Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Aaradhya Industries
(b)Name of the Company / Organisation AARADHYA INDUSTRIES
(c)Registered Address Survey no. 50 paiki 2, Village: Dhroliya, Taluka: Tankara, District: Morbi, Gujarat.,,Morbi,Gujarat-363650
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ashvin Gadara
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Survey no. 50 paiki 2, Village Dhroliya, Taluka Tankara, District Morbi, Gujarat.,,Tankara,Morbi,Gujarat-363650
(d)Pin code 363650
(e)E-mail aaradhyaindustries2018@gmail.com
(f)STD Code. 79(f)Telephone No. 27450694
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/84040/2018
(d)Master Proposal Number(Single Window) SW/142989/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey no. 50 paiki 2
(b)Pincode 363650
(c)Bounded Latitudes (North)
From
Degree 22.53138889
Minutes
Second
From
Degree 22.53277778
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 70.720000000
Minutes
Second
From
Degree 70.72055556
Minutes
Second
(e)Survey of India Topo Sheet No. F42K10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 95
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4.1
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratMorbiTankara
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/364/2018-IA-II(I)
(b)Date of Apply of TOR 16 Nov 2018
(c)Date of Issue of TOR / Standard ToR 24 Dec 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :10 Dec 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :18 Jan 2020
Distance of Public Hearing Venue from the Proposed Project :0
Survey no. 50 paiki 2, Village: Dhroliya, Taluka: Tankara, District: Morbi, Gujarat.
State :Gujarat
District :Morbi
Tehsil :Tankara
Village :Dhroliya
119Welcome and presence of air pollution & water pollution or not.District Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)M. F. /U. F. Reaction vessel5 T2 Nos
(2.)Centrifuge/Nutch Filter5 KL2 nos.
(3.)Dumping Tank15 KL4 nos.
(4.)D. G. Set10 HP--
(5.)Cooling Tower65 TR-
(6.)EBASA Reactor(MS/SS)6 KL4 nos
(7.)Chilling Plant20 MT-
(8.)Boiler400 kg/hr.-
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Ethyl Benzyl Aniline Sulphonic Acid100Tons per AnnumRoad
(2.)Para Nitro Toluene Ortho Sulphonic Acid100Tons per AnnumRoad
(3.)Melamine Formaldehyde Resin100Tons per AnnumRoad
(4.)Urea Formaldehyde Resin100Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 2.5
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.05
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.041
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 6780
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 6780
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Formaldehyde 37%1428Tons per Annumlocal Traders/suppliersRoad250 Open MarketCopy of Linkage
(2.)Para Nitro Toluene780Tons per Annumlocal Traders/suppliersRoad250 Open MarketCopy of Linkage
(3.)Oleum 23%1620Tons per Annumlocal Traders/suppliersRoad250 Open MarketCopy of Linkage
(4.)Ethyl Benzyl Aniline720Tons per Annumlocal draders/suppliersRoad250 Open MarketCopy of Linkage
(5.)Oleum 65%660Tons per Annumlocal draders/suppliersRoad250 Open MarketCopy of Linkage
(6.)Acetic acid6Tons per Annumlocal Traders/suppliersRoad250 Open MarketCopy of Linkage
(7.)Urea474Tons per Annumlocal Traders/suppliersRoad250 Open MarketCopy of Linkage
(8.)Sulfuric Acid (98%)600Tons per Annumlocal draders/suppliersRoad250 Open MarketCopy of Linkage
(9.)Melamine480Tons per Annumlocal Traders/suppliersRoad250 Open MarketCopy of Linkage
(10.)Caustic12Tons per Annumlocal Traders/suppliersRoad250 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 05 Oct 2018 To 27 Dec 2019
