1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of Dyes Intermediates by Colorband Dyestuff Pvt. Ltd. | (b)Name of the Company / Organisation | COLORBAND DYESTUFF P LTD | (c)Registered Address | Plot No.-J 2327, Phase III, Notified Industrial Area, GIDC Vapi, Ta: Pardi,,Valsad,Gujarat-396195 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Hareshwar M Upadhyay | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Plot No.-J 2327, Phase III, Notified Industrial Area, GIDC Vapi, Ta-Pardi,,Pardi,Valsad,Gujarat-396195 | (d)Pin code | 396195 | (e)E-mail | ram@colorbandindia.com | (f)STD Code. | 22(f)Telephone No. | 40186666 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | B1 | Reason for Applying at Ministry | general | (c)Proposal Number | IA/GJ/IND2/150213/2019 | (d)Master Proposal Number(Single Window) | SW/149279/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | J-2317 | (b)Pincode | 396195 | (c)Bounded Latitudes (North) | | From | | Degree | 20.371014 | Minutes | | Second | | From | | Degree | 20.371142 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.949178 | Minutes | | Second | | From | | Degree | 72.949511 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43T3 & F43S15&S11 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 99 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 5.5 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | No.IA-J-11011/246/2019-IA-II(I) | (c)Date of Issue of TOR | 13 Sep 2019 | (f)Previous TOR Letter | NA | (b)Date of Apply of EC | 02 Aug 2020 | (c)Date of Issue of EC | 15 Feb 2021 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | Proposed Expansion will be done in Notified Industrial Area GIDC Vapi. | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | SPCB | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | | (iii)Letter No. | GPCB/CCA-VSD-548(2)ID:24418/ | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jun 12 2020 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | (N-N Di Ethyl) Meta Amino Methane Sulpfonylide | 1.1 | -1.1 | 0 | Others | TPM | Road | | (2.) | EBA Oil (Benzoyl Aceto Acetate) | 1.0 | -1.0 | 0 | Others | TPM | Road | | (3.) | N-N Di Cyano Ethyl Aniline | 1.0 | -1.0 | 0 | Others | TPM | Road | | (4.) | (OR) N,N-Diethyl Meta Toluidine(DEMT) | 0 | 10 | 10 | Others | TPM | Road | | (5.) | (OR) 3-N,N-(Diallyl)4-Methoxy Acetanilide(M-29) | 0 | 10 | 10 | Others | TPM | Road | | (6.) | (OR)1Ethyl-3Cyano-4Methyl-6Hydroxy-2Pyridinone(EP) | 0 | 10 | 10 | Others | TPM | Road | | (7.) | N-[(3-Diethylamino)Phenyl]MethaneSulpfoamide,M-34B | 0 | 10 | 10 | Others | TPM | Road | | (8.) | (OR) 3-Acetylamino-N,N-Diethyl Aniline(M-12) | 0 | 10 | 10 | Others | TPM | Road | | (9.) | (OR) N-Cyanoethyl,N-Benzyl Aniline(M-38) | 0 | 10 | 10 | Others | TPM | Road | | (10.) | N-N Di Hexyl Meta Toludine | 1.0 | -1.0 | 0 | Others | TPM | Road | | (11.) | (OR) MetaaminoPhenylBenzeneSulphonate(Y-114 Amine) | 0 | 10 | 10 | Others | TPM | Road | | (12.) | N,N-Bis(2-Cyanoethyl)Benzenamine(M-22) | 0 | 10 | 10 | Others | TPM | Road | | (13.) | (OR) M-39 | 0 | 10 | 10 | Others | TPM | Road | | (14.) | (OR)N,N-Bis(3Methoxy-3oxypropyl)Benzenamide(M-19) | 0 | 10 | 10 | Others | TPM | Road | | (15.) | BA-04SH | 0 | 5 | 5 | Others | TPM | Road | | (16.) | (OR) 2:6-Di-Bromo-4-Methyl Aniline(DBPT) | 0 | 5 | 5 | Others | TPM | Road | | (17.) | 2:4-Di Bromo Propionyl Chloride(DBPC) | 0 | 5 | 5 | Others | TPM | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Steam boiler (TPH) | 0.6 | 0 | 0.6 | Natural Gas fired | (2.) | D G set, kVA | 0 | 75 | 75 | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 21 Apr 2017 | (iv)Valid Upto | 31 Dec 2021 | (v)File No. | AWH-85399 | (vi)Application No. | 119696 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 4.5 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.20 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.09 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.1635 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 265.15 | (b)Existing quantity of raw material/fuel | 8.78 | (c)Total quantity of raw material/fuel | 273.92999999999995 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Aniline | 12.14 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (2.) | Boric Acid | 1.31 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (3.) | Methyl Cyano Acetate | 1.52 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (4.) | Sulfuric Acid | 1.83 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (5.) | Hydro Quinone | 0.11 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (6.) | Caustic lye | 8.51 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (7.) | Sodium bi carbonate | 2.35 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (8.) | Soda ash | 26.84 