Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Corel Pharma Chem Pvt. Ltd.
(b)Name of the Company / Organisation COREL PHARMA CHEM PVT LTD
(c)Registered Address SURVEY NO.473 AND 481, BORISANA, KADI THOL ROAD,,Mahesana,Gujarat-382715
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant KIRIT RAMBHAI PATEL
(b)Designation (Owner/ Partner/ CEO) DIRECTOR
(c)Address COREL HOUSE, NR.SHAYONA MARBLE, OPP. BHAGWAT PETROL PUMP, S.G. HIGHWAY, GOTA, AHMEDABAD - 382481, GUJARAT, INDIA,,Ahmedabad City,Ahmedabad,Gujarat-382481
(d)Pin code 382481
(e)E-mail kirit@corelpharmachem.com
(f)STD Code. 0(f)Telephone No. 8000880011
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/65363/2017
(d)Master Proposal Number(Single Window) SW/153166/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey no. 473 & 481
(b)Pincode 384441
(c)Bounded Latitudes (North)
From
Degree 23.2313444
Minutes
Second
From
Degree 23.2324527
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.3564166
Minutes
Second
From
Degree 72.3570194
Minutes
Second
(e)Survey of India Topo Sheet No. 46A/7, 46A/8
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 48.77
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 11
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratMahesanaKadi
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/313/2017-IA-II(I)
(b)Date of Apply of TOR 29 Jun 2017
(c)Date of Issue of TOR / Standard ToR 17 Aug 2017
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :25 Jan 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :28 Feb 2019
Distance of Public Hearing Venue from the Proposed Project :00
At Site
State :Gujarat
District :Mahesana
Tehsil :Kadi
Village :Borisana
851. What precaution should be taken for atmosphere pollution in proposed project? 2. Why do you want to install a plant near Borisana Village? 3. What will be done for renewable energy? 4. When wiOthersHarshad M. Vora, Resident Additional Collector,Additional District Magistrate,Mehsana & Chairman of the committee
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)S.S. Reactor with jacket & condenser610 kl
(2.)S.S. Reactor with jacket & condenser42 kl
(3.)S.S. Reactor with jacket & condenser41.5 kl
(4.)M.S. Glassline reactor & condenser65.5 kl
(5.)RVD with condenser & receiver110 kl
(6.)RVD with condenser & receiver18.5 kl
(7.)Fluid bed dryer4150 kg/hr
(8.)Agitator nutch filter85.5 kl
(9.)Agitator nutch filter812.5 kl
(10.)Agitator nutch filter216 kl
(11.)Air classifying mill6600 kg/hr
(12.)Air classifying mill4400 kg/hr
(13.)Roto cone dryer45.5 kl
(14.)Spray Dryer2400 kg/hr
(15.)S.S. Reactor with jacket & condenser41.0 kl
(16.)RVD with condenser & receiver1012.5 kl
(17.)Vacuum transfer system10500kg/hr
(18.)Addition tank50100, 150, 300 kg
(19.)Solvent storage tank520kl , 8.5 kl
(20.)Weight balance10150 kg
(21.)SS receiver30250, 500 lit
(22.)Cooling Tower5500 TR each
(23.)Chilling Plant4150 TR
(24.)Air Compressor8150cfm
(25.)RO Plant21 kl/Hr & 10 kl/Hr
(26.)Vaccum pump / Ejector10710 mm
(27.)DG Set5500 KVA x 3 nos. & 250 KVA x 2 nos.
(28.)Jacketed Evaporator20.5 KL/Hr
(29.)Air Jet Mill4500 kg/Hr.
(30.)Spin flash dryer4200 kg/hr
(31.)S.S. Reactor with jacket & condenser225 kl
(32.)S.S. Reactor with jacket & condenser1612.5 kl
(33.)S.S. Reactor with jacket & condenser40.5 kl
(34.)RVD with condenser & receiver225 kl
(35.)Shifter1048” dia
(36.)Cold Storage350 TR
(37.)S.S. Reactor with jacket & condenser105 kl
(38.)M.S. Glassline reactor & condenser412.5 kl
(39.)Centrifuge448”/36”
(40.)Agitator nutch filter812.5 kl
(41.)Recovery storage tank820kl , 8.5 kl
(42.)Monomer Storage Tank520 KL
(43.)Transfer pump20500 lit/Hr.
(44.)Weight balance1050 kg
(45.)Boiler23 mt
(46.)Chilling Plant for HVAC550, 100 tr
(47.)Thermic fluid heater24 lakh k/c
(48.)Fire Hydrant System1-
(49.)Hot air generator66 Kcal / Hr.
