Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) A new technical grade pesticides plant capacity of 750 MTPA by MS POPULAR CHEMICAL MANUFACTURER AND SUPPLIES
(b)Name of the Company / Organisation MS POPULAR CHEMICAL MANUFACTURER AND SUPPLIES
(c)Registered Address Hastha Hosamane Extension Chikmagalur, Karnataka,,Hassan,Karnataka-577101
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Vedanth M Prabhakar
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Hastha Hosmane Extension Chikmagalur Karnatak,,Chikkamagalur,Chikmagalur,Karnataka-577101
(d)Pin code 577101
(e)E-mail chemicalspopular@gmail.com
(f)STD Code. 8262(f)Telephone No. 239838
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity
(b)Category A
(c)Proposal Number IA/KA/IND2/145725/2018
(d)Master Proposal Number(Single Window) SW/145621/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey No. 380, Karagada village, Belur Tehsil, H
(b)Pincode 573115
(c)Bounded Latitudes (North)
From
Degree 131444.86
Minutes
Second
From
Degree 131450.44
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 755051.65
Minutes
Second
From
Degree 755054.33
Minutes
Second
(e)Survey of India Topo Sheet No. 48 O/15; 48 O/16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 713
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 965
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)JharkhandEast SinghbhummusabaniSurda
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number No.IA-J-11011/367/2018-IA-II(I)
(b)Date of Apply of TOR 02 Nov 2018
(c)Date of Issue of TOR / Standard ToR 18 Dec 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :17 Nov 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :18 Dec 2019
Distance of Public Hearing Venue from the Proposed Project :0.01
Project Site
State :Karnataka
District :Hassan
Tehsil :Belur
Village :Karagada
741. What is the impact of the chemical factory on the existing agricultural land, air, water and soil? 2. Is there any chances of getting health hazards like respiratory problems, through air pollutioOthersAdditional Deputy Commissioner
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Total Plot Area8215.12Sq.m.
(2.)Total Production Capacity750TPA
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Aluminium Phosphide500Tons per AnnumRoad
(2.)Zinc Phosphide250Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 5
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.25
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.10
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.05
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 162.55
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 162.55
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Paraffin Wax2.9Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(2.)Ammonium Carbamate19.50Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(3.)Zinc stearate4.5Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(4.)Zinc Dust39.90Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(5.)Urea4.20Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(6.)Groundnut Oil0.5Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(7.)Aluminium Powder35Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(8.)Graphite Powder5.80Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
(9.)yellow/Red Phosphorous50.25Tons per AnnumLocal MarketRoad10 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2018 To 28 Feb 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube71.9244.5571.41100
(2.)NOxMicro Gram per Meter Cube23.1713.7722.4080
(3.)OthersCOMicro Gram per Meter Cube0.850.180.854
(4.)PM2.5Micro Gram per Meter Cube71.9224.9839.6460
(5.)SO2Micro Gram per Meter Cube15.096.3311.7180
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l700362501000
(2.)OthersZincmg/l1.160.11515
(3.)TDSmg/l23563685002000
(4.)Heavy MetalsFemg/l0.280.10.30.3
(5.)pHNA7.136.526.58.5
(6.)Total Hardnessmg/l1080156200600
(7.)TSSNA0000
(8.)Fluoridemg/l10.511.5
    14.3.     No. of Surface Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.327.12D
(2.)DOmg/l5.75.1D
(3.)BODmg/l1.91.4D
(4.)CODmg/l12.28.16D
(5.)OthersTDSmg/l304206D
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))36.333.770
(2.)Leq(Day)A-weighted decibels(dB(A))50.540.475
    14.5.     No. of Soil Sample Monitored locations : 7
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare263.16169.65
(2.)P(Phosphorus)Kilogram per hectare85.1471.40
(3.)K(Potassium)Kilogram per hectare142.5695.04
(4.)pH7.827.52
(5.)Electric ConductivityMillisiemens per Centimetre387219
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.40 To 21.67
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.00 To 19.42
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTanker water supply19.135Copy of Permission LettermodeOthersTankerOthersTanker010 Mar 202019.13
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial Waste Water1.21.2Biological TreatmentGreen Belt Renewal Plant1.2
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1.2
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 1.2
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used OilIndustrial Waste0.05Kilolitre10RoadAuthorized Recyclers
(2.)Process wasteIndustrial Waste11.25Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Discarded barrelsIndustrial Waste10Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)ETP SludgeIndustrial Waste0.6Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Coffeee Husk Briquette ashIndustrial Waste38Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube63.714001.566100
(2.)SO2Microgram per Meter Cube11.714001.11380
(3.)NOxMicrogram per Meter Cube21.914000.72380
(4.)PM2.5Microgram per Meter Cube37.8940003860
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boiler0.6 TPH202PM101.311
