin | 0 | 1.5 | 1.5 | Others | MT/Month | Road | | (6.) | Trityl olmesartan medoximal | 0 | 2 | 2 | Others | MT/Month | Road | | (7.) | Ploy Allamine hydrochloride | 20 | 0 | 20 | Others | MT/Month | Road | | (8.) | Spent Caustic Lye Solution | 10 | -10 | 0 | Others | MT/Month | Road | | (9.) | Allyl Isopropyl acetyl urea | 0 | 5 | 5 | Others | MT/Month | Road | | (10.) | Diacerine | 0 | 0.2 | 0.2 | Others | MT/Month | Road | | (11.) | Allylbromide | 0 | 6 | 6 | Others | MT/Month | Road | | (12.) | Spent Sulphuric acid By products | 81 | 0 | 81 | Others | MT/Month | Road | | (13.) | Gypsum(by product) | 60 | -60 | 0 | Others | MT/Month | Road | | (14.) | Hydrogen Bromide | 0 | 25 | 25 | Others | MT/Month | Road | | (15.) | Isopropanol Hydrochloride | 40 | 0 | 40 | Others | MT/Month | Road | | (16.) | Non Ferric Alum | 90 | -90 | 0 | Others | MT/Month | Road | | (17.) | Lexoprofen | 0 | 2 | 2 | Others | MT/Month | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | GL reactor | 0 | 1 | 1 | 3 KL | (2.) | Cooling Tower | 2 no | 0 | 2 No | 3.1 KLD | (3.) | DG set | 100 kVA | 200 kVA | 200 kVA | 100 kVA will be replaced after expansion | (4.) | SS reactor | 6 Nos | 3 Nos | 9 Nos | 3.2 KL, 1.2 KL, 2KL, 2 KL, 6KL, 2 KL, 3.2 KL, 3.5 KL, 5 KL | (5.) | SS dryer (48 trays) | - | 48 trays | 48 trays | - | (6.) | SS dryer (96 trays) | - | 96 trays | 96 trays | - | (7.) | Boiler | 0.7 TPH | - | 0.7 TPH | - | (8.) | Chilling plant | 1 No | 1 No | 2 Nos | 39 TR | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 03 Jul 2020 | (iv)Valid Upto | 31 Mar 2021 | (v)File No. | 2008132858125 | (vi)Application No. | F.0190VLR/RS/DEE/TNPCB/VLR/W/2020 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 4.25 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 1.61 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.085 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.161 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | 70 | (c)Total quantity of raw material/fuel | 70 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | 68 Product raw material | 16.29 | Tons per Annum | | Local | Road | | 850 | Open Market | | Copy of Linkage | (2.) | HSD | 0.5 | Others | KL/month | Local | Road | | 6 | Open Market | | Copy of Linkage | (3.) | Fire wood | 0.75 | Others | TPH | Local | Road | | 6 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 15 Jan 2020 To 30 Apr 2020 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 84.5 | 45.9 | 84.0 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 14.8 | 5.9 | 14.7 | 80 | (3.) | NOx | | Micro Gram per Meter Cube | 28.2 | 13.7 | 28.0 | 80 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 32.0 | 17.0 | 31.8 | 60 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TSS | | | mg/l | | 1 | 1 | 100 | 100 | (2.) | TDS | | | mg/l | | 1582 | 226 | 500 | 2000 | (3.) | Heavy Metals | | ZInc | mg/l | | 0.1 | 0.1 | 5 | 15 | (4.) | pH | | | NA | | 8.37 | 7.09 | 6.5 | 8.5 | (5.) | Chlorides | | | mg/l | | 560 | 22.27 | 250 | 1000 | (6.) | Total Hardness | | | mg/l | | 583 | 125 | 200 | 600 | (7.) | Fluoride | | | mg/l | | 0.57 | 0.18 | 1 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 34 | 1.2 | D | (2.) | COD | | mg/l | | 200 | 5.6 | E | (3.) | pH | | NA | | 7.62 | 6.68 | A | (4.) | DO | | mg/l | | 6.1 | 5.1 | B | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 70.7 | 51.2 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 68 | 40 | 70 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Milligram per Kilogram | | 46.69 | 15.54 | (2.) | N(Nitrogen) | Milligram per Kilogram | | 561.65 | 138 | (3.) | pH | | | 7.24 | 5.1 | (4.) | K(Potassium) | Milligram per Kilogram | | 180 | 94 | (5.) | Electric Conductivity | Others | µS/cm | 110.3 | 70 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 5 To 5 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 10 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Private Tanker | 20 | 8 | Copy of Permission Letter | modeOthers | Lorry | Others | Lorry | Nil | 01 May 2020 | 12.2 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Effluent | 6 | 10 | MEE and ATFD | Reuse within the Plant & Recycling,Others | Salt | 5.4 | 0.6 | (2.) | Sewage | 2.4 | 3 | STP | Green Belt Renewal Plant | | 2.4 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 8.4 | (b)Total Discharged Water (Kilolitre per Day) | 0.6 | (c)Total Reused Water (Kilolitre per Day) | 7.8 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Inorganic | Municipal Solid Waste | | 2.3 | Tons | 8 | Road | | Authorized Recyclers | | (2.) | Organic | Municipal Solid Waste | | 3.5 | Tons | 3 | Road | | Others | Local Bins | (3.) | Ash | Others | Other | 39 | Tons | 12 | Road | | Others | Brick manufacture | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 32 | 0 | 0.08 | 32.1 | 60 | (2.) | SO2 | | Microgram per Meter Cube | 14.8 | 0 | 0.07 | 14.88 | 80 | (3.) | NOx | | Microgram per Meter Cube | 28.2 | 0 | 1.09 | 29.3 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 84.5 | 0 | 0.08 | 84.6 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Boiler 0.75 TPH | Firewood | 20 | 0.4 | SO2 | | 0.00905 | (2.) | Boiler 0.75 TPH | Firewood | 20 | 0.4 | PM10 | | 0.0309 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 139.87 | (b)Source | TANGEDCO | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 200 kVA (proposed) | (e)Stack Height (in m) | 9 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0.3745 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 0.3745 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 20185 | (b)Waste/Barren Land (ha.) | 1289 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 4213 | (e)Settlements (ha.) | 2781 | (f)Industrial (ha.) | 328 | (g)Forest (ha.) | 2425 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Mining | 278 | Total (ha.) | 31499.