Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) INCLUSION OF TITANIUM SLAG IN PRODUCT MIX AND CHANGE IN CONFIGURATION OF 36,000 TPA FERRO ALLOY PLANT of SHRI BAJRANG POWER & ISPAT LIMITED
(b)Name of the Company / Organisation SHRI BAJRANG POWER ISPAT LIMITED
(c)Registered Address Borjhara, Urla - Guma Road Raipur (CG),,Raipur,Chhattisgarh-493221
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Shravan Kumar Goyal
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Borjhara, Urla - Guma Road Raipur,,Raipur,Raipur,Chhattisgarh-493221
(d)Pin code 493221
(e)E-mail bajrangtelang@gmail.com
(f)STD Code. 771(f)Telephone No. 4288019
(g)Fax No. 2323601
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/CG/IND/153096/2020
(d)Master Proposal Number(Single Window) SW/153094/2020
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Change of Product Mix under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 521/44
(b)Pincode 492001
(c)Bounded Latitudes (North)
From
Degree 2376238
Minutes
Second
From
Degree 2377390
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 578924
Minutes
Second
From
Degree 580493
Minutes
Second
(e)Survey of India Topo Sheet No. 64G/10,64G/14,64G/15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 287
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 8
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Chhattisgarh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. F-No 5-69/2010 (ENV)/6272 DATED 21.02.2020
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Feb 13 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Power - AFBC42042Mega Watt(MW)OthersInternal
(2.)Power - WHRB48048Mega Watt(MW)OthersInternal
(3.)Ferro Alloy Plant - Titanium Slag01800018000Tons per Annum(TPA)RoadInternal
(4.)Power - Coke Oven25025Mega Watt(MW)OthersInternal
(5.)Ferro Alloy Plant - Ferro Silico Managanese18000018000Tons per Annum(TPA)RoadInternal
(6.)Pelletisation Plant with Coal Gasifier140000001400000Tons per Annum(TPA)RoadInternal
(7.)Oxygen Plant5000500OthersTPDRoadInternal
(8.)Fly Ash Bricks Plant10000000010000000OthersNPARoadInternal
(9.)Sponge Iron6000000600000Tons per Annum(TPA)OthersInternal
(10.)Blast Furnace5500000550000Tons per Annum(TPA)RoadInternal
(11.)Hot Re-Rolling Mill4000000400000Tons per Annum(TPA)RoadInternal
(12.)Steel Melting Shop - Continuous Casting Machine100000001000000Tons per Annum(TPA)RoadInternal
(13.)Coke Oven Battery5000000500000Tons per Annum(TPA)RoadInternal
(14.)Sintering Plant7000000700000Tons per Annum(TPA)RoadInternal
(15.)Coal Washery240000002400000Tons per Annum(TPA)RoadInternal
(16.)Power - Blast F/C10010Mega Watt(MW)OthersInternal
(17.)Iron Ore Beneficiation Plant200000002000000Tons per Annum(TPA)RoadInternal
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)PowerAFBC – 42 MW-AFBC – 42 MWReduction in capacity from 42 to 33
(2.)Sponge Iron3 x 0.2 MTPA (3 X 600 TPD X 330 Days)-3 x 0.2 MTPA (3 X 600 TPD X 330 Days)No Change
(3.)PowerWHRB – 3 X 16 MW-WHRB – 3 X 16 MWNo Change
(4.)Pelletisation Plant1.40 MTPA with Coal Gasifier (3x17000 Nm3/Hr)-1.40 MTPA with Coal Gasifier (3x17000 Nm3/Hr)No change
(5.)Blast Furnace0.55 MTPA-0.55 MTPANo change
(6.)Sintering Plant0.7 MTPA-0.7 MTPANo change
(7.)PowerBlast F/C – 10 MW-Blast F/C – 10 MWDropped
(8.)PowerCoke Oven – 25 MW-Coke Oven – 25 MWDropped
(9.)Ferro Alloy Plant2 x 18000 TPA, 1 X 9 MVA + 1 X 9 MVA2 x 18000 TPA, 1 X 9 MVA + 1 X 12 MVA2 x 18000 TPA, 1 X 9 MVA + 1 X 12 MVAChange in Configuration and inclusion of Titanium Slag in product mix of Silico & Ferro Manganese
(10.)Coal washery-2.4 MTPA-2.4 MTPANo change
(11.)Oxygen Plant500 TPD-500 TPDNo change
(12.)Fly Ash Bricks Plant10000000 NPA-10000000 NPANo change
(13.)Hot Re-Rolling Mill2 x 0.20 = 0.40 MTPA-2 x 0.20 = 0.40 MTPANo Change
(14.)Iron ore beneficiation Plant2.0 MTPA-2.0 MTPANo change
(15.)Steel Melting Shop2.0 MTPA continuous Casting Machine- 1.0MTPA-2.0 MTPA continuous Casting Machine- 1.0MTPANo change
(16.)Coke Oven Battery0.5 MTPA-0.5 MTPANo change
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 18 Feb 2020
(iv)Valid Upto 28 Feb 2021
(v)File No. 10234 /TS/CECB/2020
(vi)Application No. 4489384
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 0.0
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 43200
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 43200
