1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Building construction of Group Housing Society on Residential Plot leased by DDA. | (b)Name of the Company / Organisation | THE MODEST KETKI COOP. GROUP HOUSING SOCIETY LTD. | (c)Registered Address | Plot No. 8B, Sector - 11, Dwarka, New Delhi,,South West,Delhi-110075 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Navneet Kumar | (b)Designation (Owner/ Partner/ CEO) | Secretary | (c)Address | D-103, The Modest Ketki Coop. Group Housing Society Ltd. Plot no. 8B, Sector - 11, Dwarka, New Delhi,,Delhi Cantonment.,South West,Delhi-110075 | (d)Pin code | 110075 | (e)E-mail | modestketki12@gmail.com | (f)STD Code. | 798(f)Telephone No. | 2657854 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 8(a) Building and Construction projects
| Minor Activity | | (b)Category | B2 | Reason for Applying at Ministry | SEIAA | (c)Proposal Number | IA/DL/NCP/155068/2020 | (d)Master Proposal Number(Single Window) | SW/153453/2020 | (e)EAC concerned (for category A Projects only) | INFRA-1 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 8B | (b)Pincode | 110075 | (c)Bounded Latitudes (North) | | From | | Degree | 28.5878 | Minutes | | Second | | From | | Degree | 28.606 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 77.0492 | Minutes | | Second | | From | | Degree | 77.0499 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 53D14, 53D15, 53H3 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 220 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 9.1 | (j)Seismic Zone | 4 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Delhi | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)Whether TOR is mandatory for submitting application | No | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | Not applicable | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | NA | NA | its building construction project | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Plot area in Sq.m. | 13000 | Others | Sq.m. | Others | NA | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | 31 Dec 1900 | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 40 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.95 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.16 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.09 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | NA | 0 | Tons per Annum | | NA | Road | | 0 | Fuel Supply Agreement | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Jan 1900 To 31 Dec 1900 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | (2.) | SO2 | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | (3.) | NOx | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | |
14.2. No. of Ground Water monitoring locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TDS | | | mg/l | | 0 | 0 | 0 | 0 | (2.) | Fluoride | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (4.) | Total Hardness | | | mg/l | | 0 | 0 | 0 | 0 | (5.) | Chlorides | | | mg/l | | 0 | 0 | 0 | 0 | (6.) | Heavy Metals | | Iron | mg/l | | 0 | 0 | 0 | 0 | (7.) | pH | | | NA | | 0 | 0 | 0 | 0 | (8.) | Heavy Metals | | Iron | mg/l | | 0 | 0 | 0 | 0 | |
14.3. No. of Surface Water monitoring locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 0 | 0 | B | (2.) | COD | | mg/l | | 0 | 0 | B | (3.) | DO | | mg/l | | 0 | 0 | B | (4.) | pH | | mg/l | | 0 | 0 | B | |
14.4. No. of Ambient Noise monitoring locations : 1 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 0 | 0 | 0 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 0 | 0 | 0 | |
14.5. No. of Soil Sample Monitored locations : 0 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | Electric Conductivity | Millisiemens per Centimetre | | 0 | 0 | (2.) | N(Nitrogen) | Millisiemens per Centimetre | | 0 | 0 | (3.) | pH | Millisiemens per Centimetre | | 0 | 0 | (4.) | P(Phosphorus) | Millisiemens per Centimetre | | 0 | 0 | (5.) | K(Potassium) | Millisiemens per Centimetre | | 0 | 0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1.84 To 58.89 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.76 To 60.43 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Delhi Jal Board | 71 | 17 | Copy of Permission Letter | Pipeline | | Others | Supply of DJB | F.2(149)AE-1/WD-13/DDA/(i)/19 | 03 Feb 2009 | 75 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic Waste | 78 | 200 | STP | Others | Reused in site | 43 | 35 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 78 | (b)Total Discharged Water (Kilolitre per Day) | 35 | (c)Total Reused Water (Kilolitre per Day) | 43 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Domestic waste | Municipal Solid Waste | | 227.22 | Tons | 0 | Road | | Authorized Recyclers | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | NOx | | Microgram per Meter Cube | 0 | 0 | 0 | 1 | 0 | (2.) | SO2 | | Microgram per Meter Cube | 0 | 0 | 0 | 1 | 0 | (3.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 1 | 0 | (4.) | PM10 | | Microgram per Meter Cube | 0 | 0 | 0 | 1 | 0 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG Set | LSD | 8 | 0.01 | SO2 | | 1 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 650 | (b)Source | BSES Rajdhani HPower Ltd | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 2 | (e)Stack Height (in m) | 8 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 1.3 | Total Land (ha.) | 1.3 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Residential Area | 1.3 | Total (ha.) | 1.3000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Built Up Area | | 1.3 | Residential Area | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | 0 | 0 | 0 | (2.) | WLS | 0 | 0 | 0 | (3.) | NPA | 0 | 0 | 0 | (4.) | ESAs | 0 | 0 | 0 | (5.) | ESZs | 0 | 0 | 0 | (6.) | Corridors | 0 | 0 | 0 | (7.) | Wildlife