1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | M/s. Corel Pharma Chem Pvt. Ltd. | (b)Name of the Company / Organisation | COREL PHARMA CHEM PVT LTD | (c)Registered Address | SURVEY NO.473 AND 481, BORISANA, KADI THOL ROAD,,Mahesana,Gujarat-382715 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | KIRIT RAMBHAI PATEL | (b)Designation (Owner/ Partner/ CEO) | DIRECTOR | (c)Address | COREL HOUSE, NR.SHAYONA MARBLE, OPP. BHAGWAT PETROL PUMP, S.G. HIGHWAY, GOTA, AHMEDABAD - 382481, GUJARAT, INDIA,,Ahmedabad City,Ahmedabad,Gujarat-382481 | (d)Pin code | 382481 | (e)E-mail | kirit@corelpharmachem.com | (f)STD Code. | 0(f)Telephone No. | 8000880011 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/GJ/IND2/65363/2017 | (d)Master Proposal Number(Single Window) | SW/153166/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Survey no. 473 & 481 | (b)Pincode | 384441 | (c)Bounded Latitudes (North) | | From | | Degree | 23.2313444 | Minutes | | Second | | From | | Degree | 23.2324527 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.3564166 | Minutes | | Second | | From | | Degree | 72.3570194 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 46A/7, 46A/8 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 48.77 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 11 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Gujarat | Mahesana | Kadi | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/313/2017-IA-II(I) | (b)Date of Apply of TOR | 29 Jun 2017 | (c)Date of Issue of TOR / Standard ToR | 17 Aug 2017 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 28 Feb 2019 | Distance of Public Hearing Venue from the Proposed Project : | 00 |
| At Site | State : | Gujarat | District : | Mahesana | Tehsil : | Kadi | Village : | Borisana |
| 85 | 1. What precaution should be taken for atmosphere pollution in proposed project?
2. Why do you want to install a plant near Borisana Village?
3. What will be done for renewable energy?
4. When wi | Others | Harshad M. Vora, Resident Additional Collector,Additional District Magistrate,Mehsana & Chairman of the committee | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | S.S. Reactor with jacket & condenser | 6 | 10 kl | (2.) | S.S. Reactor with jacket & condenser | 4 | 2 kl | (3.) | S.S. Reactor with jacket & condenser | 4 | 1.5 kl | (4.) | M.S. Glassline reactor & condenser | 6 | 5.5 kl | (5.) | RVD with condenser & receiver | 1 | 10 kl | (6.) | RVD with condenser & receiver | 1 | 8.5 kl | (7.) | Fluid bed dryer | 4 | 150 kg/hr | (8.) | Agitator nutch filter | 8 | 5.5 kl | (9.) | Agitator nutch filter | 8 | 12.5 kl | (10.) | Agitator nutch filter | 2 | 16 kl | (11.) | Air classifying mill | 6 | 600 kg/hr | (12.) | Air classifying mill | 4 | 400 kg/hr | (13.) | Roto cone dryer | 4 | 5.5 kl | (14.) | Spray Dryer | 2 | 400 kg/hr | (15.) | S.S. Reactor with jacket & condenser | 4 | 1.0 kl | (16.) | RVD with condenser & receiver | 10 | 12.5 kl | (17.) | Vacuum transfer system | 10 | 500kg/hr | (18.) | Addition tank | 50 | 100, 150, 300 kg | (19.) | Solvent storage tank | 5 | 20kl , 8.5 kl | (20.) | Weight balance | 10 | 150 kg | (21.) | SS receiver | 30 | 250, 500 lit | (22.) | Cooling Tower | 5 | 500 TR each | (23.) | Chilling Plant | 4 | 150 TR | (24.) | Air Compressor | 8 | 150cfm | (25.) | RO Plant | 2 | 1 kl/Hr & 10 kl/Hr | (26.) | Vaccum pump / Ejector | 10 | 710 mm | (27.) | DG Set | 5 | 500 KVA x 3 nos. & 250 KVA x 2 nos. | (28.) | Jacketed Evaporator | 2 | 0.5 KL/Hr | (29.) | Air Jet Mill | 4 | 500 kg/Hr. | (30.) | Spin flash dryer | 4 | 200 kg/hr | (31.) | S.S. Reactor with jacket & condenser | 2 | 25 kl | (32.) | S.S. Reactor with jacket & condenser | 16 | 12.5 kl | (33.) | S.S. Reactor with jacket & condenser | 4 | 0.5 kl | (34.) | RVD with condenser & receiver | 2 | 25 kl | (35.) | Shifter | 10 | 48” dia | (36.) | Cold Storage | 3 | 50 TR | (37.) | S.S. Reactor with jacket & condenser | 10 | 5 kl | (38.) | M.S. Glassline reactor & condenser | 4 | 12.5 kl | (39.) | Centrifuge | 4 | 48”/36” | (40.) | Agitator nutch filter | 8 | 12.5 kl | (41.) | Recovery storage tank | 8 | 20kl , 8.5 kl | (42.) | Monomer Storage Tank | 5 | 20 KL | (43.) | Transfer pump | 20 | 500 lit/Hr. | (44.) | Weight balance | 10 | 50 kg | (45.) | Boiler | 2 | 3 mt | (46.) | Chilling Plant for HVAC | 5 | 50, 100 tr | (47.) | Thermic fluid heater | 2 | 4 lakh k/c | (48.) | Fire Hydrant System | 1 | - | (49.) | Hot air generator | 6 | 6 Kcal / Hr. | (50.) | Double screw Extruder | 4 | 1000 kg/Hr. | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Polyacrylate Powder (By Solvent Method) | 400 | Others | MTM | Road | | (2.) | Polymethacrylate Powder | 200 | Others | MTM | Road | | (3.) | Polyacrylate Dispersion | 600 | Others | MTM | Road | | (4.) | Hydrogenated Castor Oil Powder | 100 | Others | MTM | Road | | (5.) | Polymethacrylate Dispersion | 400 | Others | MTM | Road | | (6.) | Polyacrylate Powder (By Aqueous Method) | 100 | Others | MTM | Road | | (7.) | Hydrogenated Castor Oil 400 | 200 | Others | MTM | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 20 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 2.47 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.50 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.376 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 31262.4 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 31262.4 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Ethyl Acrylate | 2280 | Tons per Annum | | Import from South Korea, Japan and Malaysia | Road | | 35 | Open Market | | Copy of Linkage | (2.) | Methyl Acrylate | 24 | Tons per Annum | | Import from South Korea, Japan and Malaysia | Road | | 35 | Open Market | | Copy of Linkage | (3.) | Acrylic acid | 5880 | Tons per Annum | | Import from South Korea, Japan and Malaysia | Road | | 35 | Open Market | | Copy of Linkage | (4.) | Methacrylic acid | 2760 | Tons per Annum | | Import from South Korea, Japan and Malaysia | Road | | 35 | Open Market | | Copy of Linkage | (5.) | White coal/Saw dust/Wood/Lignite | 3.5 | Kilo Litre per Day | | Local /Open Market | Road | | 20 | Open Market | | Copy of Linkage | (6.) | Butyl Acetate | 216 | Tons per Annum | | Import from South Korea, Japan and Malaysia | Road | | 35 | Open Market | | Copy of Linkage | (7.) | Industrial Solvent* (EA/Cyclo Hexane EDC/MDC etc) | 38.4 | Tons per Annum | | Local /Open Market | Road | | 150 | Open Market | | Copy of Linkage | (8.) | Divinyl Benzene | 120 | Tons per Annum | | Import from Japan and China | Road | | 35 | Open Market | | Copy of Linkage | (9.) | HSD / LDO | 100 | Others | L/hr | Local /Open Market | Road | | 20 | Open Market | | Copy of Linkage | (10.) | Salt | 24 | Tons per Annum | | Local /Open Market | Road | | 20 | Open Market | | Copy of Linkage | (11.) | Water | 15240 | Tons per Annum | | ground water | Others | pipeline | 0.3 | Others | CGWA | Copy of Linkage | (12.) | Potassium Carbonate/ Potassium hydroxide | 120 | Tons per Annum | | Import from South Korea and Thailand | Road | | 35 | Open Market | | Copy of Linkage | (13.) | Methyl Methacrylate | 955.2 | Tons per Annum | | Import from South Korea, Japan and Malaysia | Road | | 35 | Open Market | | Copy of Linkage | (14.) | Hydrogenated castor oil 400 | 3600 | Tons per Annum | | Local /Open Market | Road | | 35 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Nov 2017 To 31 Jan 2018 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 10 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 78 | 60 | 77.2 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 32 | 17 | 31.6 | 80 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 38 | 30 | 36.6 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 18 | 10 | 17.6 | 80 | |
14.2. No. of Ground Water monitoring locations : 5 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TSS | | | mg/l | | 10 | 8 | 100 | 100 | (2.) | Total Hardness | | | mg/l | | 290 | 215 | 200 | 600 | (3.) | Fluoride | | | mg/l | | 0.62 | 0.38 | 1.0 | 1.5 | (4.) | Heavy Metals | | iron | mg/l | | 0.05 | 0.04 | 3.0 | 3.0 | (5.) | TDS | | | mg/l | | 1117 | 776 | 500 | 2000 | (6.) | Chlorides | | | mg/l | | 390 | 276 | 250 | 1000 | (7.) | pH | | | NA | | 7.9 | 7.6 | 6.5 | 8.5 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 5.9 | 5.5 | A | (2.) | DO | | mg/l | | 7.0 | 6.0 | A | (3.) | COD | | mg/l | | 18.0 | 16.5 | A | (4.) | pH | | NA | | 8.3 | 8.0 | A | (5.) | Others | TDS | mg/l | | 820 | 166 | A | |
