1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Establishing 1x800 MW Coal Based Supercritical Thermal Power Plant and Decommissioning of 2x120 MW Units at Ukai Thermal Power Plant at Vill. Vagda, Tehsil –Fort Songadh, Dist-Tapi, Gujarat | (b)Name of the Company / Organisation | Gujarat State Electricity Corporation Limited (GSECL) | (c)Registered Address | Race Course,Vadodara,Vadodara,Gujarat-390007 | (d)Legal Status of the Company | State Government | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Chief Engineer Project and Planning | (b)Designation (Owner/ Partner/ CEO) | Chief Engineer | (c)Address | GUJARAT STATE ELECTRICITY CORPORATION LIMITED
Vidyut Bhawan, Race, Course, Vadodara,Vadodara,,Vadodara,Gujarat-390007 | (d)Pin code | 390007 | (e)E-mail | gsecltp@gmail.com | (f)STD Code. | 265(f)Telephone No. | 6612154 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(d) Thermal Power Plants
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/GJ/THE/144074/2018 | (d)Master Proposal Number(Single Window) | SW/144069/2020 | (e)EAC concerned (for category A Projects only) | Thermal Projects | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Within the premises of Ukai Thermal Power Plant of | (b)Pincode | 394680 | (c)Bounded Latitudes (North) | | From | | Degree | 21.12.21.68 | Minutes | | Second | | From | | Degree | 21.12.49.525 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 73.33.26.186 | Minutes | | Second | | From | | Degree | 73.33.50.616 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 46G7/8/11/12 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 83 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.05 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | J-13012/4/2018-IA.I(T) | (b)Date of Apply of TOR | 12 Feb 2018 | (c)Date of Issue of TOR / Standard ToR | 04 Sep 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 19 Jun 2019 | Distance of Public Hearing Venue from the Proposed Project : | 2 |
| Urja Nagar Colony Ukai | State : | Gujarat | District : | Tapi | Tehsil : | Songadh | Village : | Ukai |
| 200 | Related to CSR employment
fly ash generation health
checkup camps. | District Magistrate | | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Coal based supercritical thermal Power Station | 800 MW (Proposed) | 2x200 MW, 210MW,500 MW existing units | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Unit -6 500 MW (Existing) | 1 | Mega Watt(MW) | | Others | transmision line | (2.) | Unit -7 800 MW (Proposed) | 1 | Mega Watt(MW) | | Others | Trasmission line | (3.) | unit 3 & 4 2x 200 MW (existing) | 2 | Mega Watt(MW) | | Others | transmission line | (4.) | Unit -5 210 MW (Existing) | 1 | Mega Watt(MW) | | Others | transmission line | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 5113 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 8.466 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 12.78 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 47.4 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | d)Inter-State boundaries and international boundaries | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 3340000 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 3340000 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Coal | 3340000 | Tons per Annum | | Gare Palma Sector-I coal block | Rail | | 1200 | Captive | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 11 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 88 | 50 | 85.70 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 28 | 15 | 27.08 | 80 | (3.) | Others | CO | Mili Gram per Meter Cube | 0.97 | 0.56 | 0.96 | 2 (8 hr) | (4.) | SO2 | | Micro Gram per Meter Cube | 18 | 6 | 18 | 80 | (5.) | PM2.5 | | Micro Gram per Meter Cube | 50 | 26 | 50 | 60 | |
14.2. No. of Ground Water monitoring locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.94 | 7.36 | 7.5 | 8.5 | (2.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | TDS | | | mg/l | | 324 | 240 | 500 | 2000 | (4.) | Heavy Metals | | Pb | mg/l | | 0.01 | 0.01 | 0.01 | 0.0 | (5.) | Fluoride | | | mg/l | | 0.88 | 0.56 | 1.0 | 1.5 | (6.) | Total Hardness | | | mg/l | | 170 | 142 | 200 | 600 | (7.) | Chlorides | | | mg/l | | 68 | 29 | 250 | 1000 | |