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Graphite Electrode450Tons per AnnumIndigenousRoad0 Open MarketCopy of Linkage
(2.)Flue Dust450Tons per AnnumDe-Dusting SystemConveyor Belt0 CaptiveCopy of Linkage
(3.)Ilmenite3600Tons per AnnumIREL & Other SuppliersRoad,Rail456 Open MarketCopy of Linkage
(4.)Coke6300Tons per AnnumJharkhandRoad,Rail634 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 6.5 To 9.9
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.5 To 8.5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface31215Copy of Permission LetterPipelineTube Well5666/302/WR/TECH/03/IWS/D-419 Aug 201016000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic1040STPGreen Belt Renewal Plant10
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 10
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 10
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)NAOthersNONE0Tons0OthersNONEOthersNONE
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube240.2015.739.880
(2.)PM2.5Microgram per Meter Cube220.200.6422.6560
(3.)SO2Microgram per Meter Cube140.2010.624.780
(4.)PM10Microgram per Meter Cube880.203.291.3100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Silico ManganeseCoal & Coke320.80SO229.2
(2.)Titanium SlagCoke320.80SO211.13
(3.)Silico ManganeseCoal & Coke320.80NOx18.94
(4.)Silico ManganeseCoal & Coke320.80PM100.8
(5.)Titanium SlagCoke320.80PM100.80
(6.)Titanium SlagCoke320.80NOx5.56
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 18000
(b)Source Captive Power Plant
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) NA
(e)Stack Height (in m) 100
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 123.21
(c)Government Land (ha.) 17.98
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 141.19
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Existing Plant Area 141.19
    Total (ha.) 141.1900
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant141.19
Total (ha.) 141.19
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsNone0-
(2.)CorridorsNone0-
(3.)Wildlife CorridorsNone0-
(4.)Critically Polluted AreaNone0-
(5.)WLSNone0-
(6.)NPANone0-
(7.)ESAsNone0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone0-
(2.)Archaeological SitesNone0-
(3.)Defence InstallationsNone0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 141.19
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kharun river
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 8.3
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 800
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 800
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt46.59046.59
(2.)Percentage of Total Project Area33033
(3.)No. of Plants70000070000
(4.)Funds Allocated2000200
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalNo Solid Waste generation from the proposed project
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA 0174
(ii)Name of the EIA Consultant B. S. Envi-Tech Pvt. Ltd,
(iii)Address 12-13-1270/71/73, Amity Ville, 4th Floor, Beside Spencer Super Market, St. Ann’s Road, Tarnaka, Secunderabad-500017
(iv)Mobile No. 9848053012
(v)Landline No. 0404978306
(vi)Email Id info@bsenvitech.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 16 Nov 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan
(b)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(c)Uploaded Cover Letter Copy of Cover Letter
(d)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(e)Uploaded Additional File Copy of Additional File
(f)Uploaded Updated Form1 Copy of Updated Form1
(g)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAProposal is returned due to the following shortcomings: Form 2: i. In s.no.6, existing EC shall be uploaded. ii. In s.No.4, not able to access the KML file. Appropriate KML file shall be uploaded. iii. In s.no. 8, existing and proposed configuration as well as product details shall be furnished. iv. In s.no.9, complete certified compliance report shall be uploaded. v. In s.no. 9, the details of capacity expansion is wrongly mentioned and the same may be corrected. vi. In s.no.17, solid waste generation details shall be furnished. vii. In s.no. 18.1, AAQ modelling data is wrongly filled in and the same shall be corrected. viii. In s.no. 32, kindly furnish the time bound action plan for green belt development covering 33% of the 141.19 ha with appropriate layout. Addendum to EIA report The report uploaded on PARIVESH does not