14.4. No. of Ambient Noise monitoring locations : 10 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 69.0 | 48.0 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 58 | 44 | 70 | |
14.5. No. of Soil Sample Monitored locations : 10 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Milligram per Kilogram | | 3.0 | 2.4 | (2.) | N(Nitrogen) | Percent | | 0.04 | 0.02 | (3.) | pH | | | 8.8 | 8.3 | (4.) | K(Potassium) | Milligram per Kilogram | | 71.2 | 52.0 | (5.) | Electric Conductivity | Millisiemens per Centimetre | | 0.24 | 0.20 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 25 To 40 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 15 To 30 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 203 | 0.3 | Copy of Permission Letter | Pipeline | | Tube Well | | 52268 | 17 May 2020 | 203 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic | 8 | 10 | STP | Green Belt Renewal Plant | | 8.0 | | (2.) | Industrial | 13.33 | 15 | Primary, Secondary & Tertiary Treatment MEE & ATFD | Reuse within the Plant & Recycling,Green Belt Renewal Plant | | 13.33 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 21.33 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 21.33 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Plastic Bags | Plastic Waste | | 0.1 | Tons | 30 | Road | | Authorized Recyclers | | (2.) | Wooden, Metal, Plastic, Paper Scrap | Industrial Waste | | 1.2 | Tons | 30 | Road | | Others | Waste management by authorized vendor | (3.) | Inorganic Salt | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 48 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (4.) | Spent Solvent | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1.2 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (5.) | Bio Degradable Waste | Others | Bio Degradable Waste | 1.2 | Tons | 20 | Road | | Others | will be given to farmers | (6.) | Process Waste (Organic)) | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 12 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (7.) | Date expired product | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 7.8 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (8.) | E - Waste | E Waste | | 0.1 | Tons | 30 | Road | | Authorized Recyclers | | (9.) | ETP Sludge & Evaporation Residue | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 8.4 | Tons | 50 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (10.) | Used Oil / Spent Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.25 | Tons | 30 | Road | | Co-Processing | | (11.) | Discarded Containers / Barrels/ Liners | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 540 | Tons | 30 | Road | | Authorized Recyclers | | (12.) | Spent Carbon | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.25 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (13.) | off Specification Products | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 78 | Tons | 57 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 29.4 | 00 | 1.28 | 30.70 | 60 | (2.) | PM10 | | Microgram per Meter Cube | 65.4 | 00 | 1.28 | 66.70 | 100 | (3.) | SO2 | | Microgram per Meter Cube | 11.8 | 00 | 0.43 | 12.4 | 80 | (4.) | NOx | | Microgram per Meter Cube | 20.3 | 00 | 0.83 | 21.2 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | D.G. Set - 3 | HSD | 5 | 0.05 | Others | PM, SO2, NOx | 150mg/m3, 100 PPM, 50 PPM | (2.) | Thermic Fluid Heater - 1 | HSD / LDO | 11 | 0.1 | Others | PM, SO2, NOx | 150mg/m3, 100 PPM, 50 PPM | (3.) | Thermic Fluid Heater - II | HSD / LDO | 11 | 0.1 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (4.) | DG Set - 5 | HSD | 5 | 0.05 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (5.) | Hot Air Generator - 1 | HSD / LDO | 5 | 0.3 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (6.) | Hot Air Generator - 2 | HSD / LDO | 5 | 0.3 | Others | PM, SO2, NOx | 150mg/m3, 100 PPM, 50 PPM | (7.) | Hot Air Generator - 3 | HSD / LDO | 5 | 0.3 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (8.) | Hot Air Generator - 6 | HSD / LDO | 5 | 0.2 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (9.) | Hot Air Generator - 5 | HSD / LDO | 5 | 0.2 | Others | PM, SO2, NOx | 150 mg/m3, 10 PPM, 50 PPM | (10.) | Boiler - II | White Coal/Briquettes / PNG | 30 | 0.5 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPMPM. 50 | (11.) | D.G. Set - 4 | HSD | 5 | 0.05 