Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Propose Expansion for Speciality Chemicals & Agrochemical Intermediates
(b)Name of the Company / Organisation M/S. SAJJAN INDIA LIMITED
(c)Registered Address Plot No. 6102-6103, 6117-6119, 5809-5810, GIDC Estate, Ankleshwar,,Bharuch,Gujarat-393002
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Arun Mehta
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address Plot No. 6102-6103, 6117-6119, 5809-5810, GIDC Estate, Ankleshwar,,,Bharuch,Gujarat-393002
(d)Pin code 393002
(e)E-mail grk@sajjan.com
(f)STD Code. 2646(f)Telephone No. 250403
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/152708/2019
(d)Master Proposal Number(Single Window) SW/152707/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. 6102-6103, 6117-6119, 5809-5810 GIDC ESTA
(b)Pincode 393002
(c)Bounded Latitudes (North)
From
Degree 21.628944
Minutes
Second
From
Degree 21.629019
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 73.042342
Minutes
Second
From
Degree 73.045636
Minutes
Second
(e)Survey of India Topo Sheet No. F43N2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 81
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 8
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA/GJ/IND2/126575/2019
(b)Date of Apply of TOR 21 Nov 2019
(c)Date of Issue of TOR / Standard ToR 24 Feb 2020
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project is located within GIDC Industrial Estate.
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Reactor1 KL2 Nos.
(2.)Reactor5 KL6 Nos.
(3.)Reactor6 KL4 Nos.
(4.)Reactor6.3 KL22 Nos.
(5.)Reactor10 KL13 Nos.
(6.)Reactor20 KL35 Nos.
(7.)Reactor25 KL5 Nos.
(8.)Reactor0.87 KL2 Nos.
(9.)Reactor1.3 KL2 Nos.
(10.)Reactor1.4 KL2 Nos.
(11.)Reactor1 KL5 Nos.
(12.)Reactor3.1 KL2 Nos.
(13.)Reactor3.4 KL2 Nos.
(14.)Reactor3.8 KL2 Nos.
(15.)Reactor15 KL11 Nos.
(16.)Reactor16 KL29 Nos.
(17.)Reactor20 KL17 Nos.
(18.)Reactor0.87 KL2 Nos.
(19.)Reactor0.5 KL4 Nos.
(20.)Reactor3 KL1 Nos.
(21.)Reactor2 KL1 Nos.
(22.)Reactor2.5 KL1 Nos.
(23.)Reactor4 KL7 Nos.
(24.)Reactor4.5 KL1 Nos.
(25.)Reactor8 KL16 Nos.
(26.)Reactor12.5 KL24 Nos.
(27.)Reactor18 KL2 Nos.
(28.)Reactor2.5 KL3 Nos.
(29.)Reactor2.6 KL2 Nos.
(30.)Reactor1 KL5 Nos.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Benzene Derivatives5896Tons per AnnumRoad
(2.)Chlorinated Paraffin Wax1870Tons per AnnumRoad
(3.)Heterocyclic Derivatives4735Tons per AnnumRoad
(4.)Napthelene Based Dye Intermediates115Tons per AnnumRoad
(5.)Para quinone Derivatives30Tons per AnnumRoad
(6.)Pyridine Derivatives2930Tons per AnnumRoad
(7.)Pyrimidine Derivatives2089Tons per AnnumRoad
(8.)Pyrimidine-Pyridine Derivatives640Tons per AnnumRoad
(9.)Quinoxaline Derivatives50Tons per AnnumRoad
(10.)Triazine Derivatives280Tons per AnnumRoad
(11.)Agro and Pharma Intermediates (Napthols & Bases)3444Tons per AnnumRoad
(12.)Thiol Derivatives490Tons per AnnumRoad
(13.)R & D Product360Tons per AnnumRoad
(14.)Electrolyte30Tons per AnnumRoad
(15.)Pyrimidine Chloro Derivatives1840Tons per AnnumRoad
(16.)Benzene Nitro Derivatives184Tons per AnnumRoad
(17.)Benzidines and Alkyl Aromatics130Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 05 Mar 2020
(iv)Valid Upto 15 Jan 2025
(v)File No. AWH - 107037
(vi)Application No. 15600
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 469.03
(b) Funds Allocated for Environment Management (Capital) (in Crores) 20.02
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.90
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 11.16
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1413276
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1413276
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HCI [ 30%]2012.69Tons per AnnumLocal MarketRoad17 Open MarketCopy of Linkage
(2.)Acetic acid4365.19Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(3.)Xylene10701.3Tons per AnnumLocal MarketRoad50 Open MarketCopy of Linkage
(4.)Thionyl chloride6091.44Tons per AnnumLocal MarketRoad50 Open MarketCopy of Linkage
(5.)Bromine4724.73Tons per AnnumLocal MarketRoad15 Open MarketCopy of Linkage
(6.)Isopropyl Acetate9048Tons per AnnumLocal MarketRoad150 Open MarketCopy of Linkage
(7.)EDC8810Tons per AnnumLocal MarketRoad45 Open MarketCopy of Linkage
(8.)Sulfuric Acid21060Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(9.)Toluene10310.27Tons per AnnumLocal MarketRoad58 Open MarketCopy of Linkage
(10.)Chlorine2769.65Tons per AnnumLocal MarketRoad7 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube96.1249.2595.54100
(2.)PM2.5Micro Gram per Meter Cube58.1026.655860
(3.)SO2Micro Gram per Meter Cube26.7216.9225.7780
(4.)NOxMicro Gram per Meter Cube28.5317.5227.6380
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l32880120
(2.)Fluoridemg/l0011.5
(3.)Heavy MetalsZincmg/l00515
(4.)TDSmg/l21601825002000
(5.)Chloridesmg/l549.76622501000
(6.)pHNA8.346.786.58.5
(7.)Total Hardnessmg/l866.6460200600
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l5.805.80A
(2.)BODmg/l00A
(3.)CODmg/l2.462.46A
