1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Capacity Enhancement of Anandavadi Limestone Mines | (b)Name of the Company / Organisation | TANCEM | (c)Registered Address | Ariyalur,,Ariyalur,Tamil Nadu-621729 | (d)Legal Status of the Company | State Government | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | T Ravichandran | (b)Designation (Owner/ Partner/ CEO) | DGM | (c)Address | Ariyalur,,Perambur Purasaivakkam,Chennai,Tamil Nadu-621729 | (d)Pin code | 621729 | (e)E-mail | limetancem2018@gmail.com | (f)STD Code. | 4329(f)Telephone No. | 228531 | (g)Fax No. | 228776 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(a) Mining of minerals
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/TN/MIN/153373/2018 | (d)Master Proposal Number(Single Window) | SW/153331/2020 | (e)EAC concerned (for category A Projects only) | Non-Coal Mining | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | S.F No. 349, 350, 351 etc. | (b)Pincode | 621729 | (c)Bounded Latitudes (North) | | From | | Degree | 11.18667 | Minutes | | Second | | From | | Degree | 11.19083 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 79.1867 | Minutes | | Second | | From | | Degree | 79.19889 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 58M/4 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 102 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Tamil Nadu | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11015/173/2018-IA.II(M) | (b)Date of Apply of TOR | 06 Oct 2018 | (c)Date of Issue of TOR / Standard ToR | 26 Feb 2019 | (d)Date of Apply of EC | | (e)Date of Issue of EC | | (f)Previous TOR Letter | Copy of Previous TOR letter | (g)Previous EC Letter | NA | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 24 Oct 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| At project site | State : | Tamil Nadu | District : | Ariyalur | Tehsil : | Sendurai | Village : | Anandavadi |
| 168 | Related to the employment | District Collector | | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Chennai | (iii)Letter No. | 1136 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Aug 7 2019 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | 1.5MTPA/110.685 | 0.26 | 1.24 | 1.5 | Others | MTA | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Cement Plant | - | - | - | - | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | Copy of Consent to Operate | (iii)Date of Issue | 28 Aug 2020 | (iv)Valid Upto | 31 Mar 2022 | (v)File No. | F.0323ARY/RS/DEE/TNPCB/ARY/W/2020 | (vi)Application No. | 2008132669783 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 1 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.33 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.01 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.0593 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | 0 | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | NA its a mining Project | 0 | Tons per Annum | | 0 | Road | | 0 | Captive | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 88 | 70 | 87.08 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 52 | 36 | 51.54 | 60 | (3.) | SO2 | | Micro Gram per Meter Cube | 15 | 7 | 14.54 | 80 | (4.) | NOx | | Micro Gram per Meter Cube | 26 | 15 | 26 | 80 | |
14.2. No. of Ground Water monitoring locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.72 | 7.14 | 6.5 | 8.5 | (2.) | TDS | | | mg/l | | 623 | 338 | 200 | 600 | (3.) | Fluoride | | | mg/l | | 0.76 | 0.48 | 1 | 1.5 | (4.) | Heavy Metals | | Arsenic | mg/l | | 0.01 | 0.01 | 0.01 | 0.05 | (5.) | Others | lead | | mg/l | | 0.01 | 0.01 | 0.01 | 0.05 | (6.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (7.) | Total Hardness | | | mg/l | | 341 | 147 | 500 | 2000 | (8.) | Chlorides | | | mg/l | | 166 | 52 | 2500 | 1000 | |
14.3. No. of Surface Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.74 | 7.51 | D | (2.) | BOD | | mg/l | | 12 | 6 | D | (3.) | Others | Total Hardness | mg/l | | 246 | 168 | D | (4.) | DO | | mg/l | | 7.1 | 5.4 | D | (5.) | COD | | mg/l | | 30 | 20 | D | |
