Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Manufacturing of Asbestos Cement Sheets( Corrugated & Plain) of Capacity 50,000 TPA & Non Asbestos Flat sheets of Capacity 30,000 TPA of M/s JRT Industries LLP
(b)Name of the Company / Organisation JRT INDUSTRIES LLP
(c)Registered Address H.No. 62 , Tarun Nagar, Bye lane 2 , GS road, Kamrup,,Kamrup,Assam-781005
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant DEEPAK KAYAL
(b)Designation (Owner/ Partner/ CEO) PARTNER
(c)Address HOUSE NO. 62, BY LANE NO.2, ABC ,TARUN NAGAR , GS ROAD, DISTRICT KAMRUP , STATE ASSAM,,Guwahati,Kamrup,Assam-781005
(d)Pin code 781005
(e)E-mail sonali.jumbogroup@gmail.com
(f)STD Code. 361(f)Telephone No. 2465630
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity4(c) Asbestos milling and asbestos based products
Minor Activity
(b)Category A
(c)Proposal Number IA/AS/IND/99846/2019
(d)Master Proposal Number(Single Window) SW/154810/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 43,24,25,122,149,580,195,147,522,353,439,392
(b)Pincode 781101
(c)Bounded Latitudes (North)
From
Degree 26.239983
Minutes
Second
From
Degree 26.242111
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 91.700797
Minutes
Second
From
Degree 91.7035
Minutes
Second
(e)Survey of India Topo Sheet No. 78N/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 64
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4.5
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Assam
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)AssamKamrupGuwahati
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/161/2019-IA-II(I)
(b)Date of Apply of TOR 19 Mar 2019
(c)Date of Issue of TOR / Standard ToR 20 May 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 Nov 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :07 Dec 2019
Distance of Public Hearing Venue from the Proposed Project :0.8
Sri Sri Ganesh MandirPrathamikBidyalaycampus,Vill. HaluguriChowk, Sila, P.O. Changsari, Dist. Kamrup, Assam.
State :Assam
District :Kamrup
Tehsil :Guwahati
Village :Sila
70Environmental problems, effect on health etc., Waste water discharge, Employment to locals, To carry out some work for the interest of the locality, Construction and renovation of temple etc..OthersAddl. District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Bag Shredder1 setMotor 15 hp Shredder Blower
(2.)Waste Recycling System1 setStirrer Motor 5 hp Pump 67 cum/Hr. Motor 7.5 hp
(3.)Wet Ball Mill1 setGear box Ratio 25:1 Motor 25 hp
(4.)Hydraulic Power Pack2 setMotor 40 hp Pump PVR150-FF-140
(5.)Corrugated Templates2000 No.sLength 6200 mm Width 1200 mm
(6.)Automatic Bag Opener1 setMotor 5 hp / 2 hp HSS Cutter 2 Nos.
(7.)E.R. Mill1 setMotor 50 hp`` Gear box Ratio 30:1
(8.)Fibre Storage Tank1 setGeared Motor 10 hp Paddle Screw 2 Nos.
(9.)Hydro disintegrator1 setMotor 40 hp Metso Pump 100 cum/Hr.