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube80.2071.7376.03100
(2.)PM2.5Micro Gram per Meter Cube42.6135.0739.3160
(3.)NOxMicro Gram per Meter Cube28.2520.4324.1580
(4.)OthersCOMicro Gram per Meter Cube0002
(5.)SO2Micro Gram per Meter Cube18.1710.4214.3980
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)OthersCODmg/l45000
(2.)OthersPhenolmg/l0.03000
(3.)pHNA8.227.336.58.5
(4.)OthersPhosphorus (as P)mg/l0000
(5.)TSSmg/l104200
(6.)OthersTempratureOthers°C2624.800
(7.)OthersMagnesium (as Mg)mg/l65.64.930100
(8.)OthersCarbonatemg/l0000
(9.)OthersNitrite as NO2mg/l1.3000
(10.)OthersTurbidityOthersNTU2.40.915
(11.)OthersPotassium as Kmg/l89000
(12.)Fluoridemg/l0011.5
(13.)OthersTotal Solidsmg/l207215000
(14.)TDSmg/l19681405002000
(15.)Total Hardnessmg/l59060200600
(16.)Chloridesmg/l487412501000
(17.)Heavy MetalsIronmg/l000.30.3
(18.)OtherscolourOthersHazen00515
(19.)OthersECOthersµs289420600
(20.)OthersSulphate (as SO4)mg/l152.46.8200400
(21.)OthersCalcium Hardnessmg/l3204000
(22.)OthersTurbidityOthersNTU2.40.915
(23.)OthersDOmg/l5.5400
(24.)OthersMagnesium Hardnessmg/l2702000
(25.)OthersCalcium (as Ca)mg/l128.31675200
(26.)OthersBicarbonatesmg/l4954500
(27.)OthersBoron (as B)mg/l000.51
(28.)OthersNitrate  (as NO3)mg/l2.660.274545
(29.)OthersPhosphate (PO4)-3mg/l0000
(30.)Othersbodmg/l20.8000
(31.)OthersFecal ColiformsOthersMPN/100ml0000
(32.)OthersTotal ColiformOthersMPN/100ml1102600
(33.)OthersAmmonical Nitrogenmg/l7.50.2800
(34.)OthersSodium as Namg/l1651400
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.747.12E
(2.)DOmg/l5.63.8E
(3.)BODmg/l247.40E
(4.)CODmg/l7820E
(5.)OthersTempratureOthers°C25.924.5E
(6.)OthersTotal Dissolved Solids (TDS)mg/l1472116E
(7.)OthersTotal Suspended Solids (TSS)mg/l8012E
(8.)OthersAmmonical Nitrogenmg/l8.60E
(9.)OthersCalcium Hardnessmg/l22020E
(10.)OthersCalcium (as Ca)mg/l88.28E
(11.)OthersMagnesium (as Mg)mg/l46.23.6E
(12.)OthersBoron (as B)mg/l00E
(13.)OthersNitrate  (as NO3)mg/l00E
(14.)OthersIron (as Fe)mg/l00E
(15.)OthersPhosphate as (PO4)-3mg/l3.780E
(16.)OthersSulphate as (SO4 )-2mg/l101.112.2E
(17.)OthersPhenolmg/l0.070E
(18.)OthersTotal ColiformOthersMPN/ 100ml160090E
(19.)OthersTotal Hardness (as CaCO3)mg/l41035E
(20.)OthersFecal ColiformsOthersMPN/100ml00E
(21.)OthersECmg/l2165171E
(22.)OthersBicarbonatesmg/l34218E
(23.)OthersColourOthersHazen00E
(24.)OthersTurbidityOthersNTU2.90.4E
(25.)OthersTotal Solids (TS)mg/l1552128E
(26.)OthersChlorides (as Cl)mg/l30925E
(27.)OthersMagnesium Hardnessmg/l19015E
(28.)OthersCarbonatesmg/l780E
(29.)OthersFluoride (as F)mg/l0.210E
(30.)OthersPhosphorus (as P)mg/l1.50E
(31.)OthersSodium as Namg/l12811E
(32.)OthersNitrite as NO2mg/l1.40E
(33.)OthersPotassium as Kmg/l612E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))60.449.275
(2.)Leq(Night)A-weighted decibels(dB(A))53.138.570
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH9.277.55
(2.)N(Nitrogen)Percent12.610
(3.)K(Potassium)Othersmg/g7.731.28
(4.)P(Phosphorus)Milligram per Kilogram3.51.05
(5.)Electric ConductivityMillisiemens per Centimetre607248
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 13.65 To 2.36
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 12.38 To 3.51
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater4.40Copy of Permission LettermodeOthersNO TRANSPORTATIONTube Well21- 4/5132/GJ/IND/201930 May 20194.4
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)INDUSTRIAL1.851.85ETP followed by evaporatorOthersZLD0.90.95
(2.)Domestic2.22.2Soak pitOthersSOAK PIT02.2
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 4.05
(b)Total Discharged Water (Kilolitre per Day) 3.15
(c)Total Reused Water (Kilolitre per Day) 0.9