14.4. No. of Ambient Noise monitoring locations : 6 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 56.3 | 48.3 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 43.4 | 38.1 | 45 | |
14.5. No. of Soil Sample Monitored locations : 6 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 7.46 | 6.92 | (2.) | P(Phosphorus) | Others | mg/100gm | 0.92 | 0.78 | (3.) | K(Potassium) | Others | mg/100gm | 2.1 | 1.9 | (4.) | N(Nitrogen) | Others | mg/100gm | 22.4 | 18.4 | (5.) | Electric Conductivity | Others | micro mhos/cm | 362 | 293 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1.1 To 8.55 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1.1 To 6.8 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Mine reservoir and water tanker | 20.7 | 15 | Not Appliacble | modeOthers | water tanker | Others | Pump | none | 28 Oct 2020 | 0 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | 0 | 0 | 0 | Use for Green Belt | Green Belt Renewal Plant | | 0 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 0 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Domestic Waste | Municipal Solid Waste | | 5.42 | Tons | 0 | Road | | Others | Muncipal body will collect on daily basis. | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | Others(Specify) | CO | Microgram per Meter Cube | 0 | 0 | 0 | 0.1 | 0 | (2.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 0.1 | 0 | (3.) | NOx | | Microgram per Meter Cube | 26 | 0 | 1.7 | 27.74 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 88 | 0 | 3.86 | 91.87 | 100 | (5.) | SO2 | | Microgram per Meter Cube | 18 | 0 | 1.53 | 19.54 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 0 | 0 | 0 | 0 | Others | None | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 0 | (b)Source | 0 | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 0 | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 18.22 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 92.465 | Total Land (ha.) | 110.685 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 5 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 4.895 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Virgin land | 100.795 | Total (ha.) | 110.6900 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Safety Zone | | 2.50 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | ESZs | None | 0 | None | (2.) | Wildlife Corridors | None | 0 | None | (3.) | Critically Polluted Area | None | 0 | None | (4.) | WLS | None | 0 | None | (5.) | ESAs | None | 0 | None | (6.) | Corridors | None | 0 | None | (7.) | NPA | None | 0 | None | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | None | 0 | None | (2.) | Defence Installations | | None | 0 | None within 10 Km area | (3.) | Others | None | None | 0 | None | (4.) | Forest | | Vannankurichi RF | 0 | NOC from the DFO has been obtained | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Patta Land has been acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Pavocristatus(Indian Peafowl) | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 5 | (iii)Period of Implementation | As per direction of DFO | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Seasonal nallah flowing from NNE to SW | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | PeriyaEri | (ii)Direction of Water Bodies in Buffer Area | North West | (iii)Distance of Water Bodies in Buffer Area | 1 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 7 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 34 | (e)No. of working days | 300 | (f)Total Manpower | 41 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 0 | 36.5 | 36.5 | (2.) | Percentage of Total Project Area | 0 | 33 | 33 | (3.) | No. of Plants | 0 | 54750 | 54750 | (4.) | Funds Allocated | 0 | 32.85 | 32.85 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | High purity limestone is essential for soda ash manufacturing. | (2.) | Social | Local Villagers are getting direct and indirect benefit by employment due to the proposed project. | (3.) | Financial | Royalty will be submitted to state government. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Non-Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | Limestone | Minor | |