14.3. No. of Surface Water monitoring locations : 9 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 6.8 | 5.8 | C | (2.) | COD | | mg/l | | 66 | 18 | C | (3.) | BOD | | mg/l | | 26 | 6 | C | (4.) | pH | | NA | | 8.22 | 7.25 | C | |
14.4. No. of Ambient Noise monitoring locations : 11 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 60.2 | 42.4 | 55,75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 52.2 | 36.2 | 45,70 | |
14.5. No. of Soil Sample Monitored locations : 6 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 8.14 | 7.52 | (2.) | P(Phosphorus) | Others | mg/100gm | 0.94 | 0.58 | (3.) | Electric Conductivity | Others | micro mhos/cm | 456.2 | 326.2 | (4.) | N(Nitrogen) | Others | mg/100 gm | 16.4 | 12.6 | (5.) | K(Potassium) | Others | mg/100gm | 1.2 | 0.6 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 5 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 5 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 45600 | 0.5 | Copy of Permission Letter | Canal | | Others | open channel | WTR/2007/475/5/P | 23 Aug 2007 | 1531200 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | FGD system | 600 | 300 | ETP | Reuse within the Plant & Recycling | | 600 | | (2.) | Domestic | 48 | 0 | STP/ septic tank | Green Belt Renewal Plant | | 48 | | (3.) | service water | 96 | 300 | ETP | Reuse within the Plant & Recycling | | 96 | | (4.) | Boiler blow down & other DM water | 240 | 300 | ETP | Reuse within the Plant & Recycling | | 240 | | (5.) | CW system blow down | 8640 | 300 | ETP | Reuse within the Plant & Recycling | | 8640 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 9624 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 9624 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Ash | Bottom Ash | | 227120 | Tons | 0.4 | Others | High Conc. slurry | Others | Existing ash dyke, other users | (2.) | Ash | Fly Ash | | 908480 | Tons | 12 | Road | | Others | abundoned mines, others users | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | SO2 | | Microgram per Meter Cube | 18 | 5.0 | 1.19 | 19.20 | 80 | (2.) | NOx | | Microgram per Meter Cube | 28 | 7.0 | 1.19 | 29.20 | 80 | (3.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 0.1 | 0 | (4.) | PM10 | | Microgram per Meter Cube | 88 | 2.0 | 0.35 | 88.36 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Chimney | Coal | 150 | 7.2 | SO2 | | 91.8 | (2.) | Chimney | Coal | 150 | 7.2 | NOx | | 91.8 | (3.) | chimney | Coal | 150 | 7.2 | Others | PM | 27.2 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 400 | (b)Source | Ukai TPS switch-yard | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 0 | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 36 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 36 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 13730 | (b)Waste/Barren Land (ha.) | 4406 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 6192 | (e)Settlements (ha.) | 3429 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 8489 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : NIL | 0 | Total (ha.) | 36246 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 20.23 | Main Plant 12.14, Coal handling 8.094 | (2.) | Township | | 0 | area does not invloved plant area | (3.) | Ash Pond | | 0 | Nil (existing to be used) | (4.) | Quarry Area | | 0 | NA | (5.) | OB Dump Area | | 0 | NA | (6.) | Safety Zone | | 0 | NA | (7.) | Tailing Pond | | 0 | NA | (8.) | LandFill | | 0 | NA | (9.) | Water Reservoir | | 0 | NA | (10.) | Desalination Plant | | 0 | NA | (11.) | Area for Solid Waste Management | | 1.62 | Ash handling Plant | (12.) | Built Up Area | | 6.07 | | (13.) | Others | Balance of Plant + FGD | 8.09 | Balance of plant 6.07, FGD- 2.02 | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | NA | 00 | not present with 10 km study area | (2.) | ESAs | NA | 00 | not present with 10 km study area | (3.) | ESZs | NA | 00 | not present with 10 km study area | (4.) | Corridors | NA | 00 | not present with 10 km study area | (5.) | Wildlife Corridors | NA | 00 | not present with 10 km study area | (6.) | Critically Polluted Area | NA | 00 | not present with 10 km study area | (7.) | NPA | NA | 00 | not present with 10 km study area | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NA | 00 | not present within 10 km study area | (2.) | Forest | | NA | 00 | not present within 10 km study area | (3.) | Defence Installations | | NA | 00 | not present within 10 km study area | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Ukai Left Bank Main Canal | (ii)Direction of Water Bodies in Buffer Area | North | (iii)Distance of Water Bodies in Buffer Area | 0.2 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 200 | (b)Permanent Employment-During Operation | 200 | (c)Temporary Employment- During Construction | 600 | (d)Temporary Employment- During Operation | 100 | (e)No. of working days | 365 | (f)Total Manpower | 1100 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 3.50 | (b)Percentage of Total Project Area | 9.72 | (c)No. of Plants to be Planted | 7000 | (d)Funds Allocated for Plantation | 10000000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Increase in green belt area. | (2.) | Social | Direct employment to eligible persons preferable local persons besides creating indirect employment opportunities. Various CSR, CER activities in adjoining villages will help in improving social status. | (3.) | Financial | The project will contribute to the Government through various taxes. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Thermal Projects |
|
1. | Specifications of Plant: | (b) Technology Proposed | Supercritical | (b) Plant Load Factor(%) | 85 | (c) Station Heat Rate (Kcal/Kwh) | 2150 | (d) Steam Rate/Flow Rate | 2277.4 | (e) Boiler Temperature | 602 | (f) Boiler Pressure | 274 | (g) Type of Stack | Single flue | (h) No. of Stacks | 1 | |
|
S. No. | Stack ID | Stack Height (m) | Stack Diameter at exit (m) | Exit Velocity of Stack Gas (m/s) | Exit Temperature of Stack Gas (Degree Celsius) |
---|
(1.) | 7 | 150 | 7.2 | 25.6 | 65 | |
|
2. Details of Fuel Linkage |
---|
S. No. | Type of Fuel | Type of Linkage | Other Type of Linkage | Details | Characteristics |
---|
(1.) | Coal | Captive | | Source of Linkage : | Gare Palma Sector-I coal block | Quantity of Linkage Granted : | 3340000 | Date of Linkage : | 10 Feb 2020 | Duration of Linkage : | 34 |
| Gross Calorific Value (Kcal/Kg) : | 4706 | Ash Content (%) : | 31.97 | Sulphur Content (%) : | 0.54 | Moisture (%) : | 5.38 | Mercury (mg/kg) : | 0.12 | Fixed Carbon (%) : | 35.66 | Volatile Matter (%) : | 26.99 |
| |
|
3. Details of Transportation of Fuel |
---|
S. No. | Fuel | Rail | Road | Pipe Conveyor | Conveyor Belt | Arial Ropeway | Other Mode of Transportation | Total Distance | Total Quantity |
---|
(1.) | Coal | Distance : | 1200 | Quantity : | 3340000 |
| | | | | | 1200 | 3340000 | |
TOTAL | Distance : 1200 Quantity : 3340000 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | |
|
4. | Details of Cooling System: | (a) Type of Cooling System | Water Cooled | (b) Type of Draft | Natural Draft | (c) Type of Air Circulation | Counter Flow | (d) Cycle of Cooling (COC) | 5 | (e) Water Req. For Cooling (m3/day) | 43728 | (f) Boiler Blow Down Temperature | 0 | |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/SA083 (Rev.01) | (ii)Name of the EIA Consultant | Mantec Consultants Pvt. Ltd | (iii)Address | D-36, sector 6 Noida | (iv)Mobile No. | 9911994264 | (v)Landline No. | 0120421580 | (vi)Email Id | envmantec@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Thermal Projects | (ix)Validity of Accreditation | 18 Apr 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Dear Sir,
This has reference to the above-mentioned subject and cited references, the project was consider & appraised in 39th EAC meeting (Thermal) held on 10.04.2020 through video conferencing. Subsequently, MOEF&CC vide letter dated 01.05.2020 Sought additional details/information for further consideration of the project. The point wise response to the Additional details sought is attached herewith.
We hope you would find the same in order for your kind perusal as necessary action.
Thanking You. | 10 Jul 2020 | 2. | NA | Committee after deliberations, deferred the proposal for furnishing the information as per the observations
| 01 May 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Chief Engineer Project and Planning | Designation | Chief Engineer | Name of Company (Applicant Name should not be given here) | Gujarat State Electricity Corporation Limited (GSECL) | Address | Race Course |
|