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (9.) | Meta amino phenol | 2.98 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (10.) | Acetic acid | 6.99 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (11.) | Allyl Chloride | 4.91 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (12.) | Oleum | 1.59 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (13.) | AB-40 Powder | 0.49 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (14.) | ICE | 47.73 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (15.) | HCl | 20.63 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (16.) | Para Toludine | 1.25 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (17.) | Methane Sulphonyl Chloride | 3.92 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (18.) | N- Ethyl Amine | 1.21 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (19.) | Hydrogen Peroxide | 0.94 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (20.) | Thionyl chloride | 1.93 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (21.) | Magnesium oxide | 0.5 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (22.) | Zinc chloride | 1.25 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (23.) | Acrylic acid | 0.78 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (24.) | Toluene | 2.13 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (25.) | Acetic anhydride | 6.87 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (26.) | Catalyst | 0.04 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (27.) | Benzene Sulfonyl Chloride | 4.89 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (28.) | Meta- Toluidine | 6.59 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (29.) | 3 Amino 4 Methoxy acetanilide | 7.06 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (30.) | Methyl Acrylate | 8.42 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (31.) | Bromine | 4.13 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (32.) | Meta Phenylene Diamine | 6.9 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (33.) | Liq. Ammonia | 0.83 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (34.) | Methyl Chloro Acetate | 3.2 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (35.) | Di ethyl sulphate | 47.11 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (36.) | Benzyl Chloride | 10.63 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (37.) | methyl aceto acetate | 1.89 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (38.) | Aluminum chloride | 0.95 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | (39.) | Acrylo Nitrile | 10.58 | Others | TPM | indigenous | Road | | 100 | Others | Local dealer | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2019 To 31 Dec 2019 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 16.5 | 7.9 | 13.9 | 80 | (2.) | PM10 | | Micro Gram per Meter Cube | 87.1 | 60.3 | 78.4 | 100 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 47.7 | 31.2 | 40.5 | 60 | (4.) | NOx | | Micro Gram per Meter Cube | 21.6 | 13.2 | 18.4 | 80 | (5.) | Others | CO | Micro Gram per Meter Cube | 592 | 332 | 495.8 | 2000 | |
14.2. No. of Ground Water monitoring locations : 7 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (2.) | TDS | | | mg/l | | 1032 | 704 | 500 | 2000 | (3.) | Chlorides | | | mg/l | | 306 | 184 | 250 | 1000 | (4.) | Total Hardness | | | mg/l | | 624 | 324 | 200 | 600 | (5.) | pH | | | Others | pH unit | 7.62 | 7.18 | 8 | 8 | (6.) | Fluoride | | | mg/l | | 0.7 | 0.5 | 1.0 | 1.5 | (7.) | Heavy Metals | | Zinc | mg/l | | 0.2 | 0.11 | 5 | 15 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 6 | 4 | E | (2.) | COD | | mg/l | | 18 | 12 | E | (3.) | DO | | mg/l | | 6.2 | 5.7 | E | (4.) | pH | | Others | pH unit | 7.54 | 7.18 | E | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 56.4 | 42 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 62.2 | 49.8 | 75 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Others | mg/100g | 15.2 | 9.6 | (2.) | K(Potassium) | Others | mg/100g | 1.8 | 1.4 | (3.) | N(Nitrogen) | Percent | | 0.08 | 0.06 | (4.) | Electric Conductivity | Others | dS/m | 1.86 | 1.0 | (5.) | pH | Others | pH unit | 7.68 | 7.42 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 15 To 20 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 5 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | GIDC Water Supply | 11.88 | 10 | Copy of Permission Letter | Pipeline | | Others | GIDC Pipeline | NO.GIDC/RM/VPI/ALT/PLT/2086 | 17 Jul 2015 | 12 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic effluent | 1 | 2 | septic tank/soak pit | Others | septic tank/soak pit | 0 | 1 | (2.) | Industrial Effluent | 5.94 | 10 | ETP/CMEE | Discharge into Seawater Body | | | 5.94 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 6.94 | (b)Total Discharged Water (Kilolitre per Day) | 6.94 | (c)Total Reused Water (Kilolitre per Day) | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Waste from ETP | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 2.0 | Tons | 50 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (2.) | Discarded Containers | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 2.0 | Tons | 20 | Road | | Authorized Recyclers | | (3.) | HCl(30%) from scrubber | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 31.3 | Tons | 50 | Road | | Others | Recycle in process | (4.) | Spent solvent | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 26.44 | Tons | 50 | Road | | Others | Recycle in process | (5.) | Used oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.01 | Tons | 50 | Road | | Authorized Recyclers | | (6.) | Bleed liquor from scrubber | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 40.89 | Tons | 50 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | NOx | | Microgram per Meter Cube | 21.5 | 0.05 | 2.17 | 23.68 | 80 | (2.) | SO2 | | Microgram per Meter Cube | 16.40 | 0.05 | 0.07 | 16.48 | 80 | (3.) | PM2.5 | | Microgram per Meter Cube | 45.8 | 0.05 | 0 | 45.9 | 60 | (4.) | PM10 | | Microgram per Meter Cube | 86.4 | 0.05 | 0 | 86.5 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Steam Boiler | Natural Gas | 11 | 0.3 | Others | SO2, NOX | 0.0004,0.05 | (2.) | Reaction Vessel of Product-(BA-04SH, DBPT,DBPC) | Water and alkali | 11 | 0.15 | Others | SO2,HBr,HCl,Br2 | 0.0003,0.0002,0.0001,0.00002 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 400 | (b)Source | Dakshin Gujarat Veej Co. Ltd. | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | One D.G. set of 75 kVA | (e)Stack Height (in m) | 11 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0.0583 | Total Land (ha.) | 0.0583 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 18809 | (b)Waste/Barren Land (ha.) | 276 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 1223 | (e)Settlements (ha.) | 4357 | (f)Industrial (ha.) | 1325 | (g)Forest (ha.) | 149 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Open Vegetation, Plantation, Scrub Land | 5261 | Total (ha.) | 31400.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 0.0272 | | (2.) | Green belt | | 0.0233 | | (3.) | Others | Storage area and open space | 0.0053 | | (4.) | Area for Solid Waste Management | | 0.0025 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | GIDC Vapi | 2 | Project located in GIDC Vapi | (2.) | Corridors | NIL | 0 | NIL | (3.) | WLS | NIL | 0 | NIL | (4.) | NPA | NIL | 0 | NIL | (5.) | ESAs | NIL | 0 | NIL | (6.) | ESZs | NIL | 0 | NIL | (7.) | Wildlife Corridors | NIL | 0 | NIL | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | NIL | 0 | NIL | (2.) | Archaeological Sites | | NIL | 0 | NIL | (3.) | Defence Installations | | NIL | 0 | NIL | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0.06 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Pavo cristatus/Indian Peafowl | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | Rs. 1.50 lakhs | (iii)Period of Implementation | After getting EC from Authority | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | Yes | (i)Uploaded copy of approval | Copy of approval | (ii)Letter No. | --- | (iii)Date of issue | 19 Jun 2020 | (iv)Recommendation | Acknowledgment is uploaded in approval tab. | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Daman Ganga river | (ii)Direction of Water Bodies in Buffer Area | South West | (iii)Distance of Water Bodies in Buffer Area | 5.01 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 10 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 330 | (f)Total Manpower | 10 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 160 | 73 | 233 | (2.) | Percentage of Total Project Area | 27.44 | 12.52 | 39.96 | (3.) | No. of Plants | 40 | 20 | 60 | (4.) | Funds Allocated | 0 | 10 | 10 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | local people will get employment | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/SA 085 | (ii)Name of the EIA Consultant | Eco Chem Sales and Services | (iii)Address | Office Floor, Ashoka Pavillion – A, Opp. Kapadia Health Club, Surat – 395 001 | (iv)Mobile No. | 9825123805 | (v)Landline No. | 0261223622 | (vi)Email Id | eco@ecoshripad.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 26 Oct 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | (i) This is an expansion proposal and as per TOR for expansion project, the PP shall submit the compliance report to the conditions of consents from the SPCB. However PP has not submitted the certified compliance report from SPCB as per TOR granted to PP. (S.No 9 of Form 2 has to revised and uploaded),
(ii) PP in SNo. 6 of Form 2 mentioned that EC was granted in 13.09.2019, however copy of EC is not uploaded in SNo. 6.