|
2. | Mine Capacity in ROM (Run of Mine) | 413030 | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | TN/ALR/MP/LST/2050.MDS | (b)Date of Approval | 24 Jul 2018 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | IBM | (e)Approved Mining Lease Area | 110.685 | (f)Approved Capacity | 15 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 21.70 | (b)Mineable Reserves (Million Ton) | 18.49 | (c)Extractable Reserves(Million Ton) | 3.210 | (d)Percent(%) of Extraction | 59 | (e)Grade of Coal /Ore /Mineral | Limestone | (f)Stripping Ratio | 1 : 0.52 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | Not applicable | (h)Average Gradient(Degree) | 45 | (i)Mining Method | Opencast | (j)Life of Mine (Years) | 13 | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | No | (b)Whether it is proposed to install crusher within the mining lease area | No | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | No | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 110.685 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | No | (i)Reason thereof | Goverment Order has been alloted | (c)Whether Lease Deed Executed ? | Yes | (i)Copy of Executed Lease deed valid as on Date | Copy of Executed Lease deed | (ii)Provide area in Hectare as per executed lease deed (initial) document | 110.685 | (iii)Validity of the lease deed | From : 23 Sep 1998 To : 15 Mar 2050 | (iv)Date of Execution of Mining Lese | 16 Mar 2000 | (v)Reference Number | 00DD687496 | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | • As per the section 8 A (5) of new MMDR amendment | |
|
9. | OB (Over Burden) Management: | (a) Details of External Dumps: | (i)No. of OB Dumps | 0 | (ii)Total Area (in Hectare) | 0 | (iii)Height (in meter) | 0 | (iv)Quantity (in Million Cubic meter) | 0 | (v)No. of year back fill up | 0 | (b) Details of Internal Dumps: | (i)No. of Internal Dumps | 2 | (ii)Total Area (in Hectare) | 6.72 | (iii)Height (in meter) | 18 | (iv)Quantity (in Million Cubic meter) | 8.85 | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 0 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 0 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | 15.045 | (b)Depth (in meter) | 15 | (c)Volume (in Million Cubic meter) | 3.503 | |
|
12. | Details of Quarry: | (a)Final Void of 15.045 (hectare) at a Depth of 15 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 15.045 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | Manpower | (b)Surface to Siding/Loading | Manpower | (c)Transportation / Conveyor Details | By trolley/trusks | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | FOREST LAND | | 0 | 0 | 0 | (2.) | OTHERS(Specify) | Area under mining,Top soil storage, dump storage | 4.895 | 0 | 4.895 | (3.) | SURFACE WATER BODIES | | 0 | 0 | 0 | (4.) | SETTLEMENTS | | 0 | 0 | 0 | (5.) | AGRICULTURE LAND | | 5 | 0 | 5 | (6.) | WASTE LAND | | 100.790 | 0 | 100.79 | (7.) | GRAZING LAND | | 0 | 0 | 0 | |
TOTAL | 110.685 | 0 | 110.685 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | INTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (2.) | ROADS | | 0 | 0 | 0.5 | | 0.5 | (3.) | BUILT UP AREA (COLONY/OFFICE) | | 0 | 0 | 1 | | 1 | (4.) | VIRGIN AREA | | 0 | 0 | 0 | | 0 | (5.) | TOP SOIL STORAGE | | 0 | 0 | 0 | | 0 | (6.) | EXTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (7.) | GREEN BELT | | 48.5 | 0 | 0 | | 48.5 | (8.) | Other | None | 0 | 0 | 0 | | 0 | (9.) | EXCAVATION/QUARRY | | 0 | 0 | 60.685 | | 60.685 | |
TOTAL | 48.5 | 0 | 62.185 | 0 | 110.685 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | 0 | (b)Internal Dump(in hectare) | 88.51 | (c)Quarry(in hectare) | 60.685 | (d)Safety Zone(in hectare) | 2.50 | (e)Final Void of 5.99 (hectare) at a Depth of 15 meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | 1500 | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | 4.895 | (h)Total afforestation plant (in hectare) | 36.5 | |
|