(10.)Beater tank1 setmotor 25hp
(11.)Agitator cum Storage mixer1 setMotor 20 hp Gear Box Ratio 50:1
(12.)Agitator cum Storage mixer1 setMotor 20 hp Gear Box Ratio 50:1
(13.)Hydro Pulper and Pulp Slurry Storage Tank1 setSlusher Motor 75 hp Stirrer Motor 5hp
(14.)Cement Storage & Feeding System1 setScreen Motor 5 hp
(15.)Fly ash storage & slurry/feeding Sys1 setGeared Motor 5 hp Blower 75 hp
(16.)Fly ash storage & slurry/feeding Sys1 setGeared Motor 5 hp Blower 75 hp
(17.)Waste Desolving System1 SetStirrer Motor 15 hp Pump Metso HM-100 Motor 30 hp
(18.)Hatscheck Machine1 setComplete with Main Drive 125hp
(19.)Vacuum Pump3 setMotor 75 hp Complete with Water Separator Pump and
(20.)1st Conveyor1 setGeared Motor 5 hp
(21.)2nd Conveyor1 setGeared Motor 5 hp Ratio 8:14 15 m long PVC Belt
(22.)Atmospheric Corrugator1 setHydraulic Cylinder Operated
(23.)Electrical Control System1Complete with Contactors, Relay, MCB
(24.)Moulding Cutting Press1 setHydraulic Operated
(25.)Pulp Slurry Refiner1 SETDouble Disc Refiner 150 hp motor
(26.)Weighing System /Fibre Hopper1 setLoad Cell 250 kg x 4 Pneumatically Operated
(27.)Waste Shredder1 setGeared Motor 10 hp Ratio 46:3
(28.)Pre-mix Tank1 setGeared Motor 5 hp Ratio 20:2
(29.)High Pressure Pump2 setMotor 50 hp Max Pressure 5.0 bar
(30.)EOT Crane 10 Ton Capacity1 setCT 2 hp LT 5 hp Hoist 15 hp
(31.)Agitator cum Storage mixer1 setMotor 20 hp Gear Box Ratio 50:1
(32.)Dust Collectors 3 Nos.3 setMotor 15 hp
(33.)Back Water Pump1 setMotor 75 hp
(34.)D.G. Set3 set600 KVA 320 KVA With Enclosures
(35.)Cone Tanks 4 Nos.4 No.sCap 85 KL with overflow and blow down arrangements
(36.)Air Compressor3 setsIR Screw type Motor 40 hp
(37.)Hydraulic Power Pack2 setMotor 40 hp Pump PVR150-FF-140
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Non Asbestos flat Sheets30000Tons per AnnumRoad,Rail
(2.)Asbestos Corrugated Sheets40000Tons per AnnumRoad,Rail
(3.)Asbestos Plain Sheets10000Tons per AnnumRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 71.75
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.05
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.445
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.125
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 64200
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 64200
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Asbestos Fibre Chrysotile4600Tons per AnnumRussiaRoad,Rail,Otherssea1000 OthersIntentCopy of Linkage
(2.)Cement36000Tons per Annumlocal industryRoad100 OthersIntentCopy of Linkage
(3.)Fly ash20000Tons per AnnumNTPC- Assam and West BengaRoad,Rail1000 OthersIntentCopy of Linkage
(4.)pulp1000Tons per AnnumLocal SuppliersRoad15 OthersIntentCopy of Linkage
(5.)Virgin pulp2600Tons per AnnumTasmania, ChileRoad,Rail,Otherssea1000 OthersIntentCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube15.56.0314.380
(2.)PM10Micro Gram per Meter Cube70.427.6770.1100
(3.)PM2.5Micro Gram per Meter Cube56.1315.4652.860
(4.)NOxMicro Gram per Meter Cube29.87.128.880
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l256224200600
(2.)Fluoridemg/l0.650.4511.5
(3.)Heavy MetalsLEADmg/l0.010.010.010.01
(4.)Chloridesmg/l46282501000
(5.)OthersNitratemg/l15.610.964545
(6.)pHNA7.447.026.58.5
(7.)TDSmg/l6945355002000
(8.)TSSmg/l0000
(9.)Heavy MetalsLEADmg/l0.010.010.010.01
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.867.77C
(2.)DOmg/l5.55.1C
(3.)BODmg/l22C
(4.)CODmg/l00C
(5.)OthersTDSmg/l735632C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))65.950.175 (Industrial) and 55 (Residential)
(2.)Leq(Night)A-weighted decibels(dB(A))52.441.770 (Industrial) and 45 (Residential)
    14.5.     No. of Soil Sample Monitored locations : 3
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare180148
(2.)pH6.86.35
(3.)Electric ConductivityOthersµ mhos/cm310234
(4.)P(Phosphorus)Kilogram per hectare13096
(5.)K(Potassium)Kilogram per hectare11878
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 6.55
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.5 To 4.55
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater1000.15Copy of Permission LetterPipelineTube WellNOC.No. –CGWA/NOC/IND/ORIG/2020/816703 Jul 2020100
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic,office,canteen1515STPGreen Belt Renewal Plant15
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 15
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 15
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Hard broken piecesOthersdamages rejects28.82Tons0RoadOthers100% Recycled in process
(2.)Process sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)13.74Tons0Pipe ConveyorOthers100% Recycled in process
(3.)Empty Fibre bagsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)6.86Tons0Conveyor BeltOthers100% Recycled in process
(4.)FLY ASH DUSTFly Ash0.24Tons0Conveyor BeltOthers100% Recycled in process
(5.)Fibre dustHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.07Tons0Conveyor BeltOthers100% Recycled in process
