Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Pesticide Intermediates and Specialty Chemicals in Existing Unit
(b)Name of the Company / Organisation ACETOCHEM PRIVATE LIMITED
(c)Registered Address Plot No. 274/3/1, GIDC Estate, Pandesara,,Ta. Chorasi, Dist. Surat, Gujarat,Surat,Gujarat-394221
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Bansibhai D Patel
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Plot No. 274/3/1, GIDC Estate, Pandesara,,Ta. Chorasi, Dist. Surat, Gujarat,Chorasi,Surat,Gujarat-394221
(d)Pin code 394221
(e)E-mail info@acetochemindia.com
(f)STD Code. 261(f)Telephone No. 2890998
(g)Fax No. 2892345
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/91826/2019
(d)Master Proposal Number(Single Window) SW/153208/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. 274/3/1, GIDC Estate, Pandesara, Dist: Su
(b)Pincode 394221
(c)Bounded Latitudes (North)
From
Degree 21.138614
Minutes
Second
From
Degree 21.139356
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.831636
Minutes
Second
From
Degree 72.832238
Minutes
Second
(e)Survey of India Topo Sheet No. F43M16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 8
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 8
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratSuratChorasi
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/23/2019-IA-II(I)
(b)Date of Apply of TOR 05 Mar 2019
(c)Date of Issue of TOR / Standard ToR 06 Apr 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project is Located Within GIDC
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)HDPE Spiral Tank/storage tank10 Nos.
(2.)MS Rubber Line Vessel10 Nos.
(3.)Filter press5 Nos.
(4.)Thermo Pack1 No.
(5.)Steam Boiler1 No
(6.)Compressor5 NOS.
(7.)Diesel generator set1 No
(8.)Cooling Tower5 No
(9.)Chilling Plant2 Nos
(10.)Chilling Plant2 Nos
(11.)Pump100 Nos
(12.)Scrubber2 Nos.
(13.)Dryer20 Nos
(14.)Glass line vessel10 Nos.
(15.)S S Vessel/Reactor20 nos.
(16.)Condenser5 Nos
(17.)Centrifuge30 Nos
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Alpha Nitro Napthalene100OthersTPMRoad
(2.)Alpha Napthylamine165OthersTPMRoad
(3.)Phenyl Alpha Naphthylamine (PANA)90OthersTPMRoad
(4.)2,4-Dichloro Acetophenone60OthersTPMRoad
(5.)3, 5 Dichloro aniline50OthersTPMRoad
(6.)Transfluthrin Acid Chloride30OthersTPMRoad
(7.)2- Chloro 5- Chloromethyl Pyridine30OthersTPMRoad
(8.)Nytrosyl Sulphuric Acid (from Sulfur) *600OthersTPMRoad
(9.)Epichlorohydrin Based Polyamide resin116OthersTPMRoad
(10.)3-Methyl 4- Nitro Imino Per hydro1,3,5 Oxidiazine20OthersTPMRoad
(11.)Nytrosyl Sulphuric Acid (from Sodium Thio Sulphate Solution and Spent Acid (H2SO4)) **468OthersTPMRoad
(12.)Acetophenone60OthersTPMRoad
(13.)Anisole100OthersTPMRoad
(14.)1,2,4 Triazole50OthersTPMRoad
(15.)4-Methyl Acetophenone / Acetyl Furan60OthersTPMRoad
(16.)IGBA - 3-(2-methylpropyl) pentanedioic acid / KSM - 3-(2-amino-2-oxoethyl)-5-methylhexanoic acid68.26OthersTPMRoad
(17.)D- Allethrollone10OthersTPMRoad
(18.)Diethyl Ketone179OthersTPMRoad
(19.)Methyl Propyl Ketone /Dipropyl Ketone/Propiophenone100OthersTPMRoad
(20.)4-Methoxy Acetophenone60OthersTPMRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 18 Jun 2015
(iv)Valid Upto 11 Jan 2020
(v)File No. AWH - 71094
(vi)Application No. 93289
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 1.50
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.33
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.03
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.26
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 134970.96
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 134970.96
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Anisole2490.84Tons per AnnumLocal MarketRoad80 Open MarketCopy of Linkage
(2.)Chlorine865.56Tons per AnnumLocal MarketRoad200 Open MarketCopy of Linkage
(3.)Acetic anhydride4331.18Tons per AnnumLocal MarketRoad83 Open MarketCopy of Linkage
(4.)Toluene20114.46Tons per AnnumLocal MarketRoad90 Open MarketCopy of Linkage
(5.)Methanol6901.08Tons per AnnumLocal MarketRoad60 Open MarketCopy of Linkage