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 2005 | 0.26 | 0.26 | 0.26 | 0.01000 | 0 | (2.) | 2002 | 0.26 | 0.26 | 0.26 | 0 | 0 | (3.) | 2000 | 0.26 | 0.26 | 0.26 | 0 | 0 | (4.) | 2001 | 0.26 | 0.26 | 0.26 | 0.500020 | 0 | (5.) | 2003 | 0.26 | 0.26 | 0.26 | 0 | 0 | (6.) | 2015 | 0.26 | 0.26 | 0.26 | 0 | 0 | (7.) | 2007 | 0.26 | 0.26 | 0.26 | 0.054893670 | 0 | (8.) | 2008 | 0.26 | 0.26 | 0.26 | 0.055057900 | 0 | (9.) | 2004 | 0.26 | 0.26 | 0.26 | 0.01000 | 0 | (10.) | 2006 | 0.26 | 0.26 | 0.26 | 0.6995999 | 0 | (11.) | 2016 | 0.26 | 0.26 | 0.26 | 0 | 0 | (12.) | 2020 | 0.26 | 0.26 | 0.26 | 0.175463240 | 0 | (13.) | 2009 | 0.26 | 0.26 | 0.26 | 0.059994900 | 0 | (14.) | 2010 | 0.26 | 0.26 | 0.26 | 0.039701870 | 0 | (15.) | 2011 | 0.26 | 0.26 | 0.26 | 0 | 0 | (16.) | 2018 | 0.26 | 0.26 | 0.26 | 0.02599 | 0 | (17.) | 2012 | 0.26 | 0.26 | 0.26 | 0 | 0 | (18.) | 2013 | 0.26 | 0.26 | 0.26 | 0 | 0 | (19.) | 2014 | 0.26 | 0.26 | 0.26 | 0 | 0 | (20.) | 2017 | 0.26 | 0.26 | 0.26 | 0.058514560 | 0 | (21.) | 2019 | 0.26 | 0.26 | 0.26 | 0.064048300 | 0 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/SA083 Rev 01 | (ii)Name of the EIA Consultant | Mantec Consultants PVt. Ltd. | (iii)Address | D- 36, Sector – 6, Noida – 201301 | (iv)Mobile No. | 9871095806 | (v)Landline No. | 0120421500 | (vi)Email Id | envmantec@yahoo.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Non-Coal Mining | (ix)Validity of Accreditation | 20 Dec 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | On scrutiny of the proposals, the following observations were made: ) Copy of advertisement for PH is not clear w.r.t. Newspaper it was published. 2) Attendance Sheet is not enclosed with PH proceedings 3) PP has not uploaded CTO copies for the period from 2015 to 2019 4) Conservation plan for Schedule-I Species is not approved by competent authority 5) Copy uploaded w.r.t. Eco-sensitive Zone is in native language. Translated copy not provided. 6) Copy of lease deed not illegiable 7) Certificate of Accreditation certified by QCI/NABET expired on 18.04.2020 8) EIA Report is incomplete (Does not have 12 chapter format)
Further, it has observed that the proposal was considered in EAC meeting held on 15.11.2018 for grant of ToR and Committee deferred the proposal for want of requisite information. Please submit the details of EAC meeting wherein tor was recommended and lToR letter issued by the Ministry. You are requested to get the ToR first issued by the ministry and the cab be made application for EC as per the ToRs issued by the ministry but not with Standard ToR as per the provisions of EIA Notification, 2006. | 05 Jun 2020 | 2. | NA | The correction have been made as per the instruction received | 11 Jul 2020 | 3. | NA | It has observed that EDS raised previously is not complied fully. Point wise reply to EDS was not provided. SL No 18 of Form-II is not filled correctly, authenticated list of Schedule-1 Species needs to be submitted. Based on the authenticated list conservation plan needs to be prepared and proof of its submission to CWLW needs to be submitted, conservation plan approved by DFO is not acceptable. Annexure to EIA Report is not uploaded. Further, it has observed that the proposal was considered in EAC meeting held on 15.11.2018 for grant of ToR and Committee deferred the proposal for want of requisite information. Please submit the details of EAC meeting wherein tor was recommended and ToR letter issued by the Ministry. You are requested to get the ToR first issued by the ministry and then made application for EC as per the ToRs issued by the ministry but not with Standard ToR as per the provisions of EIA Notification, 2006. | 16 Jul 2020 | 4. | NA | The correction have been made as per the instruction received | 28 Oct 2020 | 5. | NA | Reply of EDS letter not found enclosed. | 09 Nov 2020 | 6. | NA | The correction have been made as per the instruction received | 10 Nov 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | T Ravichandran | Designation | DGM | Name of Company (Applicant Name should not be given here) | TANCEM | Address | Ariyalur |
|