(4.)pHNA7.487.48A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))544555
(2.)Leq(Night)A-weighted decibels(dB(A))444245
    14.5.     No. of Soil Sample Monitored locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram164.598.5
(2.)Electric ConductivityMillisiemens per Centimetre5.081.38
(3.)P(Phosphorus)Milligram per Kilogram89.2715.9
(4.)pH7.997.21
(5.)K(Potassium)Milligram per Kilogram721326.9
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 30
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 20
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGIDC Water Supply229010Copy of Permission LetterPipelineOthersGIDC PipelineNTA/ANK/DEE(WS)/199208 Nov 20192290
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic91160STPOthersReuse in Gardening910
(2.)Industrial753855ETP, Stripper, MEE, ATFD & ROOthersFETP of NCT77676
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 844
(b)Total Discharged Water (Kilolitre per Day) 676
(c)Total Reused Water (Kilolitre per Day) 168
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Fly AshFly Ash360Tons40RoadOthersSent to Brick manufacturer.
(2.)Distillation ResidueIndustrial Waste1220Tons19RoadCo-Processing
(3.)Process WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1240Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)Spent AcidIndustrial Waste5492.45Tons60RoadOthersCompany have Valid Rule - 9 Permission
(5.)Inorganic AcidIndustrial Waste20236Tons80RoadOthersCompany have Valid Rule - 9 Permission
(6.)Spent SolventIndustrial Waste1456Tons7RoadOthersUnder Rule - 9
(7.)Spent CatalystIndustrial Waste85.6Tons15RoadOthersCompany have Valid Rule - 9 Permission
(8.)Spent SolventIndustrial Waste69410.36Tons65RoadOthersCompany have Valid Rule - 9 Permission S
(9.)Used OilIndustrial Waste70Tons10RoadOtherssell to authorized re-refiners/recyclers
(10.)Chemical SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)19800Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(11.)Incinerator ash & Flue Gas cleaning residueIndustrial Waste320Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(12.)Empty Barrels/ Containers/Bags/Liners contaminatedIndustrial Waste315Tons10RoadOthersSend back to supplier
(13.)Metal hydrogen SulphatesIndustrial Waste4274Tons150RoadOthersCompany have Valid Rule - 9 Permission
(14.)AmmoniaIndustrial Waste5768Tons50RoadOthersCompany have Valid Rule - 9 Permission
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube96.122.730.0196.14100
(2.)PM2.5Microgram per Meter Cube58.102.730.0158.1260
(3.)SO2Microgram per Meter Cube26.722.730.0226.7580
(4.)NOxMicrogram per Meter Cube28.532.730.028.5480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)boiler - INatural Gas420.3OthersSPM, SO2, NOx150-262-94
(2.)Boiler - IIICoal440.3OthersSPM, SO2, NOx150-262-94
(3.)Boiler - IINatural Gas440.3OthersSPM, SO2, NOx150-262-94
(4.)Boiler - VCoal440.3OthersSPM, SO2, NOx150-262-94
(5.)Boiler - IVCoal440.3OthersSPM, SO2, NOx150-262-94
(6.)D.G SetDiesel110.2OthersSPM, SO2, NOx150-262-94
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 14000
(b)Source DGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 7000 KVA
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 10.2746
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 10.2746
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 2.2938
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0.1167
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0.3592
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : (Scrub land, Residential Area, Mud Flats 0.38
    Total (ha.) 3.1496999999999997
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant6.16
(2.)Green belt4.1146
Total (ha.) 10.2746
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0--
(2.)ESZsNA0--
(3.)CorridorsNA0--
(4.)Wildlife CorridorsNA0--
(5.)ESAsNA0--
(6.)Critically Polluted AreaAnkleshwar3--
(7.)NPANA0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0--
(2.)Archaeological SitesNA0--
(3.)Defence InstallationsNA0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 10.27
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species 10 Schedule-I Species
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 10.225 Lakh
(iii)Period of Implementation 2 Years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 60
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 5
(e)No. of working days 350
(f)Total Manpower 120
32.
Green Belt in Ha:
(a)Total Area of Green Belt 4.11
(b)Percentage of Total Project Area 40.00
(c)No. of Plants to be Planted 5212
(d)Funds Allocated for Plantation 14600000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay Order Against NABET/QCI
(ii)Name of the EIA Consultant M/s. Aqua Air Environmental Engineers. Pvt. Ltd.
(iii)Address 403, CENTER POINT, NR. KADIWALA SCHOOL, RING ROAD, SURAT – 395002 (GUJ.) INDIA
(iv)Mobile No. 9904496967
(v)Landline No. 0261246085
(vi)Email Id aqua_eia@yahoo.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 03 Mar 2016
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS Reply 31 Aug 2020
2.NA