(6.)Sulphuric Acid10995.84Tons per AnnumLocal MarketRoad70 Open MarketCopy of Linkage
(7.)Dimethyl carbonate1149.48Tons per AnnumLocal MarketRoad150 Open MarketCopy of Linkage
(8.)Naphthalene4671.12Tons per AnnumLocal MarketRoad90 Open MarketCopy of Linkage
(9.)Propionic Acid5409Tons per AnnumLocal MarketRoad150 Open MarketCopy of Linkage
(10.)Acetic acid834.4Tons per AnnumLocal MarketRoad150 Open MarketCopy of Linkage
(11.)Benzoic acid1092.84Tons per AnnumLocal MarketRoad80 Open MarketCopy of Linkage
(12.)EDC8345.88Tons per AnnumLocal MarketRoad150 Open MarketCopy of Linkage
(13.)Nitric acid13756.68Tons per AnnumLocal MarketRoad65 Open MarketCopy of Linkage
(14.)Hydrogen193.2Tons per AnnumLocal MarketRoad65 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2019 To 29 Feb 2020
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube51.844.225160
(2.)PM10Micro Gram per Meter Cube84.4177.0884100
(3.)NOxMicro Gram per Meter Cube16.3012.891680
(4.)SO2Micro Gram per Meter Cube18.4514.721880
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.997.386.58.5
(2.)Chloridesmg/l574.88308.472501000
(3.)Fluoridemg/l0011.5
(4.)Heavy MetalsZincmg/l00515
(5.)TSSmg/l14680120
(6.)TDSmg/l16308985002000
(7.)Total Hardnessmg/l576.29160.64200600
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l5.25.2A
(2.)BODmg/l00A
(3.)pHNA7.597.59A
(4.)CODmg/l22A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))554555
(2.)Leq(Night)A-weighted decibels(dB(A))444245
    14.5.     No. of Soil Sample Monitored locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milligram per Kilogram721326.9
(2.)pH8.077.18
(3.)N(Nitrogen)Milligram per Kilogram343.2198.5
(4.)P(Phosphorus)Milligram per Kilogram3.801.35
(5.)Electric ConductivityMillisiemens per Centimetre2.841.17
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 30
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 20
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersSMC Water Supply1403Copy of Permission LetterPipelineOthersPipelineSMC Water Supply17 Jan 2019140
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic1010Septic Tank & Soak pit SystemOthersSeptic Tank & Soak pit System010
(2.)Industrial6060ETPOthersCETP of M/s. PIL060
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 70
(b)Total Discharged Water (Kilolitre per Day) 70
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15Tons40RoadTreatment, Storage and Disposal Facility(TSDF)
(2.)Diethyl KetoneIndustrial Waste948Tons0RoadAuthorized Recyclers
(3.)BenzeneIndustrial Waste84Tons0RoadOthersReuse in Process
(4.)Used OilIndustrial Waste100Kilolitre20RoadAuthorized Recyclers
(5.)Spent CatalystIndustrial Waste432Tons60RoadTreatment, Storage and Disposal Facility(TSDF)
(6.)NSAIndustrial Waste528Tons0RoadOthersReused in to same process
(7.)Nitric AcidIndustrial Waste8160Tons0RoadOthersReused in to same process
(8.)Acetic AcidIndustrial Waste1062Tons60RoadOthersUnder Rule - 9
(9.)Discarded Containers/ Barrels/Liners/Carboy/BagsIndustrial Waste6.4Tons25RoadAuthorized Recyclers
(10.)Sodium Thiosulfate SolutionIndustrial Waste6012Tons0RoadOthersReuse in Process
(11.)Spent AcidIndustrial Waste3432Tons0RoadOthersReuse in Process
(12.)Spent H2SO4Industrial Waste8340Tons0RoadOthersReuse in Process
(13.)Distillation ResidueIndustrial Waste840Tons40RoadTreatment, Storage and Disposal Facility(TSDF)
(14.)Aniline/ODCBIndustrial Waste4632Tons0RoadOthersReuse in Process
(15.)MCBIndustrial Waste4080Tons0RoadOthersReuse in Process
(16.)Acetic AnhydrideIndustrial Waste1308Tons0RoadOthersReuse in Process
(17.)MethanolIndustrial Waste396Tons0RoadAuthorized RecyclersReuse in Process
(18.)TolueneIndustrial Waste17304Tons0RoadOthersReuse in Process
(19.)1,3- DichlorobenzeneIndustrial Waste90Tons0RoadOthersReused in to same process
(20.)Thio LayerIndustrial Waste4608Tons0RoadOthersReuse in Process
(21.)IPA/MethanolIndustrial Waste3288Tons0RoadOthersReuse in Process
(22.)AnilineIndustrial Waste684Tons0RoadOthersReuse in Process