(6.)Cement dustHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.29Tons0Conveyor BeltOthers100% Recycled in process
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube11.36.40.0311.3480
(2.)PM10Microgram per Meter Cube62.183.50.0062.19100
(3.)PM2.5Microgram per Meter Cube44.125.40.1944.3160
(4.)NOxMicrogram per Meter Cube26.56.40.0326.5480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Asbestos fibre dust collectorNA190.35OthersPM0.1
(2.)Cement dust collectorNA190.35OthersPM0.15
(3.)Fly ash dust collectorNA190.35OthersPM0.14
(4.)DG SETDiesel190.2OthersPM0.89
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1500
(b)Source APDCL & Solar
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 900 KVA & 320 KVA
(e)Stack Height (in m) 19
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 4.34
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 4.34
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : PVT NON AGRICULTURE 4.34
    Total (ha.) 4.3400
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.59
(2.)Green belt1.43
(3.)Built Up Area1.5Office,stock yard,warehouse
(4.)Othersincludes parking,silos,roads0.82
Total (ha.) 4.34
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNOT APPLICABLE0NOT APPLICABLE
(2.)ESAsNOT APPLICABLE0NOT APPLICABLE
(3.)ESZsNOT APPLICABLE0NOT APPLICABLE
(4.)CorridorsNOT APPLICABLE0NOT APPLICABLE
(5.)Critically Polluted AreaNOT APPLICABLE0NOT APPLICABLE
(6.)NPANOT APPLICABLE0NOT APPLICABLE
(7.)Wildlife CorridorsNOT APPLICABLE0NOT APPLICABLE
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNOT APPLICABLE0NOT APPLICABLE
(2.)ForestNOT APPLICABLE0NOT APPLICABLE
(3.)Defence InstallationsNOT APPLICABLE0NOT APPLICABLE
(4.)OthersRiverBrahamaputra river5.5South direction
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.34
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NIL
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Brahamputra river
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 5.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 50
(e)No. of working days 335
(f)Total Manpower 250
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.43
(b)Percentage of Total Project Area 32.95
(c)No. of Plants to be Planted 2150
(d)Funds Allocated for Plantation 1000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialState will earn revenue which will be utilised for development of the area.
(2.)EnvironmentalPP will take care of the environment by regular monitoring of environmental parameters as per plan and take mitigative measures as & when required.
(3.)SocialTotal direct & indirect employment generation will be approx. 100 & 150 respectively. The work men will be employed from nearby local villages at different levels depending on availability.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/SA 95
(ii)Name of the EIA Consultant Ecomen Laboratories Pvt. Ltd.
(iii)Address Flat No. 8, 2nd Floor , ArifChamber –V, Sector –H, Aliganj, Lucknow-226024
(iv)Mobile No. 9415410773
(v)Landline No. 0522276188
(vi)Email Id ravi.bhargava@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 20 Sep 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAProposal is returned due to the following shortcomings: i. Ground water withdrawal permission may be submitted. ii. Occupational Risk assessment is inadequate. Accidental releases were not envisaged and corresponding risk was not assessed. iii. Risk Assessment for containment failure of HSD tank and related safety features /procedures as per OISD guidelines. iv. Topo sheet loaded seems to be not covered 10 km aerial distance around project site. v. Kml file is not accessible. Appropriate KML file shall be uploaded. vi. Complete list of attendees is not attached with proceedings of Public Hearing. vii. Advertisement/ Public Notice in the daily in local language for Public Hearing is not attached. 16 Jun 2020
2.NAProposal is returned due to the following shortcomings: i. Ground water withdrawal permission may be submitted. ii. Occupational Risk assessment is inadequate. Accidental releases were not envisaged and corresponding risk was not assessed. iii. Risk Assessment for containment failure of HSD tank and related safety features /procedures as per OISD guidelines. iv. Topo sheet loaded seems to be not covered 10 km aerial distance around project site. v. Kml file is not accessible. Appropriate KML file shall be uploaded. vi. Complete list of attendees is not attached with proceedings of Public Hearing. vii. Advertisement/ Public Notice in the daily in local language for Public Hearing is not attached. 16 Jun 2020
3.NAThe correction have been made as per the instruction received 08 Jul 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDEEPAK KAYAL
DesignationPARTNER
Name of Company (Applicant Name should not be given here)JRT INDUSTRIES LLP
AddressH.No. 62 , Tarun Nagar, Bye lane 2 , GS road, Kamrup