requisite information. In view of this, addendum to the existing EIA report shall be prepared covering the following: i. QCI/NABET accreditation status of the EIA consultant ii. Details of the existing Environmental Clearances (ECs) obtained. iii. Implementation status of the existing Environmental Clearances. iv. Details of the earlier Public consultation conducted and the compliance to the issues raised in the PH. v. Certified compliance report of existing environmental clearances from the concerned Regional Office of the MoEF&CC. vi. Closure report of Regional Office in case of non-compliances observed in the certified compliance report. vii. Existing baseline conditions based on the periodic environmental monitoring program viii. Proposed Expansion or Modernization or Change of product mix vis-à-vis with granted EC capacity along with percentage of increase in production. ix. Proposed plant lay out vis-à-vis with layout for which Environmental Clearance was granted. x. Proposed resources requirement (Land/raw materials/water/power) vis-à-vis with granted Environmental Clearance xi. Pollution load calculations (Air/Water/Solid & hazardous waste/traffic) vis-à-vis with granted Environmental Clearance xii. Environmental Management Plan for the proposed Expansion or Modernization or Change of product mix along with budget provision for implementation. xiii. Proposed Corporate Environment Responsibility activities for the additional investment proposed. xiv. Litigation if any, pending in any Court related to the project (or) activity. Pre-feasibility report has not been uploaded and the same be uploaded on PARIVESH. 16 Jun 2020
2.NAProposal is returned due to the following shortcomings: Form 2: i. In s.no.6, existing EC shall be uploaded. ii. In s.No.4, not able to access the KML file. Appropriate KML file shall be uploaded. iii. In s.no. 8, existing and proposed configuration as well as product details shall be furnished. iv. In s.no.9, complete certified compliance report shall be uploaded. v. In s.no. 9, the details of capacity expansion is wrongly mentioned and the same may be corrected. vi. In s.no.17, solid waste generation details shall be furnished. vii. In s.no. 18.1, AAQ modelling data is wrongly filled in and the same shall be corrected. viii. In s.no. 32, kindly furnish the time bound action plan for green belt development covering 33% of the 141.19 ha with appropriate layout. Addendum to EIA report The report uploaded on PARIVESH does not requisite information. In view of this, addendum to the existing EIA report shall be prepared covering the following: i. QCI/NABET accreditation status of the EIA consultant ii. Details of the existing Environmental Clearances (ECs) obtained. iii. Implementation status of the existing Environmental Clearances. iv. Details of the earlier Public consultation conducted and the compliance to the issues raised in the PH. v. Certified compliance report of existing environmental clearances from the concerned Regional Office of the MoEF&CC. vi. Closure report of Regional Office in case of non-compliances observed in the certified compliance report. vii. Existing baseline conditions based on the periodic environmental monitoring program viii. Proposed Expansion or Modernization or Change of product mix vis-à-vis with granted EC capacity along with percentage of increase in production. ix. Proposed plant lay out vis-à-vis with layout for which Environmental Clearance was granted. x. Proposed resources requirement (Land/raw materials/water/power) vis-à-vis with granted Environmental Clearance xi. Pollution load calculations (Air/Water/Solid & hazardous waste/traffic) vis-à-vis with granted Environmental Clearance xii. Environmental Management Plan for the proposed Expansion or Modernization or Change of product mix along with budget provision for implementation. xiii. Proposed Corporate Environment Responsibility activities for the additional investment proposed. xiv. Litigation if any, pending in any Court related to the project (or) activity. Pre-feasibility report has not been uploaded and the same be uploaded on PARIVESH. 16 Jun 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantShravan Kumar Goyal
DesignationDirector
Name of Company (Applicant Name should not be given here)SHRI BAJRANG POWER ISPAT LIMITED
AddressBorjhara, Urla - Guma Road Raipur (CG)
Print