(50.)Double screw Extruder41000 kg/Hr.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Polyacrylate Powder (By Solvent Method)400OthersMTMRoad
(2.)Polymethacrylate Powder200OthersMTMRoad
(3.)Polyacrylate Dispersion600OthersMTMRoad
(4.)Hydrogenated Castor Oil Powder100OthersMTMRoad
(5.)Polymethacrylate Dispersion400OthersMTMRoad
(6.)Polyacrylate Powder (By Aqueous Method)100OthersMTMRoad
(7.)Hydrogenated Castor Oil 400200OthersMTMRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 20
(b) Funds Allocated for Environment Management (Capital) (in Crores) 2.47
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.50
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.376
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 31262.4
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 31262.4
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Ethyl Acrylate2280Tons per AnnumImport from South Korea, Japan and MalaysiaRoad35 Open MarketCopy of Linkage
(2.)Methyl Acrylate24Tons per AnnumImport from South Korea, Japan and MalaysiaRoad35 Open MarketCopy of Linkage
(3.)Acrylic acid5880Tons per AnnumImport from South Korea, Japan and MalaysiaRoad35 Open MarketCopy of Linkage
(4.)Methacrylic acid2760Tons per AnnumImport from South Korea, Japan and MalaysiaRoad35 Open MarketCopy of Linkage
(5.)White coal/Saw dust/Wood/Lignite3.5Kilo Litre per DayLocal /Open MarketRoad20 Open MarketCopy of Linkage
(6.)Butyl Acetate216Tons per AnnumImport from South Korea, Japan and MalaysiaRoad35 Open MarketCopy of Linkage
(7.)Industrial Solvent* (EA/Cyclo Hexane EDC/MDC etc)38.4Tons per AnnumLocal /Open MarketRoad150 Open MarketCopy of Linkage
(8.)Divinyl Benzene120Tons per AnnumImport from Japan and ChinaRoad35 Open MarketCopy of Linkage
(9.)HSD / LDO100OthersL/hrLocal /Open MarketRoad20 Open MarketCopy of Linkage
(10.)Salt24Tons per AnnumLocal /Open MarketRoad20 Open MarketCopy of Linkage
(11.)Water15240Tons per Annumground waterOtherspipeline0.3 OthersCGWACopy of Linkage
(12.)Potassium Carbonate/ Potassium hydroxide120Tons per AnnumImport from South Korea and ThailandRoad35 Open MarketCopy of Linkage
(13.)Methyl Methacrylate955.2Tons per AnnumImport from South Korea, Japan and MalaysiaRoad35 Open MarketCopy of Linkage
(14.)Hydrogenated castor oil 4003600Tons per AnnumLocal /Open MarketRoad35 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Nov 2017 To 31 Jan 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube786077.2100
(2.)NOxMicro Gram per Meter Cube321731.680
(3.)PM2.5Micro Gram per Meter Cube383036.660
(4.)SO2Micro Gram per Meter Cube181017.680
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l108100100
(2.)Total Hardnessmg/l290215200600
(3.)Fluoridemg/l0.620.381.01.5
(4.)Heavy Metalsironmg/l0.050.043.03.0
(5.)TDSmg/l11177765002000
(6.)Chloridesmg/l3902762501000
(7.)pHNA7.97.66.58.5
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l5.95.5A
(2.)DOmg/l7.06.0A
(3.)CODmg/l18.016.5A
(4.)pHNA8.38.0A
(5.)OthersTDSmg/l820166A
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))69.048.075
(2.)Leq(Night)A-weighted decibels(dB(A))584470
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram3.02.4
(2.)N(Nitrogen)Percent0.040.02
(3.)pH8.88.3
(4.)K(Potassium)Milligram per Kilogram71.252.0
(5.)Electric ConductivityMillisiemens per Centimetre0.240.20
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 25 To 40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 15 To 30
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater2030.3Copy of Permission LetterPipelineTube Well5226817 May 2020203
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic810STPGreen Belt Renewal Plant8.0
(2.)Industrial13.3315Primary, Secondary & Tertiary Treatment MEE & ATFDReuse within the Plant & Recycling,Green Belt Renewal Plant13.33
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 21.33
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 21.33
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Plastic BagsPlastic Waste0.1Tons30RoadAuthorized Recyclers
(2.)Wooden, Metal, Plastic, Paper ScrapIndustrial Waste1.2Tons30RoadOthersWaste management by authorized vendor
(3.)Inorganic SaltHazardous Waste (as per Hazardous and Other Waste Management rules 2016)48Tons57RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)Spent SolventHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1.2Tons57RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Bio Degradable WasteOthersBio Degradable Waste1.2Tons20RoadOtherswill be given to farmers
(6.)Process Waste (Organic))Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)12Tons57RoadTreatment, Storage and Disposal Facility(TSDF)
(7.)Date expired productHazardous Waste (as per Hazardous and Other Waste Management rules 2016)7.8Tons57RoadTreatment, Storage and Disposal Facility(TSDF)
(8.)E - WasteE Waste0.1Tons30RoadAuthorized Recyclers
(9.)ETP Sludge & Evaporation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)8.4Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(10.)Used Oil / Spent OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.25Tons30RoadCo-Processing
