EC Report
1.
Project Details
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? :
No
1.
Project Details
i. Proposal No. :
IA/RJ/MIN/19643/2013
ii. MoEFCC File No. :
J-11015/275/2013-IA-II(M)
iii.Short narrative of the project:
Limestone mine
iv. Project Sector :
Mining Projects
v. Company/Proponent :
M/s Associated Limestone Ltd.
vi.Details of State of the project
Details of State of the project
S.no.
State Name
District Name
Tehsil Name
1.
Rajasthan
chittorgarh
Dungla
vii.Date of TOR Granted
30 Dec 2013
viii.TOR letter issued by Ministry:
Annexure-TOR letter
ix.Date of Submission for EC:
25 Dec 2015
x.Project Type:
New
2.
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP:
Annexure-EIA/EMP
ii.Risk Assessment:
Annexure-Risk Assessment
iii.Public Hearing:
Annexure-Public Hearing
iv. Date of Public Hearing:
30 Nov 2012
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC:
Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter:
Annexure-Cover Letter
vii.Remarks:
Dear Sir, There was no communication from MoEF&CC through letter related to the decision of MoEF&CC except that the minutes of 32nd EAC meeting held on 29-30 April, 2015 was displaced on the MoEF&CC
3.
Additional Detail Sought
Additional Detail Sought
Sno.
ADS Letter
Remarks
Date of ADS
1.
NA
The Proposal of EC was appraised by the Reconstituted Expert Appraisal Committee in its 2nd meeting held during January 20-22, 2016 wherein the Committee deliberated at length the information submitted by Project Proponent and deferred the Proposal and sought the following information/clarifications for further consideration:- (i) A detailed analysis report on occupational health of the workers need to be submitted; (ii) Details of Crusher and Screening Plant along with flow diagram need to be submitted; (iii) Details of plantation carried out till date in and around the mine lease area; (iv) Copy of mine lease showing the mine lease area of 119ha to be submitted. (v) The Committee noted that the PP has submitted the Conservation Plan for Peacock, however, the budgetary provision are left blank. In this context the PP need to submit a copy of Conservation Plan for Schedule I Species along with budgetary provision and also the status of its approval with the Chief Wild Life W
04 Mar 2016
2.
ADS Letter
NA
10 Jun 2016
3.
ADS Letter
Additional Letter
14 Sep 2016
4.
ADS Letter
Dear Sir, With reference to the ADS letter dated 14.09.2016, we are attaching herewith the NOC from forest department regarding non- involvement of forest land within the mine lease area.
28 Nov 2016
4.
Accredited Consultant Details
i. Accreditation status :
Yes
ii. Accreditation No. :
Rev 35, 8th October, 2015 at S.No-116
iii. Name of Consultant:
M/S PERFACT ENVIRO SOLUTIONS PVT. LTD
iv. Address :
505, 5th Floor, NN Mall, Mangalam Palace, Sector – 3, Rohini - 110085
v. Mobile No.:
9818346370
vi. Landline No.:
01147528467
vii. Email Id:
assoagro@gmail.com
5.
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
i. Name of Applicant :
Mr. Subhash Agarwal
ii. Designation :
Owner
iii. Name of Company(Applicant Name should not be given here) :
M/s. Associated Limestone Ltd.
iv. Address :
C/o - 216, Shanti Nagar, Durgapura, Jaipur (Rajasthan)
v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
NIL