Corridors | 0 | 0 | 0 | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Pusa Hill Forest/Central Ridge Reserve forest | 9.78 | 0 | (2.) | Archaeological Sites | | NA | 0 | 0 | (3.) | Defence Installations | | NA | 0 | 0 | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 1.3 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 30 | (b)Permanent Employment-During Operation | 5 | (c)Temporary Employment- During Construction | 10 | (d)Temporary Employment- During Operation | 5 | (e)No. of working days | 365 | (f)Total Manpower | 50 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.21 | (b)Percentage of Total Project Area | 16.15 | (c)No. of Plants to be Planted | 48 | (d)Funds Allocated for Plantation | 0 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Its generates local economic activity including jobs and income generated by construction workers and new residential. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For INFRA-1 |
|
1. | Details of Building Construction: | (a)Maximum Height of the Building (Meters) | 50 | (b)Total No. of Flats to be Build | 226 | (c)No. of Buildings | 5 | (d)Total plot area (sqm) | 13000 | (e)Total built up area (sqm) | 32624.75 | |
|
2. | Foreshore Facilities and/or Marine Disposal: | (a)Whether Project Involves Foreshore Activities and/or marine Disposal? | No | |
|
3. | Rain Water Harvesting: | (a)No. of Storage | 0 | (b)Capacity | 0 | (c)No. of Recharge Pits | 1 | (d)Capacity | 56.52 | |
|
4. | Parking: | (a)Details of 4 Wheeler/ 2 Wheeler Parking | 387 | |
|
5. | Energy Saving Measures: | (a)Source/Mode | Solar Energy | (b)Percentage | 25 | (c)Quantity | 160 | |
|
|
7. Type of Industries to be established with Industrial Estate as per their category A/B |
---|
S. No. | Type of Industry | No. of Units | Category A/B |
---|
NIL | |
8. | Length of the alignment | N/A | |
|
9. | Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass | Details Not Applicable | |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1922/RA0128 | (ii)Name of the EIA Consultant | Shivalik Solid Waste Management Ltd. | (iii)Address | SCO 20-21, 1st Floor, Near Hotel Dolphin, Kalka Shimla, Highway, Dhakoli, Zirakpur, Punjab 140604 | (iv)Mobile No. | 9650601156 | (v)Landline No. | 0176250949 | (vi)Email Id | s.brahma@beil.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | INFRA-1 | (ix)Validity of Accreditation | 16 Feb 2022 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | The Application has been examined.
2. Please address following deficiencies found in your application No. IA/DL/NCP/155068/2020, Dated 31st May:
I. No clarity w.r.t. applicability of EIA Notification 1994, as amended vide notification dated 07.07.2004 on the existing building;
II. Date of completion of existing building and existing built-up area is not available. Submit Building Completion/ occupancy certificate;
III. Information supplied in Form-2 w.r.t. Details of Consent to Operate (CTO) are mismatching (See entries for 9.1/ (i) and (iv));
IV. Copy of the CTO for existing building obtained from Delhi Pollution Control Committee has not been provided;
V. In FORM 2; Funds Allocated towards CER (Corporate Environment Responsibility) (in Crores) are not as per MOEFCC’s Guidelines issued vide Office Memorandum vide F.No. 22-65/2017-IA.III dated 1st May 2018. Submit Revise CER Plan;
VI. Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency has not been attached at SI No. 2 of FORM 2 ( File attached pertains to accreditation certificate of consultant appointed for the proposed project) ;
VII. In FORM 2; Units for Maximum Elevation Above Means Sea Level (AMSL) and Distance of Nearest HFL within the study area from the project boundary, waste water generation and treatment have not been provided. Mismatch in built-up area given at ‘SI 1’ and ‘SI 22’ of FORM 2. Mismatch in Lat./ Long. of the project site given in FORM 2 and FORM-1/1A;
VIII. Justification for the proposal to Install STP of 200KLD, while Waste Water generation is reported to be 87.2 KLD; and
IX. In FORM 2; Incorrect data w.r.t. Period of Base Line Data Collection in FORM 2 (FROM 01 Jan 1900 to 31 Dec 1900). Further, details of Monitoring Locations along with data for Ambient Air Quality, Ambient Noise Ground Water, Surface Water and Soil Quality are not provided.
You may like to submit the revised Application after addressing the above deficiencies. | 01 Jun 2020 | 2. | NA | The correction have been made as per the instruction received | 11 Aug 2020 | 3. | NA | The Application has been examined. Earlier, an EDS was raised on 01.06.2020 and deficiencies found in the application No. IA/DL/NCP/155080/2020, dated 31st May, 2020 were communicated to you.
2. Now, your reply dated 11.08.2020 to the EDS dated 01.06.2020 also suffers from the following deficiencies:
(i) Your letter dated 11.08.2020 uploaded on the central Parivesh portal is addressed to Member Secretary, SEAC, Himachal Pradesh;
(ii) The subject of letter dated 11.08.2020 is regarding withdrawal of TOR Proposal, whereas your application i.e. IA/DL/NCP/155080/2020 is for grant of Environmental Clearance; and
(iii) The letter dated 11.08.2020 has not be signed by the authorised representative of the Project Proponent.
3. In case of intention to withdraw the current application (IA/DL/NCP/155080/2020), the PP shall submit a formal request at the portal in “Withdrawal Section”. Otherwise, address deficiencies as conveyed vide MoEFCC’s EDS dated 01.06.2020. | 14 Aug 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Navneet Kumar | Designation | Secretary | Name of Company (Applicant Name should not be given here) | THE MODEST KETKI COOP. GROUP HOUSING SOCIETY LTD. | Address | Plot No. 8B, Sector - 11, Dwarka, New Delhi |
|