1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of Chemical Manufacturing unit of M/s Flowtech Chemicals Pvt. Ltd. | (b)Name of the Company / Organisation | M/S FLOW TECH CHEMICALS PVT. LTD. | (c)Registered Address | PACL Campus, Industrial Area, Naya Nangal, District- Ropar, Punjab,,Ropar,Punjab-140126 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | S S Dahiya | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | PACL Campus, Industrial Area, Naya Nangal, District- Ropar, Punjab,,Ropar,Ropar,Punjab-140126 | (d)Pin code | 140126 | (e)E-mail | flowtechchemicals1@gmail.com | (f)STD Code. | 172(f)Telephone No. | 4669295 | (g)Fax No. | 4669295 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/PB/IND2/145121/2018 | (d)Master Proposal Number(Single Window) | SW/145103/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 512/979, 1218/578, 590-592 | (b)Pincode | 140126 | (c)Bounded Latitudes (North) | | From | | Degree | 312206.78 | Minutes | | Second | | From | | Degree | 312207.02 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 762042.04 | Minutes | | Second | | From | | Degree | 762042.04 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | H43E3 H43E7 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 351 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 4 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Punjab | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Orissa | Kendujhar | Harichandanpur | Talpada & Rebana R.F. | (2.) | Orissa | Jajpur | Sukinda | Daitari | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/335/2012-IA II (I) | (c)Date of Issue of TOR | 13 May 2018 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 29 Jul 2020 | (c)Date of Issue of EC | 28 Dec 2020 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 19 Jun 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| Project Premises | State : | Punjab | District : | Rupnagar | Tehsil : | Anandpur Sahib | Village : | PACL Campus, Naya Nangal |
| 160 | Safety Measures | Others | ADC | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Chandigarh | (iii)Letter No. | 5-731/2014/RO (NZ)/308 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Mar 4 2020 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Hydrochloric Acid | 38400 | 38400 | 76800 | Tons per Annum(TPA) | | Road | | (2.) | Chlorinated Paraffin | 19200 | 19200 | 38400 | Tons per Annum(TPA) | | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Chemical Manufacturing Plant | Chlorinated Paraffin wax, Hydrochloric acids | Chlorinated Paraffin wax, Hydrochloric acids | Chlorinated Paraffin wax, Hydrochloric acids | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 01 Jan 2019 | (iv)Valid Upto | 31 Dec 2021 | (v)File No. | CTOA/Renewal/RPN/2018/7572177 | (vi)Application No. | 7572177 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 7.60 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.54 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.08 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.20 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | c)Notified Eco-sensitive areas | Yes | d)Inter-State boundaries and international boundaries | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 33415 | (b)Existing quantity of raw material/fuel | 33415 | (c)Total quantity of raw material/fuel | 66830 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Liquid chlorine | 51902 | Tons per Annum | | Local | Road | | 0 | MoU | | Copy of Linkage | (2.) | Heavy Normal Paraffin | 14792 | Tons per Annum | | Local | Road | | 0 | MoU | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2018 To 31 Dec 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | Others | Cl2 | Micro Gram per Meter Cube | 15.1 | 2.1 | 12.6 | NS | (2.) | NOx | | Micro Gram per Meter Cube | 25.7 | 19.2 | 23.7 | 80 | (3.) | PM10 | | Micro Gram per Meter Cube | 82.2 | 64.5 | 80.9 | 100 | (4.) | SO2 | | Micro Gram per Meter Cube | 9.5 | 6.3 | 9 | 80 | (5.) | PM2.5 | | Micro Gram per Meter Cube | 45.2 | 27.1 | 44.1 | 60 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TDS | | | mg/l | | 380 | 308 | 500 | 2000 | (2.) | Chlorides | | | mg/l | | 48.2 | 38.9 | 250 | 1000 | (3.) | Total Hardness | | | mg/l | | 250 | 200 | 200 | 600 | (4.) | pH | | | NA | | 7.61 | 7.19 | 6.5 | 8.5 | (5.) | Heavy Metals | | Fe | mg/l | | 0.12 | 0.10 | 1.0 | 1.0 | (6.) | Heavy Metals | | Ca | mg/l | | 56 | 40 | 75 | 200 | (7.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (8.) | Fluoride | | | mg/l | | 0 | 0 | 1.0 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 1 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.81 | 7.72 | E | (2.) | COD | | mg/l | | 8.6 | 8.4 | E | (3.) | BOD | | mg/l | | 2 | 1.9 | E | (4.) | DO | | mg/l | | 7.2 | 6.6 | E | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 61.3 | 34.4 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 73.1 | 47.3 | 75 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Kilogram per hectare | | 3.0 | 1.22 | (2.) | pH | | | 8.76 | 7.80 | (3.) | N(Nitrogen) | Percent | | 2.4 | 1.1 | (4.) | K(Potassium) | Kilogram per hectare | | 88.3 | 50.2 | (5.) | Electric Conductivity | Millisiemens per Centimetre | | 504 | 194.2 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10.3 To 2.7 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 11.6 To 2.1 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 180 | 0 | Copy of Permission Letter | Pipeline | | Tube Well | | PACL 2014 | 25 Mar 2014 | 180 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Waste Water | 5.6 | 6 | Septic Tank | Reuse within the Plant & Recycling | | 5.6 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 5.6 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 5.6 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Solid waste | Municipal Solid Waste | | 1.75 | Tons | 3 | Road | | Others | As per norms by Municipal Council | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 72 | 0 | 0.24 | 72.3 