EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/MH/MIS/32506/2015    ii. MoEFCC File No. : 11-43/2015-IA-III    iii.Short narrative of the project: CRZ clearance for setting up of 10 MW wind farm by dismantling and removal of existing 1.1 MW wind farm at Deogad, Dist. Sindhudurg, Maharashtra    iv. Project Sector : INFRA-2    v. Company/Proponent : MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.MaharashtraSindhudurgDevgad
 
   vii.Date of TOR Granted N/A viii.TOR letter issued by Ministry: N/A ix.Date of Submission for EC: 14 Mar 2016 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 04 Nov 2015   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: As required we have uploaded (in public hearing folder) the document wherein MCZMA has recommended the project to the SEIAA for grant of CRZ Clearance. Request you to present the proposal before EAC.
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAAn ADS letter No. 11-43/2016-IA.III(actual File No.11-43/2015-IA.III) dated 27th July, 2017 has already been issued with the request to provide the mandatory documents as per para no.4.2 of the CRZ notification, 2011 such as (i)EIA Report and Social Impact Assessment Report (ii) CRZ Map covering 7 Km radius etc (iii)Clearcut recommendation of the MCZMA. However, till date the same is still awaited. It is requested to provide the documents at the earliest to enable this Ministry in taking further course of action 02 Aug 2017
2. ADS Letter1.Renewable energy/Green Energy Project does not require EIA and social impact Assessment report as per EIA notification 2006. However Rapid EIA is attached as per CRZ 2011 notification. 2.CRZ Map covering 7 km radius is attached 3.The proposal was included before MCZMA 95th meeting held on dated 13th January 2015 and recommended for the same (minutes attached), however since as per the amended CRZ notification dated 28th November 2014, the activities which are not covered under EIA notification, 2006, are to be dealt at State level for CRZ clearance. Therefore MCZMA recommended the proposal and forwarded it to SEIAA. As per Para 4 (ii) (h) of CRZ Notification 2011,facilities for generating power by Non-Conventional Energy Resources shall require clearance from MoEF & CC .Therefore SEIAA forwarded the proposal to MoEF &CC for further necessary action in the matter(letter attached). 17 Oct 2017
4. Accredited Consultant Details
   i. Accreditation status : No    ii. Reason for not hiring the Consultant : Since this project does not require EIA as per EIA notification 2006, the Consultant is not required. Similarly, the required information /data is available with the user agency.
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Balchandra    ii. Designation : Chief Engineer    iii. Name of Company(Applicant Name should not be given here) : MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO    iv. Address : Prakash, 5th Floor, Station Road, Bandra (E), Mumbai-400051 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL
Print