The Committee has opined that if there is storage of raw materials having high safety issues, the project proponent shall go for advanced modelling and prediction and make management plan accordingly. The Committee after detailed deliberations, deferred the proposal and insisted for requisite information/clarification with respect to the following:

(i)           As project is located at CPA, PP needs to submit the Zero Liquid Discharge plan as per Ministry’s OM dated 31.10.2019 (CPA).

 

(ii)         PP needs to submit the following details on the Risk associated with the hazardous chemicals proposed to be used as a raw material;

 

·         Risk need to be carried out for medium and catastrophic ruptures/leak even for Methanol, Bromine including Hydrochloric acid, Sulphuric acid and Benzoyl Chloride etc.

·         Frequency/Probability of leak per year as done for any risk analysis.

·         Individual risk contours and societal risk F-N curves to assess against risk acceptance criteria using advanced 3D modeling.

(iii)        Adequate Plan for storage of rain water.

 

(iv)        PP needs to submit copy of all CTOs since inception of the project and the production details to verify the violation case, if any.

 

(v)         The Committee noted that for PM10 & PM2.5 value, the incremental value w.r.t. GLC is reported as 0.01-0.02 μg/ m3. In this regard verification of incremental values w.r.t. GLC and revised data needs to be submitted.

26 Jun 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantArun Mehta
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)M/S. SAJJAN INDIA LIMITED
AddressPlot No. 6102-6103, 6117-6119, 5809-5810, GIDC Estate, Ankleshwar