Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) PROPOSED SMALL SCALE LNG IMPORT, STROAGE & DISTRIBUTION FACILITY WITH TARGETED THROUGHPUT OF 1 MMTPA CAPACITY WITHIN THE INDUSTRIAL ZONE OF HALDIA DOCK COMPLEX AT HALDIA, WEST BENGAL, INDIA
(b)Name of the Company / Organisation VENERABLE LNG PRIVATE LIMITED
(c)Registered Address E 258, Shastri Nagar Delhi,,North West,Delhi-110052
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Mayank Garg
(b)Designation (Owner/ Partner/ CEO) MD
(c)Address E 258 Shastri Nagar Delhi 110052,,Sadar Bazar,North,Delhi-110052
(d)Pin code 110052
(e)E-mail mayank@vlng.in
(f)STD Code. 11(f)Telephone No. 40666300
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity6(a) Oil & gas transportation pipe line (crude and refinery/ petrochemical
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/IND2/93561/2019
(d)Master Proposal Number(Single Window) SW/152427/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. The proposed LNG terminal will be located within i
(b)Pincode 721605
(c)Bounded Latitudes (North)
From
Degree 220156.38
Minutes
Second
From
Degree 220206.76
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 880552.02
Minutes
Second
From
Degree 880608.54
Minutes
Second
(e)Survey of India Topo Sheet No. F45K8
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 0.5
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.05
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)West BengalEast MedinipurSutahata - I
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/41/2019-IA-II(I)
(b)Date of Apply of TOR 30 Jan 2019
(c)Date of Issue of TOR / Standard ToR 23 Mar 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The proposed LNG terminal will be located within i
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)LNG Storage1 MMTPAA small scale LNG terminal
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)LNG1OthersMMTPAOthersLNG Carriers through Bay of Bengal Sea
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 700
(b) Funds Allocated for Environment Management (Capital) (in Crores) 12
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 10
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)LNG1OthersMMTPALNG Gobal MarketOthersby LNG carrier3000 OthersVLNG LetterCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)OthersCOMicro Gram per Meter Cube7821567702000
(2.)PM2.5Micro Gram per Meter Cube49.117.248.560
(3.)SO2Micro Gram per Meter Cube26.58.826.180
(4.)NOxMicro Gram per Meter Cube39.615.339.180
(5.)PM10Micro Gram per Meter Cube81.231.480.2100
    14.2.     No. of Ground Water monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.47.16.58.5
(2.)Total Hardnessmg/l320236200600
(3.)Fluoridemg/l0.460.1411.5
(4.)Chloridesmg/l3541862501000
(5.)Heavy MetalsIronmg/l0.240.180.30.3
(6.)TSSmg/l1.01.000
(7.)TDSmg/l13467105002000
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.67.1C
(2.)BODmg/l33C
(3.)OthersTotal Hardness as CaCO3mg/l276197C
(4.)DOmg/l6.26C
(5.)CODmg/l55C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))63.349.075
(2.)Leq(Night)A-weighted decibels(dB(A))59.446.370
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.97
(2.)K(Potassium)Kilogram per hectare312.5195.2
(3.)P(Phosphorus)Kilogram per hectare138.655.3
(4.)Electric ConductivityMillisiemens per Centimetre220142.8
(5.)N(Nitrogen)Kilogram per hectare134.858.6
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 11.63 To 2.71
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 16.34 To 3.05
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersHaldia Port Water Supply40.2Copy of Permission LetterPipelineOtherspipelineVLNG/MOEF&CC/2020/402 May 20204
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)domestic sewage3.23.2sewage drainage system which shall be provided by Haldia dock complexDischarge into Seawater Body3.2
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 3.2
(b)Total Discharged Water (Kilolitre per Day) 3.2
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Oily wasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.5Kilolitre0.01RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube29.5010.1629.6780
(2.)PM10Microgram per Meter Cube81.20081.21100
(3.)PM2.5Microgram per Meter Cube49.10049.1160
(4.)SO2Microgram per Meter Cube26.50026.5180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)FlareLNG166NOx4.8
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 3500
(b)Source West Bengal State Electricity Distribution Company
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1500 KVA
(e)Stack Height (in m) 7.8
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 11.48
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 11.48
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 8164.80
(b)Waste/Barren Land (ha.) 1749.60
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 12862.80
(e)Settlements (ha.) 1101.60
(f)Industrial (ha.) 2300.40
(g)Forest (ha.) 0
(h)Mangroves (ha.) 41.20
(i)Marine Area (ha.) 2000
(j)Others (ha.) : Aquaculture, Salt pan, Mud plot & Water-logged are 4179.60
    Total (ha.) 32400.0000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant11.48
Total (ha.) 11.48
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil within the study area0Nil within the study area
(2.)NPANil within the study area0Nil within the study area
(3.)WLSNil within the study area0Nil within the study area
(4.)Wildlife CorridorsNil within the study area0Nil within the study area
(5.)ESAsNil within the study area0Nil within the study area
(6.)ESZsNil within the study area0Nil within the study area
(7.)CorridorsNil within the study area0Nil within the study area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestReserved Forest near Pariyar Chak6.1WNW direction from the site
(2.)Archaeological SitesNil within the study area0Nil within the study area
(3.)Defence InstallationsNil within the study area0Nil within the study area
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 11.48
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired accquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 1
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Hugli river/Haldia Channel
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 0.1
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 20
(c)Temporary Employment- During Construction 290
(d)Temporary Employment- During Operation 30
(e)No. of working days 300
(f)Total Manpower 350
32.
Green Belt in Ha:
(a)Total Area of Green Belt 2
(b)Percentage of Total Project Area 17.42
(c)No. of Plants to be Planted 0
(d)Funds Allocated for Plantation 5000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThe proposed project will result in improvement of additional infrastructures as well as overall socio-economic development in the area. The people residing in the nearby areas will be benefited directly and or indirectly due to the proposed project. It is anticipated that the proposed project will provide benefits for the locals in two phases i.e. during construction phase as well as during operational stage of the project. VLNG shall employ local people to the extent possible in order to reduc
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/ENV/ACO/19/0957
(ii)Name of the EIA Consultant VIMTA LABS LTD
(iii)Address 142, IDA, Phase-2, Cherlapally, Hyderabad, Telangana
(iv)Mobile No. 9000711309
(v)Landline No. 0402726414
(vi)Email Id janardhan@vimta.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 19 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) pl provide the copy of notifn. issued for the project site being located in the industrial area issued before the yr 2006. OR otherwise provide the copy of EC issued for industrial area to avail PH exemption. (ii) applicability of CRZ clearance for LNG treminal and associated facilities. 28 May 2020
2.NAThe correction have been made as per the instruction received 15 Jul 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NAPl comply with the ADS dt. 25/11/2020 by MoEFCC. 25 Feb 2021
2. ADS Reply LetterThis has reference to above-mentioned subject and our letter dated 11th Nov 2020 (attached) we would like to update that the process to obtain CRZ Clearance from WBSCZMA got delayed due to COVID 19 situation, and now is expected by April-May 2021. We request you to please give us 3 months more time to complete all the requisite work as per the ADS. 17 Feb 2021
3.NAYour application has been examined and it is noted that PP has not submitted all the requisite information as sought by the EAC. PP w.r.t. State CZMA mentioned that " Work in progress, and CRZ clearance from WBSCZMA expected by January 2021". It is mentioned that the recommendations from State CZMA is must as project requires both CRZ & EC, therefore it can only be considered before the EAC after State CZMA recommendation. 25 Nov 2020
4. ADS Reply LetterNA 11 Nov 2020
5.NA

