Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Permission for removal/disposal of developmental Waste as rough stone @ 2.12 million TPA in G.O.No.81 (ML Area 251.59 ha) in existing EC under Para 7(ii) of EIA notification, 2006 without change in to
(b)Name of the Company / Organisation CHETTINAD CEMENT CORPORATION PRIVATE LIMITED
(c)Registered Address 4th Floor, Chettinad Towers, 603, Annasalai chennai,,Chennai,Tamil Nadu-600006
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ganesan V
(b)Designation (Owner/ Partner/ CEO) ChiefOperatingOfficer
(c)Address 4th Floor, chettinad Towers, 603, Annasalai, Chennai,,Egmore Numgambakkam,Chennai,Tamil Nadu-600006
(d)Pin code 600006
(e)E-mail envi@chettinadcement.com
(f)STD Code. 44(f)Telephone No. 42988659
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/TN/MIN/155004/2020
(d)Master Proposal Number(Single Window) SW/155003/2020
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. khasra map is given
(b)Pincode 624703
(c)Bounded Latitudes (North)
From
Degree 10.70077778
Minutes
Second
From
Degree 10.72363889
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 78.05222222
Minutes
Second
From
Degree 78.07527778
Minutes
Second
(e)Survey of India Topo Sheet No. 58J2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 248
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 248
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Tamil Nadu
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chennai
(iii)Letter No. EP/12.1/2010-11/9/TN/1544
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 19 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Limestone297000002970000Tons per Annum(TPA)Conveyor Belt.
(2.)Area251.590251.59Hectares(ha)Others.
(3.)Rough Stone021000002100000Tons per Annum(TPA)Road.
(4.)waste from excavated area398000003980000Tons per Annum(TPA)Road,Otherswaste will be reduced from 3.98 MTPA to 1.88 MTPA
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Wagon Drill4-4-
(2.)Compressor4-4-
(3.)Taurus dumper15-15-
(4.)Water bouser1-1-
(5.)Pumps2-2-
(6.)Mobile Lighting tower1-1-
(7.)Tractor1-1-
(8.)Hydraulic Excavator3-3-
(9.)Jeep1-1-
(10.)Dozer2-2-
(11.)Terminator/Rock Breaker2-2-
(12.)Explosive Van1-1-
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 14 Aug 2018
(iv)Valid Upto 30 Jun 2020
(v)File No. T2/TNPCB/F.0910DGL/RL/DGL/W/2018
(vi)Application No. -
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 0.35
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.20
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.0052
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.10
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 378718
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 378718
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HSD378718OthersLiter per dayOpen marketRoad4 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 110 To 120
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 100 To 110
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersHarvested rain water from Existing Mine Pits84.50 Not Appliacble PipelineOthersPipelineNil31 May 202084.5
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic8.088.08Soak pit via septic tankOthersSoak Pit via septic tank08.08
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 8.08
(b)Total Discharged Water (Kilolitre per Day) 8.08
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)WasteOthersRough stone from waste dump2110000Tons0RoadOthersdisposed as developmental Waste as rough stone.
(2.)wasteOtherswaste from excavated area1870000Tons0RoadOthersdumping within lease area
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube2401.425.580
(2.)PM10Microgram per Meter Cube6001.8561.86100
(3.)PM2.5Microgram per Meter Cube2900.7429.7560
(4.)SO2Microgram per Meter Cube1901.920.9180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)--00Others..
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1500
(b)Source captive power plant
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 35.30
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 216.29
    Total Land (ha.) 251.59
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 69.96
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : excavated area, built up and greenbelt 181.63
    Total (ha.) 251.5900
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OB Dump Area69.96-
(2.)Quarry Area99.2954.35 ha will be as water reservoir
(3.)Built Up Area10.74office, workshop, crusher and screening plant
(4.)Othersgreenbelt, safety zone, railway and undisturbed71.6greenbelt, safety zone, railway and undisturbed
Total (ha.) 251.59
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone00
(2.)WLSNone0.
(3.)ESAsNone0.
(4.)Wildlife CorridorsNone0-
(5.)ESZsNone0-
(6.)CorridorsNone0-
(7.)NPANone0.
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestThoppasamymalai RF and Kadavur RF8.0.
(2.)Archaeological SitesNone0.
(3.)Defence InstallationsNone0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 251.59
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kodavanar river
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 9.8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 33
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 33
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt57.0538.0595.1
(2.)Percentage of Total Project Area22.615.1237.72
(3.)No. of Plants9500063000158000
(4.)Funds Allocated300000200000500000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalUtilisation of waste dump as rough stone for the purpose of mineral conservation. Removal of these dumps mitigate the environmental problems associated with fresh mining of rough stone by elimination of Drilling & Blasting, etc
(2.)SocialSocial development will be done
(3.)FinancialProject is being/will contribute additional revenue to the State and Central Govt. in the form of royalty, cess and other taxes etc
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 2
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)Rough StoneMinor
(2.)LimestoneMajor
2.