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 38.9 | 0 | 0 | 39 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 7.2 | 0 | 0 | 7.3 | 80 | (4.) | NOx | | Microgram per Meter Cube | 21.1 | 0 | 3.4 | 25 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 0 | 0 | 0 | 0 | Others | NA | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 350 | (b)Source | PSPCL | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 2 | (e)Stack Height (in m) | 13.4 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 1.2 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 1.2 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 1.2 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : 0 | 0 | Total (ha.) | 1.2000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 1.2 | in Ha | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | Nangal Wildlife Sanctuary | 2.6 | Ecologically sensitive area - WLS present in study area | (2.) | Critically Polluted Area | NA | 0 | 0 | (3.) | ESAs | NA | 0 | 0 | (4.) | Corridors | NA | 0 | 0 | (5.) | Wildlife Corridors | NA | 0 | 0 | (6.) | NPA | Nangal Wildlife Sanctuary | 2.6 | Ecologically sensitive area - NPA present in study area | (7.) | ESZs | Eco sensitive zone of Nangal WLS | 2.6 | Ecologically sensitive area - ESZ present in study area | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NA | 0 | 0 | (2.) | Others | Wetland | Nangal Wetland/Reservoir | 2.6 | Present in study area | (3.) | Forest | | NA | 0 | 0 | (4.) | Defence Installations | | NA | 0 | 0 | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 1.24 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | (IWPA,1972) Faunal species i.e. Peacock or Indian Peafowl (Pavo cristatus), Python (Pythin molurus), Pangolin (Manis crassicaudata) and Leopard (Panthera pardus) | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | Rs. 40 Lakh | (iii)Period of Implementation | 5 years | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Satluj River | (ii)Direction of Water Bodies in Buffer Area | East | (iii)Distance of Water Bodies in Buffer Area | 3.5 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 50 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 350 | (f)Total Manpower | 50 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 1593.31 | 2389.96 | 3983.27 | (2.) | Percentage of Total Project Area | 13.27 | 19.91 | 33.18 | (3.) | Funds Allocated | 500000 | 1200000 | 1700000 | (4.) | No. of Plants | 200 | 397 | 597 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Landscaping | (2.) | Social | Employment | (3.) | Financial | Revenue generation | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/SA095 | (ii)Name of the EIA Consultant | M/S ECO LABORATORIES & CONSULTANTS PVT. LTD. | (iii)Address | Eco Bhawan, E-207, 204 & 205, Industrial Area, Phase VIII-B, (Sector- 74), Mohali (Punjab) - 160071 | (iv)Mobile No. | 9501514169 | (v)Landline No. | 0172461622 | (vi)Email Id | consulteco@yahoo.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 13 Dec 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | (i) Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation has not been submitted. Kindly upload the requisite documents. Form 2 (Sno. 7.1)
(ii) TOR compliance is not adequate in EIA/EMP report and need to revise as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006.
(iii) Air Quality Impact Prediction (18.1 of form 2) mentioned wrong. Please correct the same
(iv) Details of R&R
(v) This is an expansion case. Details of action plan on non compliances reported by MoEFCC RO needs to be submitted
(vi) Status of Conservation Plan approval from CWLW.
(vii) Status of Water approval.
(viii) Details of membership for TSDF.
(ix) Details of Raw material linkage (S. no. 13.1 of form 2) and its mitigation measure during transportation needs to be submitted.
(x) PP mentioned green belt @20%. PP Shall submit plan of about at least 30% Green belt development program along-with time line and budgetary allocation needs to be provided
(xi) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Report. The EIA/EMP Report shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submitted the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. | 05 Mar 2020 | 2. | NA | The correction have been made as per the instruction received | 17 Jul 2020 | 3. | NA | Your application vide dated 17.07.2020 has been examined and on perusal it is noted that the Nangal Wildlife Sanctuary is located at 2.6 Km. PP has mentioned that unit is in operation with earlier EC, However NBWL clearance has not obtained yet. Please clarify and provide justification why PP has operated without NBWL Clearance. It is noncompliance of EC. | 28 Jul 2020 | 4. | NA | The correction have been made as per the instruction received | 29 Jul 2020 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | ADS Reply dated 17.09.2020 | 07 Nov 2020 | 2. | NA |
The Committee after detailed deliberations has desired for additional information/inputs in respect of the following:
(i) Detailed action plan for management of emissions from the unit.
(ii) Incremental GLC due to the proposed project needs to be justified.
(iii) Details of protected/ESZ area within 10 km of the project site.
(iv) Copy of notification of ESZ details of the sanctuary and distance of the project from the sanctuary and the ESZ.
(v) CER plan based on the public hearing issues.
(vi) Details of fresh water requirement along with source.
(vii) Detailed effluent management plan along with quantity.
(viii) Details of conservation plan submitted to the Chief Wildlife Warden
(ix) Details regarding the operation of Unit without NBWL clearance.
The proposal was accordingly DEFERRED for the needful.
| 29 Sep 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | S S Dahiya | Designation | Director | Name of Company (Applicant Name should not be given here) | M/S FLOW TECH CHEMICALS PVT. LTD. | Address | PACL Campus, Industrial Area, Naya Nangal, District- Ropar, Punjab |
|