(iii) S. no. 23.1 of form 2 (CPA) mentioned; However PP has not submitted the Report as per the Ministry’s office memorandum 31st October, 2019 regarding projects located in Critically Polluted Area.
(iv) All old CTOs not uploaded to verify the violation, if any done by PP.
(v) Details of earlier production of various products with financial years needs to submit to check violation, if any.
(vi) PP submitted zero incremental value for PM10 & PM2.5 & SOx. Air Quality Impact Prediction mentioned (18.1 of form 2) is inadequate kindly check and correct it accordingly.
(vii) Effluent treatment mechanism with plan for Zero Liquid Discharge for the complete plant needs to be submitted
(viii) PP in form 2 (S.No. 23.1& 23.2-Details of Ecological Sensitivity), mentioned for all ecological sensitivity, the distance is zero Km. PP/Consultant has submitted wrong information.
(ix) PP in form 2 (S.No. 27) has not adequately mentioned the details of R&R. Everything mentioned zero.
(x) As per s.no. 28 of form 2, Schedule I species reported. But the approval of conservation plan to CWLW has not been submitted/uploaded. Details of approval regarding to conservation plan needs to be uploaded.
(xi) Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2)
(xii) It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. | 22 Apr 2020 | 2. | NA | (i) This is an expansion proposal and as per TOR for expansion project, the PP shall submit the compliance report to the conditions of consents from the SPCB. However PP has not submitted the certified compliance report from SPCB as per TOR granted to PP. (S.No 9 of Form 2 has to revised and uploaded),
(ii) PP in SNo. 6 of Form 2 mentioned that EC was granted in 13.09.2019, however copy of EC is not uploaded in SNo. 6.
(iii) S. no. 23.1 of form 2 (CPA) mentioned; However PP has not submitted the Report as per the Ministry’s office memorandum 31st October, 2019 regarding projects located in Critically Polluted Area.
(iv) All old CTOs not uploaded to verify the violation, if any done by PP.
(v) Details of earlier production of various products with financial years needs to submit to check violation, if any.
(vi) PP submitted zero incremental value for PM10 & PM2.5 & SOx. Air Quality Impact Prediction mentioned (18.1 of form 2) is inadequate kindly check and correct it accordingly.
(vii) Effluent treatment mechanism with plan for Zero Liquid Discharge for the complete plant needs to be submitted
(viii) PP in form 2 (S.No. 23.1& 23.2-Details of Ecological Sensitivity), mentioned for all ecological sensitivity, the distance is zero Km. PP/Consultant has submitted wrong information.
(ix) PP in form 2 (S.No. 27) has not adequately mentioned the details of R&R. Everything mentioned zero.
(x) As per s.no. 28 of form 2, Schedule I species reported. But the approval of conservation plan to CWLW has not been submitted/uploaded. Details of approval regarding to conservation plan needs to be uploaded.
(xi) Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2)
(xii) It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. | 22 Apr 2020 | 3. | NA | (i) This is an expansion proposal and as per TOR for expansion project, the PP shall submit the compliance report to the conditions of consents from the SPCB. However PP has not submitted the certified compliance report from SPCB as per TOR granted to PP. (S.No 9 of Form 2 has to revised and uploaded),
(ii) PP in SNo. 6 of Form 2 mentioned that EC was granted in 13.09.2019, however copy of EC is not uploaded in SNo. 6.
(iii) S. no. 23.1 of form 2 (CPA) mentioned; However PP has not submitted the Report as per the Ministry’s office memorandum 31st October, 2019 regarding projects located in Critically Polluted Area.
(iv) All old CTOs not uploaded to verify the violation, if any done by PP.
(v) Details of earlier production of various products with financial years needs to submit to check violation, if any.