Mine Capacity in ROM (Run of Mine) 2.97 + 2.10
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. TN/DGL/MP/LST/2048.MDS
(b)Date of Approval 17 Jul 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 251.59
(f)Approved Capacity 3000000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 121.164
(b)Mineable Reserves (Million Ton) 96.603
(c)Extractable Reserves(Million Ton) 96.603
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral cement grade and for stone crusher
(f)Stripping Ratio 1 : 1.34
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 45 for mine bench and 1 in 16 for haul road
(i)Mining Method Opencast
(j)Life of Mine (Years) 32
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 251.59
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof Mining lease has already been granted
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 251.59
(iii)Validity of the lease deed From : 07 Sep 2001 To : 06 Sep 2021
(iv)Date of Execution of Mining Lese 13 Aug 2003
(v)Reference Number -
(d)Whether Lease Deed Renewed ? Yes
     8.1.    Earlier Renewals:
S. No.Lease Details Date of Renewal Period Copy of Earlier Lease Letter No.Area Remarks
(1.)Initial 01 Jan 1900 From : 07 Sep 1965 To : 06 Sep 1985 Copy of Earlier LeaseG.O No 1307 251.59 -
(2.)Renewal 17 Jul 1985 From : 07 Sep 1985 To : 06 Sep 1991 Copy of Earlier LeaseG.O No 636 251.59 -
(3.)Renewal 13 Aug 2003 From : 07 Sep 2001 To : 06 Sep 2021 Copy of Earlier LeaseG.O.No. 81 251.59 -
(4.)Initial 01 Jan 1900 From : 24 Dec 2018 To : 31 Mar 2030 Copy of Earlier LeaseGO 158 38.05 -
(5.)Renewal 25 Nov 1991 From : 07 Sep 1991 To : 06 Sep 2001 Copy of Earlier LeaseG.O. No. 477 251.59 -
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 18
(ii)Total Area (in Hectare) 68.54
(iii)Height (in meter) 9.66
(iv)Quantity (in Million Cubic meter) 14.18
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 00
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 99.29
(b)Depth (in meter) 100
(c)Volume (in Million Cubic meter) 99.29
12.
Details of Quarry:
(a)Final Void of 54.35 (hectare) at a Depth of 100 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 99.29
13.
Details of Transportation:
(a)In Pit/Underground to Surface Bu Dumpers/Truck
(b)Surface to Siding/Loading Loading will be done by Hydraulic Excavators
(c)Transportation / Conveyor Details Transportation of limestone from mine to plant wil
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)WASTE LAND000
(2.)AGRICULTURE LAND35.30035.3
(3.)GRAZING LAND000
(4.)SURFACE WATER BODIES000
(5.)SETTLEMENTS000
(6.)OTHERS(Specify)Poramboke land216.290216.29
(7.)FOREST LAND000
TOTAL251.590251.59
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY054.3544.9499.29
(2.)INTERNAL OB DUMPS31.910031.91
(3.)ROADS003.853.85
(4.)OtherUndisturbed land0014.5514.55
(5.)TOP SOIL STORAGE0000
(6.)GREEN BELT95.10095.1
(7.)EXTERNAL OB DUMPS0000
(8.)BUILT UP AREA (COLONY/OFFICE)006.896.89
(9.)VIRGIN AREA0000
TOTAL127.0154.3570.230251.59
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 31.91
(c)Quarry(in hectare) 99.29
(d)Safety Zone(in hectare) 95.1
(e)Final Void of 54.35 (hectare) at a Depth of 100 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2000
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 25.29
(h)Total afforestation plant (in hectare) 127.01
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)19939401.141.0038041.0037000
(2.)19949501.141.0037450.8916850
(3.)19979801.141.0712341.0704990
(4.)20010201.140.9653170.9615780
(5.)20020301.141.0076931.0027570
(6.)2012132.973.02.9823201.8422440
(7.)2013142.973.03.1589541.2626140
(8.)19959601.140.9603700.9557960
(9.)20030401.141.1298241.11289910
(10.)20040501.141.0251821.0219230
(11.)20060701.142.0240001.1386920
(12.)2014152.973.03.0033121.1768320
(13.)2016172.973.02.9976091.2494550
(14.)2018192.973.03.0032731.9820480
(15.)2019202.973.03.0006802.2443640
(16.)19989901.141.0331951.0331950
(17.)2000200101.141.1166771.1079990
(18.)20050601.141.1209481.1191330
(19.)2015162.973.03.0000001.0890070
(20.)2007082.02.02.0240001.2581590
(21.)2008092.02.02.0280001.3285420
(22.)2009102.02.02.9700001.2537780
(23.)2010112.972.02.9700001.4922480
(24.)2011122.972.03.0159261.6343950
(25.)2017182.973.02.9995761.2957050
(26.)19969701.140.9451580.9448570
(27.)1999200001.141.1567891.1390900
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0069
(ii)Name of the EIA Consultant JM EnviroNet Pvt Ltd
(iii)Address 202-A, ABW Tower, MG Road, IFFCO Chowk, Sector 25, Gurugram (Haryana) – 122001
(iv)Mobile No. 9509267011
(v)Landline No. 0124414192
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 30 Jun 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report Copy of District Survey Report
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data Copy of Replenishment Study Report & Baseline Survey Data
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAOn scrutiny of application, 1) Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency is not proper as the Applicant himself has given authorization to another person in the uploaded letter. 2) Copies of all Consent to operate obtained since inception are not enclosed, only latest CTO enclosed which expired on 31.03.2020 3) PP has not uploaded copy of approved mining plan. Please reply to the the above points 06 Jun 2020
2.NAThe correction have been made as per the instruction received 08 Jun 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe are herewith submitting ADS reply 31 Jul 2020
2.NA

the proposal is deferred.

01 Jul 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantGanesan V
DesignationChiefOperatingOfficer
Name of Company (Applicant Name should not be given here)CHETTINAD CEMENT CORPORATION PRIVATE LIMITED
Address4th Floor, Chettinad Towers, 603, Annasalai chennai
Print