(23.)EDCIndustrial Waste2736Tons0RoadOthersReuse in Process
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube51.82.720.0451.8460
(2.)NOxMicrogram per Meter Cube16.302.720.0116.3280
(3.)PM10Microgram per Meter Cube84.412.720.0284.43100
(4.)SO2Microgram per Meter Cube18.452.720.0418.580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Steam BoilerNatural Gas120.2OthersPM-SO2-NOx150-100-50
(2.)Thermo PackNatural gas120.2OthersPM-SO2-NOx150-100-50
(3.)D.G SetDiesel70.12OthersPM-SO2-NOx150-100-50
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 90
(b)Source DGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 250 KVA
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0.27
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0.27
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1951.024
(b)Waste/Barren Land (ha.) 1877.254
(c)Grazing/ Community Land (ha.) 1097.383
(d)Surface Water Bodies (ha.) 15552.28
(e)Settlements (ha.) 876.09
(f)Industrial (ha.) 845.68
(g)Forest (ha.) 4120.504
(h)Mangroves (ha.) 670.1761
(i)Marine Area (ha.) 3160.648
(j)Others (ha.) : Habitation 1277.47
    Total (ha.) 31428.509100000003
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.0432
(2.)Green belt0.0540
(3.)Area for Solid Waste Management0.0212
(4.)OthersETP, RM Storage, FG Storage, Tank Farm, utility0.1516
Total (ha.) 0.27
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Wildlife CorridorsNA0--
(2.)Critically Polluted AreaNA0--
(3.)WLSNA0--
(4.)ESZsNA0--
(5.)CorridorsNA0--
(6.)NPANA0--
(7.)ESAsNA0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0--
(2.)Archaeological SitesNA0--
(3.)Defence InstallationsNA0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.27
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species 8 Schedule - I Species
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 9.20 Lakh
(iii)Period of Implementation 2 Years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 20
(b)Permanent Employment-During Operation 20
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 350
(f)Total Manpower 40
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.05
(b)Percentage of Total Project Area 18.52
(c)No. of Plants to be Planted 215
(d)Funds Allocated for Plantation 600000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay Order Against NABET/QCI
(ii)Name of the EIA Consultant M/s. Aqua Air Environmental Engineers. Pvt. Ltd.
(iii)Address 403, CENTER POINT, NR. KADIWALA SCHOOL, RING ROAD, SURAT – 395002 (GUJ.) INDIA
(iv)Mobile No. 9904496967
(v)Landline No. 0261246085
(vi)Email Id aqua_eia@yahoo.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 03 Mar 2016
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterNA 01 Jul 2020
2.NA

The project/activities are covered under category A of item 5(b) ‘Pesticides industry and Pesticide specific intermediates’ of the Schedule to the Environment Impact Assessment Notification, 2006, and requires appraisal at central level by the sectoral Expert Appraisal Committee (EAC) in the Ministry.

 

The standard terms of references (TORs) for the Project was granted by the Ministry on 6th April, 2019. Total land area is estimated to be 2700 sqm. Industry will develop greenbelt in an area of 20% i.e., 540 sqm out of total area of the project and remaining (20%) (107 trees) will be develop at Survey Number 287, lajpore Village, Surat. Therefore total green belt will be 40%. Therefore total green belt will be 40%.

 

The Committee during deliberation noted that the project proponent has proposed only 20% area i.e., 540  sqm. land for greenbelt inside the plant premises and  20% green belt will be developed at outside the premises in nearby area. The committee suggested to submit the revised layout plan with 33% greenbelt area.          

          The EAC therefore deferred the proposal.

26 Jun 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantBansibhai D Patel
DesignationDirector
Name of Company (Applicant Name should not be given here)ACETOCHEM PRIVATE LIMITED
AddressPlot No. 274/3/1, GIDC Estate, Pandesara,
Print