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (12.) | Hot Air Generator - 4 | HSD/ LDO | 5 | 0.2 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (13.) | D.G.Set - 2 | HSD | 3 | 0.05 | Others | PM, SO2, NOx | 150 mg/m3, 100 PPM, 50 PPM | (14.) | D.G. Set - 1 | HSD | 3 | 0.05 | Others | PM, SO2, NOx | 150mg/m3, 100 PPM, 50 PPM | (15.) | Boiler - 1 | White Coal / Briquettes / PNG | 30 | 0.5 | Others | PM, SO2, NOx | 150 Mg/m3, 100 PPM, 50 PPM | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 2500 | (b)Source | UGVCL Kadi | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | DG Sets having capacity of 250 KVA (2 nos.) & 500 | (e)Stack Height (in m) | 5 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 00 | (b)Private Land (ha.) | 5.6129 | (c)Government Land (ha.) | 00 | (d)Revenue Land (ha.) | 00 | (e)Other Land (ha.) | 00 | Total Land (ha.) | 5.6129 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 24651 | (b)Waste/Barren Land (ha.) | 2422.18 | (c)Grazing/ Community Land (ha.) | 00 | (d)Surface Water Bodies (ha.) | 775.19 | (e)Settlements (ha.) | 3244.46 | (f)Industrial (ha.) | 00 | (g)Forest (ha.) | 00 | (h)Mangroves (ha.) | 00 | (i)Marine Area (ha.) | 00 | (j)Others (ha.) : open area | 332.40 | Total (ha.) | 31425.23 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 0.7775 | 13.85 % | (2.) | Green belt | | 1.8750 | 33.41% | (3.) | Others | Storage ETP Other & Open space | 2.9604 | 52.74% | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | ESAs | None within 10 Km | 00 | None within 10 Km | (2.) | Corridors | None within 10 Km | 00 | None within 10 Km | (3.) | Wildlife Corridors | None within 10 Km | 00 | None within 10 Km | (4.) | WLS | None within 10 Km | 00 | None within 10 Km | (5.) | ESZs | None within 10 Km | 00 | None within 10 Km | (6.) | NPA | None within 10 Km | 00 | None within 10 Km | (7.) | Critically Polluted Area | None within 10 Km | 00 | None within 10 Km | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | None within 10 Km | 00 | None within 10 Km | (2.) | Forest | | None within 10 Km | 00 | None within 10 Km | (3.) | Defence Installations | | None within 10 Km | 00 | None within 10 Km | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 00 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 5.61 | (b)Land yet to be acquired(Ha) | 00 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 00 | (b)No. of Households | 00 | (c)No. of PDFs (Project Displaced Families) | 00 | (d)No. of PAFs (Project Affected Families) | 00 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 00 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 5 | (b)Permanent Employment-During Operation | 195 | (c)Temporary Employment- During Construction | 10 | (d)Temporary Employment- During Operation | 10 | (e)No. of working days | 330 | (f)Total Manpower | 220 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 1.87 | (b)Percentage of Total Project Area | 33.32 | (c)No. of Plants to be Planted | 10000 | (d)Funds Allocated for Plantation | 500000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Financial | Growth in the industrial sector creates proposed new opportunities for employment and can also help diversify the economy. | (2.) | Social | 1. Our project can help to decrease import so it forex can be saved as still many pharmaceutical and cosmetic companies are dependent on overseas manufacturers. 2. We are manufacturing handsanitizer chemical as well as Pharmaceutical raw materials so we can help to fight against COVID19. | (3.) | Environmental | Project proponent will provide 2.5% CER of the project cost. Green belt development will benefit the biological environment | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/IA0029 | (ii)Name of the EIA Consultant | Green Circle Inc. | (iii)Address | green Empire (Anupusham), Above Axis bank, Near Yash Complex Vadodara, Gujarat 390021 | (iv)Mobile No. | 9725701594 | (v)Landline No. | 0265237129 | (vi)Email Id | info@greencircleinc.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 04 Jun 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | KIRIT RAMBHAI PATEL | Designation | DIRECTOR | Name of Company (Applicant Name should not be given here) | COREL PHARMA CHEM PVT LTD | Address | SURVEY NO.473 AND 481, BORISANA, KADI THOL ROAD |
|