During deliberations, the EAC noted the following:

 

The EAC during deliberations noted that the proposed project is for LNG import, storage & distribution facility and as such there is no much impact on the environment is anticipated. The Committee has noted that the proponent has sought public hearing exemption claiming the project site as Industrial area. It is also noted that the transportation of LNG is planned through trucks and as such facility for parking is not sufficient in the plant. The Committee after deliberations has agreed for in principle recommendations to the project. However, the project being located in the CRZ II area, it first requires recommendations from the concerned State Coastal Zone Management Authority, on arriving at permissibility of such activities in the area, and its admissibility. The Committee after detailed deliberations has desired for additional information/inputs in respect of the following:

 

·         Recommendations from State Coastal Zone Management Authority.

·         Copy of Notification of project area being located in the Industrial area/estate.

·         Detailed transportation plan. Commitment for not parking vehicles outside plant premises/roads.

·         Revised layout plan with details of parking.

·         VOC analysis

·         Occupational health plan.

·         Conservation plan for Schedule-1 species in the area submitted with State Wildlife/Forest Dept.

·         Arsenic study in the ground water.

·         Detailed CER plan.

·         Safety and risk assessment using advanced modelling.

 

The proposal was therefore DEFERRED for the needful.

07 Sep 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantMayank Garg
DesignationMD
Name of Company (Applicant Name should not be given here)VENERABLE LNG PRIVATE LIMITED
AddressE 258, Shastri Nagar Delhi