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 0.3745 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Wildlife Corridors | Nil | 0 | Nil | (2.) | WLS | Nil | 0 | Nil | (3.) | NPA | Nil | 0 | Nil | (4.) | ESAs | Nil | 0 | Nil | (5.) | ESZs | Nil | 0 | Nil | (6.) | Critically Polluted Area | Ranipet SIPCOT | 2.88 | WSW | (7.) | Corridors | Nil | 0 | Nil | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Ammur RF | 1.82 | ENE | (2.) | Defence Installations | | Nil | 0 | Nil | (3.) | Archaeological Sites | | Nil | 0 | Nil | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Settithangal Lake | (ii)Direction of Water Bodies in Buffer Area | South West | (iii)Distance of Water Bodies in Buffer Area | 0.96 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 25 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 10 | (e)No. of working days | 365 | (f)Total Manpower | 35 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 597.4 | 900.67 | 1498.07 | (2.) | Percentage of Total Project Area | 15.95 | 24.03 | 39.980000000000004 | (3.) | No. of Plants | 15 | 165 | 180 | (4.) | Funds Allocated | 50000 | 450000 | 500000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Job offer to 35 | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA 0083 | (ii)Name of the EIA Consultant | HUBERT ENVIRO CARE SYSTEMS (P) LTD, CHENNAI | (iii)Address | A-21, (Behind Lions Club School) III Phase, Thiru Vi Ka Industrial Estate. Guindy, Chennai - 600 032. | (iv)Mobile No. | 9884390811 | (v)Landline No. | 0444363555 | (vi)Email Id | moses@hecs.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 29 Sep 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | 1. Documents related to Public hearing proceedings which has forwarded by the Member Secretary, SPCB to the MoEFCC along with complete public hearing/consultation documents, needs to be uploaded. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation has not been submitted. Kindly upload the requisite documents. Form 2 (S.no. 7.1)
2. Action Plan with budgetary provisions and time lines on the issues raised during PH has not uploaded in Form 2. Kindly upload the action plan in S.No. 7.1 of Form 2 alongwith other requisite details.
3. This is an expansion proposal accordingly, the PP shall submit the compliance report to the conditions of consents from the SPCB. (S.No 9 of Form 2 has to revised and uploaded),
4. S. no. 23.1 of form 2 (CPA) mentioned However PP has not submitted the Report as per the Ministry’s office memorandum 31st October, 2019 regarding projects located in Critically Polluted Area.
5. All old CTOs not uploaded to verify the violation, if any done by PP (S No. 9.1 of Form 2).
6. Details of earlier production capacity needs to be authenticated and uploaded to check the violation, if any.
7. Effluent treatment mechanism with plan for Zero Liquid Discharge for the complete plant needs to be submitted
8. Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2)
9. It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. | 26 Jun 2020 | 2. | NA | The correction have been made as per the instruction received | 06 Jul 2020 | 3. | NA | 1. Please read the earlier EDS sought by the Ministry earlier. The matter was again examined and noted that PP has not revised the Form 2 and not uploaded the requisite information on Parivesh Portal (For eg. (a) Certified compliance report on CTO, as per TOR, has not uploaded in Form 2, and, (b) Documents related to Public hearing proceedings which has forwarded by the Member Secretary, SPCB to the MoEFCC has not uploaded in Form 2. PP/consultant has not uploaded the document on PH forwarded by SPCB to MoEFCC) Form 2 (S.no. 7.1)
2. It is pertain to mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action.
3. It is also mentioned that after acceptance the Form 2 and EIA/EMP report can not be revise. Therefore, PP/Consultant is again requested to kindly do needful. | 28 Jul 2020 | 4. | NA | The correction have been made as per the instruction received | 11 Sep 2020 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | As per the ADS, we upload Revised EIA report with DAR Report along with ADS reply and affidavit | 19 Dec 2020 | 2. | NA | The Committee, at the first instance opined that the matter may be examined by the Ministry and the proposal shall be considered by the EAC based on the decisions taken.
The Committee also observed that the consultant has also tried to conceal the facts and mislead the EAC/Ministry. The attitude of the consultant may be reported to QCI to debar from this sector for presenting the cases before EAC in MoEF&CC.
After detailed deliberation, the proposal was deferred for the needful. | 29 Oct 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Dinesh Kumar R | Designation | Owner | Name of Company (Applicant Name should not be given here) | SANSKAR CHEMICALS AND DRUGS PRIVATE LIMITED | Address | S.F. No. 457/3A, 457/3C, 457/4A, 457/4C, 457/4C (Part), Ammoor village, |
|