(vi) PP submitted zero incremental value for PM10 & PM2.5 & SOx. Air Quality Impact Prediction mentioned (18.1 of form 2) is inadequate kindly check and correct it accordingly.
(vii) Effluent treatment mechanism with plan for Zero Liquid Discharge for the complete plant needs to be submitted
(viii) PP in form 2 (S.No. 23.1& 23.2-Details of Ecological Sensitivity), mentioned for all ecological sensitivity, the distance is zero Km. PP/Consultant has submitted wrong information.
(ix) PP in form 2 (S.No. 27) has not adequately mentioned the details of R&R. Everything mentioned zero.
(x) As per s.no. 28 of form 2, Schedule I species reported. But the approval of conservation plan to CWLW has not been submitted/uploaded. Details of approval regarding to conservation plan needs to be uploaded.
(xi) Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2)
(xii) It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. | 22 Apr 2020 | 4. | NA | (i) This is an expansion proposal and as per TOR for expansion project, the PP shall submit the compliance report to the conditions of consents from the SPCB. However PP has not submitted the certified compliance report from SPCB as per TOR granted to PP. (S.No 9 of Form 2 has to revised and uploaded),
(ii) PP in SNo. 6 of Form 2 mentioned that EC was granted in 13.09.2019, however copy of EC is not uploaded in SNo. 6.
(iii) S. no. 23.1 of form 2 (CPA) mentioned; However PP has not submitted the Report as per the Ministry’s office memorandum 31st October, 2019 regarding projects located in Critically Polluted Area.
(iv) All old CTOs not uploaded to verify the violation, if any done by PP.
(v) Details of earlier production of various products with financial years needs to submit to check violation, if any.
(vi) PP submitted zero incremental value for PM10 & PM2.5 & SOx. Air Quality Impact Prediction mentioned (18.1 of form 2) is inadequate kindly check and correct it accordingly.
(vii) Effluent treatment mechanism with plan for Zero Liquid Discharge for the complete plant needs to be submitted
(viii) PP in form 2 (S.No. 23.1& 23.2-Details of Ecological Sensitivity), mentioned for all ecological sensitivity, the distance is zero Km. PP/Consultant has submitted wrong information.
(ix) PP in form 2 (S.No. 27) has not adequately mentioned the details of R&R. Everything mentioned zero.
(x) As per s.no. 28 of form 2, Schedule I species reported. But the approval of conservation plan to CWLW has not been submitted/uploaded. Details of approval regarding to conservation plan needs to be uploaded.
(xi) Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2)
(xii) It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. | 22 Apr 2020 | 5. | NA | The correction have been made as per the instruction received | 02 Jul 2020 | 6. | NA | 1. Please read the earlier EDS sought by the Ministry earlier. The matter was again examined and noted that PP has not revised the Form 2 and not uploaded the requisite information on Parivesh Portal (For eg. Certified compliance report on CTO, as per TOR, has not uploaded in Form 2, only letter uploaded. PP/consultant has not uploaded the document on PH forwarded by SPCB to MoEFCC) Form 2 (S.no. 7.1)
2. It is pertain to mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action
3. It is also mentioned that after acceptance the Form 2 and EIA/EMP report can not be revise. Therefore, PP/Consultant is again requested to kindly do needful. | 28 Jul 2020 | 7. | NA | The correction have been made as per the instruction received | 02 Aug 2020 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Please find herewith attached legible Certified CCA Report as per ADS generated on 29.12.2020. | 29 Dec 2020 | 2. | NA | On examination it is noted that the some of the part of the report uploaded is not legible. Kindly upload the legible report so that the proposal may be placed before the EACV for appraisal. | 29 Dec 2020 | 3. | ADS Reply Letter | We have received certified CCA compliance report from GPCB and the same is enclosed herewith.
We request you to kindly consider our proposal in the next EAC Meeting | 23 Dec 2020 | 4. | NA |
The project proponent, vide email dated 02.09.2020, has requested to postponed the project appraisal as the certified compliance report of existing project is still awaited from the Gujarat Pollution Control Board. The Committee accepted the request of Project Proponent and deferred the proposal accordingly.
| 29 Sep 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Hareshwar M Upadhyay | Designation | Director | Name of Company (Applicant Name should not be given here) | COLORBAND DYESTUFF P LTD | Address | Plot No.-J 2327, Phase III, Notified Industrial Area, GIDC Vapi, Ta: Pardi |
|