Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Setting Up of 5 MLD Common Effluent Treatment Plant’ at Kadechuru Industrial Area, Yadgiri Taluk, Yadgiri District, Karnataka by M/s Mother Earth Environ Tech Pvt Ltd
(b)Name of the Company / Organisation MOTHER EARTH ENVIRONTECH PVT LTD
(c)Registered Address no.2542,28th cross,17th main, BSK 2ND STAGE BANGALORE-70,,Bangalore Urban,Karnataka-560070
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant PARAMESH TN
(b)Designation (Owner/ Partner/ CEO) MANAGING DIRECTOR
(c)Address nO. 2542,28TH CROSS,17TH MAIN ,BSK 2ND STAGE, BANGALORE,,Test,Bangalore Urban,Karnataka-560070
(d)Pin code 560070
(e)E-mail raghavendra.k@motherearthenviron.com
(f)STD Code. 80(f)Telephone No. 26712303
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(h) Common Effluent Treatment Plants (CETPs)
Minor Activity
(b)Category A
(c)Proposal Number IA/KA/MIS/152717/2020
(d)Master Proposal Number(Single Window) SW/152714/2020
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 158, 159, 160, 161, 162, 163 & 164
(b)Pincode 585221
(c)Bounded Latitudes (North)
From
Degree 77.308658
Minutes
Second
From
Degree 77.312196
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 16.518866
Minutes
Second
From
Degree 16.523699
Minutes
Second
(e)Survey of India Topo Sheet No. E43X06
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 365
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5.8
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 10-22/2020-IA-III
(c)Date of Apply of TOR 19 Feb 2020
(d)Date of Issue of TOR / Standard ToR 23 Apr 2020
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Located in a notified Industrial Estate
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)CETP5 MLD
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Common Effluent Treatment Plant (CETP)5Million Liters per DayPipe Conveyor
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 154.72
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.35
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.3
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)NA0OthersNA0Pipe Conveyor0 OthersNCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2017 To 28 Feb 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube361133.780
(2.)OthersCOMili Gram per Meter Cube0.880.110.862
(3.)PM10Micro Gram per Meter Cube745672.5100
(4.)PM2.5Micro Gram per Meter Cube33121560
(5.)SO2Micro Gram per Meter Cube331127.680
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l440215200600
(2.)Chloridesmg/l650222501000
(3.)Fluoridemg/l0.2011.5
(4.)TSSmg/l0000
(5.)OthersCalciummg/l1265075200
(6.)pHNA7.857.216.58.5
(7.)TDSmg/l18403955002000
(8.)Heavy MetalsZincmg/l00515
    14.3.     No. of Surface Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.947.62C
(2.)BODmg/l10C
(3.)OthersTDSmg/l355145C
(4.)CODmg/l44C
(5.)DOmg/l00C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))434070
(2.)Leq(Day)A-weighted decibels(dB(A))555075
    14.5.     No. of Soil Sample Monitored locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milligram per Kilogram246.5120.5
(2.)Electric ConductivityMillisiemens per Centimetre145.523.3
(3.)pH7.166.66
(4.)N(Nitrogen)Milligram per Kilogram70.854.8
(5.)P(Phosphorus)Milligram per Kilogram84.018.3
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.15 To 8.75
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.77 To 9.53
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTreated Effluent5760 Not Appliacble PipelineOthersTreated Effluentnil01 Jan 19905000
(2.)OthersKIADB70Copy of Permission LetterPipelineOthersKIADBI&C/ID/SLSWCC-90/E-2/2015-1607 Apr 2016400
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewage6.6510Septic Tank with Soak pitOthersOwn Land6.650
(2.)Boiler blow down235000CETPReuse within the Plant & Recycling23
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 29.65
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 29.65
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used / spent oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2.0Tons0RoadAuthorized Recyclers
(2.)AshFly Ash256Tons0RoadOthersFly ash brick making/cement plant
(3.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)730Tons0RoadOthersDisposed to cement plant/TSDF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube73.60.80.7374.34100
(2.)PM2.5Microgram per Meter Cube32.60.80.7333.3460
(3.)SO2Microgram per Meter Cube32.60.86.4639.0780
(4.)NOxMicrogram per Meter Cube37.20.81.4238.6380
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boiler (6 TPH-4 Nos)Coal/Briquette240.75PM100.55
(2.)DG set (4 Nos)Diesel100.2NOx0.10
(3.)DG set (4 Nos)Diesel100.2SO20.20
(4.)Boiler (6 TPH-4 Nos)Coal/Briquette240.75SO25.33
(5.)Boiler (6 TPH-4 Nos)Coal/Briquette240.75NOx1.10
(6.)DG set (4 Nos)Diesel100.2PM100.05
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 5500
(b)Source Guberga Electricity Supply Company
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 4 No of DG sets each of capacity 500 KVA
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 3.567
    Total Land (ha.) 3.567
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 3.567
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Nil 0
    Total (ha.) 3.5670
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant1.011
(2.)Green belt1.177
(3.)OthersRoad, Coal storage area & Future expansion1.379
Total (ha.) 3.567
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNil0Nil
(2.)ESAsNil0Nil
(3.)ESZsNil0Nil
(4.)NPANil0Nil
(5.)CorridorsNil0Nil
(6.)Wildlife CorridorsNil0Nil
(7.)Critically Polluted AreaNil0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNil0Nil
(2.)ForestNil0Nil
(3.)Archaeological SitesNil0Nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 3.57
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Bhima river
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 8.2
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 50
(e)No. of working days 365
(f)Total Manpower 210
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.18
(b)Percentage of Total Project Area 33.08
(c)No. of Plants to be Planted 1200
(d)Funds Allocated for Plantation 1000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalTreatment of effluent various industries
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 6
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 2
(d)Total plot area (sqm) 35670
(e)Total built up area (sqm) 500
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 4
(b)Capacity 165
(c)No. of Recharge Pits 73
(d)Capacity 7.5
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking car parking for 20 cars and 2 wheeler parking for
5.
Energy Saving Measures:
(a)Source/Mode Solar Street light & power generation
(b)Percentage 1
(c)Quantity 50
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area No water body will be affected
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA0155
(ii)Name of the EIA Consultant ABC Techno Labs India Private Limited
(iii)Address ABC Tower, No. 400, 13th Street, SIDCO Industrial Estate - North Phase, Ambattur, Chennai - 600098
(iv)Mobile No. 9566067777
(v)Landline No. 0442526778
(vi)Email Id abc@abctechnolab.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 24 May 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterSir, we are updated the EIA report covering effluent from other sources and attached herewith. 17 Jul 2020
2.NAReference is invited to your e-mail dated 01.07.2020 wherein it has been desired to refer your application again to EAC (Infra-2) in its next meeting. The Competent Authority has granted the approval for considering your above mentioned request. You are therefore requested to keep looking at Parivesh Portal w.r.t. consideration of your proposal in the forthcoming meeting. You may also like to submit additional information, if any for consideration of EAC(Infra-2). 10 Jul 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPARAMESH TN
DesignationMANAGING DIRECTOR
Name of Company (Applicant Name should not be given here)MOTHER EARTH ENVIRONTECH PVT LTD
Addressno.2542,28th cross,17th main, BSK 2ND STAGE BANGALORE-70
Print