(11.)Discarded Containers / Barrels/ LinersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)540Tons30RoadAuthorized Recyclers
(12.)Spent CarbonHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.25Tons57RoadTreatment, Storage and Disposal Facility(TSDF)
(13.)off Specification ProductsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)78Tons57RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube29.4001.2830.7060
(2.)PM10Microgram per Meter Cube65.4001.2866.70100
(3.)SO2Microgram per Meter Cube11.8000.4312.480
(4.)NOxMicrogram per Meter Cube20.3000.8321.280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)D.G. Set - 3HSD50.05OthersPM, SO2, NOx150mg/m3, 100 PPM, 50 PPM
(2.)Thermic Fluid Heater - 1HSD / LDO110.1OthersPM, SO2, NOx150mg/m3, 100 PPM, 50 PPM
(3.)Thermic Fluid Heater - IIHSD / LDO110.1OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(4.)DG Set - 5HSD50.05OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(5.)Hot Air Generator - 1HSD / LDO50.3OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(6.)Hot Air Generator - 2HSD / LDO50.3OthersPM, SO2, NOx150mg/m3, 100 PPM, 50 PPM
(7.)Hot Air Generator - 3HSD / LDO50.3OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(8.)Hot Air Generator - 6HSD / LDO50.2OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(9.)Hot Air Generator - 5HSD / LDO50.2OthersPM, SO2, NOx150 mg/m3, 10 PPM, 50 PPM
(10.)Boiler - IIWhite Coal/Briquettes / PNG300.5OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPMPM. 50
(11.)D.G. Set - 4HSD50.05OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(12.)Hot Air Generator - 4HSD/ LDO50.2OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(13.)D.G.Set - 2HSD30.05OthersPM, SO2, NOx150 mg/m3, 100 PPM, 50 PPM
(14.)D.G. Set - 1HSD30.05OthersPM, SO2, NOx150mg/m3, 100 PPM, 50 PPM
(15.)Boiler - 1White Coal / Briquettes / PNG300.5OthersPM, SO2, NOx150 Mg/m3, 100 PPM, 50 PPM
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2500
(b)Source UGVCL Kadi
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) DG Sets having capacity of 250 KVA (2 nos.) & 500
(e)Stack Height (in m) 5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 00
(b)Private Land (ha.) 5.6129
(c)Government Land (ha.) 00
(d)Revenue Land (ha.) 00
(e)Other Land (ha.) 00
    Total Land (ha.) 5.6129
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 24651
(b)Waste/Barren Land (ha.) 2422.18
(c)Grazing/ Community Land (ha.) 00
(d)Surface Water Bodies (ha.) 775.19
(e)Settlements (ha.) 3244.46
(f)Industrial (ha.) 00
(g)Forest (ha.) 00
(h)Mangroves (ha.) 00
(i)Marine Area (ha.) 00
(j)Others (ha.) : open area 332.40
    Total (ha.) 31425.23
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.777513.85 %
(2.)Green belt1.875033.41%
(3.)OthersStorage ETP Other & Open space2.960452.74%
Total (ha.) 5.6129
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNone within 10 Km00None within 10 Km
(2.)CorridorsNone within 10 Km00None within 10 Km
(3.)Wildlife CorridorsNone within 10 Km00None within 10 Km
(4.)WLSNone within 10 Km00None within 10 Km
(5.)ESZsNone within 10 Km00None within 10 Km
(6.)NPANone within 10 Km00None within 10 Km
(7.)Critically Polluted AreaNone within 10 Km00None within 10 Km
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone within 10 Km00None within 10 Km
(2.)ForestNone within 10 Km00None within 10 Km
(3.)Defence InstallationsNone within 10 Km00None within 10 Km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 5.61
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in INR) (in Lacs) 00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 195
(c)Temporary Employment- During Construction 10
(d)Temporary Employment- During Operation 10
(e)No. of working days 330
(f)Total Manpower 220
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.87
(b)Percentage of Total Project Area 33.32
(c)No. of Plants to be Planted 10000
(d)Funds Allocated for Plantation 500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialGrowth in the industrial sector creates proposed new opportunities for employment and can also help diversify the economy.
(2.)Social1. Our project can help to decrease import so it forex can be saved as still many pharmaceutical and cosmetic companies are dependent on overseas manufacturers. 2. We are manufacturing handsanitizer chemical as well as Pharmaceutical raw materials so we can help to fight against COVID19.
(3.)EnvironmentalProject proponent will provide 2.5% CER of the project cost. Green belt development will benefit the biological environment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/IA0029
(ii)Name of the EIA Consultant Green Circle Inc.
(iii)Address green Empire (Anupusham), Above Axis bank, Near Yash Complex Vadodara, Gujarat 390021
(iv)Mobile No. 9725701594
(v)Landline No. 0265237129
(vi)Email Id info@greencircleinc.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 04 Jun 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKIRIT RAMBHAI PATEL
DesignationDIRECTOR
Name of Company (Applicant Name should not be given here)COREL PHARMA CHEM PVT LTD
AddressSURVEY NO.473 AND 481, BORISANA, KADI THOL ROAD