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 65
(b)Source State Electricity Board
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 60 kVA(1 no.) and 25 kVA ( 1no.)
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0.8215
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0.8215
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 21553.72
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1235.52
(e)Settlements (ha.) 1345.91
(f)Industrial (ha.) 0
(g)Forest (ha.) 4431.92
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Fellow land and scrub land 9641.19
    Total (ha.) 38208.26
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersTotal Plot Area0.8215
Total (ha.) 0.8215
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone00
(2.)Wildlife CorridorsNone00
(3.)ESZsNone00
(4.)NPANone00
(5.)ESAsNone00
(6.)WLSNone00
(7.)CorridorsNone00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestKalasapur state forest5.07ENE
(2.)Archaeological SitesNone00
(3.)Defence InstallationsNone00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.82
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Yagachi Reservoir
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 4.61
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 20
(b)Permanent Employment-During Operation 30
(c)Temporary Employment- During Construction 20
(d)Temporary Employment- During Operation 10
(e)No. of working days 300
(f)Total Manpower 80
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.27
(b)Percentage of Total Project Area 32.87
(c)No. of Plants to be Planted 1500
(d)Funds Allocated for Plantation 50000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmental2868.00 Sq.m. area will be under greenbelt plantation. This will improve the surrounding environment and increase the aesthetic view.
(2.)FinancialInfrastructure will get improved and enhance the employment opportunity for both skilled and unskilled person from nearby area. Direct employment as well as indirect employment due to ancillary services will be given to the local people.
(3.)SocialDue to proposed project activity, social infrastructure will be improved by means of civilization, vocational training and basic amenities.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 169
(ii)Name of the EIA Consultant Wolkem India Limited
(iii)Address E- 101-102, Mewar Industrial Area, Madri, Udaipur – 313003 (Rajasthan)
(iv)Mobile No. 9772833883
(v)Landline No. 0294249460
(vi)Email Id info@wolkem.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 04 Feb 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation has not been submitted. Kindly upload the requisite documents. Form 2 (Sno. 7.1) (ii) TOR compliance is not adequate in EIA/EMP report and need to revise as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006. PP shall provide adequate TOR compliances in the EIA report (iii) Air Quality Impact Prediction (18.1 of form 2) mentioned wrong. Please correct the same (iv) Details of R&R (v) Status of Conservation Plan approval from CWLW. (vi) Status of Water approval. (vii) Details of membership for TSDF. (viii) Details of Raw material linkage (S. no. 13.1 of form 2) and its mitigation measure during transportation needs to be submitted. (ix) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Report. The EIA/EMP Report shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submitted the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. 05 Mar 2020
2.NAThe correction have been made as per the instruction received 27 Mar 2020
3.NA1. Please read the earlier EDS sought by the Ministry. The matter was again examined and noted that PP has not revised the Form 2 and not uploaded the requisite information. (For example, in S. No. 7.1 of Form 2, the letter from SPCB Head Office w.r.t. forwarding Public hearing proceedings to the Ministry as per EIA Notification 2006 has not be uploaded. However PP in its letter dated 17.03.2020 mentioned they have uploaded. Kindly rectify the error. 2. It is pertain to mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action. 3. It is also mentioned that after acceptance the application, Form 2 and EIA/EMP report can not be revise. Therefore, PP/Consultant is again requested to kindly do needful. 04 Apr 2020
4.NAThe correction have been made as per the instruction received 21 Apr 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS REPLY OF PROJECT "POPULAR CHEMICALS MANUFACTURERS AND SUPPLIES" 17 Jul 2020
2.NA

The EAC, after detailed deliberations decided to defer the proposal for want of requisite information as under and have asked the PP to revise the Report alongwith following clarification/information: -

                                             

(i)           The Committee noted that the KML file shows the construction at the project site and the project proponent has informed that the said construction is for their formulation unit. However, the project proponent could not explain the details and even no documentary evidence provided during the meeting. In this context, the Committee at first instance is of the view that the PP to explain all the details w.r.t. violation, if any, etc. 

 

(ii)         The project proponent need to submit clarification with proper proof to establish, past production details.

 

(iii)        Permission for fresh water withdrawal other than gram panchayat.

 

(iv)        Status of TSDF membership.

 

The EAC therefore deferred the proposal.

26 Jun 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVedanth M Prabhakar
DesignationPartner
Name of Company (Applicant Name should not be given here)MS POPULAR CHEMICAL MANUFACTURER AND SUPPLIES
AddressHastha Hosamane Extension Chikmagalur, Karnataka