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)USED OILIndustrial Waste0.08Tons100RoadAuthorized Recyclers
(2.)DISCARDED PLASTIC BAGS/ BARRELIndustrial Waste71.36Tons100RoadAuthorized Recyclers
(3.)ETP SLUDGE + EVAPORATION RESIDUEIndustrial Waste6Tons70RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)SPENT SULPHURIC ACID (70%)Industrial Waste1725Tons100RoadOthersRULE 9-authorized vendor
(5.)BLEED LIQUORIndustrial Waste240Tons0RoadOthersETP
(6.)SPENT SULPHURIC ACID (30%)Industrial Waste2280Tons100RoadOthersRULE 9 authorized vendor
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube84.9900.0485.04100
(2.)NOxMicrogram per Meter Cube36.783.630.4537.2480
(3.)SO2Microgram per Meter Cube231.280.0323.0480
(4.)PM2.5Microgram per Meter Cube52.9800.0453.0260
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)BOILERBIO COAL/COAL110.6NOx0.56
(2.)BOILERBIO COAL/COAL110.6PM102.69
(3.)BOILERBIO COAL/COAL110.6SO20.08
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 74600
(b)Source PGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1 DG SET-7460
(e)Stack Height (in m) 6
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 1.0117
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1.0117
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 25321
(b)Waste/Barren Land (ha.) 408
(c)Grazing/ Community Land (ha.) 3801
(d)Surface Water Bodies (ha.) 1290
(e)Settlements (ha.) 548
(f)Industrial (ha.) 7
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : WATER LOGGED 40
    Total (ha.) 31415
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt0.4656
(2.)Built Up Area0.2974
(3.)OthersOpen/ Road area0.2487
Total (ha.) 1.0117
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0-
(2.)ESAsNA0-
(3.)NPANA0-
(4.)ESZsNA0-
(5.)Wildlife CorridorsNA0-
(6.)Critically Polluted AreaNA0-
(7.)CorridorsNA0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0-
(2.)Archaeological SitesNA0-
(3.)Defence InstallationsNA0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.01
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0.0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl (Peacock)
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made Incorporated in EMP cost
(iii)Period of Implementation 5 year
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 1. Dhroliya pond-1.28km NW 2. Mitana Dam on Dami river-3.63km NE 3. Neknam pond-3.11 km SW
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area 1. Jainagar Pond
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 7.65
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 25
(e)No. of working days 360
(f)Total Manpower 75
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.47
(b)Percentage of Total Project Area 46.46
(c)No. of Plants to be Planted 450
(d)Funds Allocated for Plantation 100000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Social1. Upliftment of social and economic status of people living in nearby villages. 2.Employment generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA 0142(Rev.01)
(ii)Name of the EIA Consultant T. R. ASSOCIATES
(iii)Address T. R. Associates, A-401, S.G.Business Hub, Between Bhagwat Vidhyapith & Gota Over Bridge, Near Umiya Campus, S.G.Highway, Ahmedabad - 380060.
(iv)Mobile No. 9825371099
(v)Landline No. 0792745069
(vi)Email Id adm.trassociates@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 09 Oct 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe have already did application to CWLW and proof of doing so is attached here with all required documents. 27 Jun 2020
2.NAOn examination it is noted that there is Schedule I species Indian Peafowl (Peacock) reported for which PP has made conservation plan and uploaded on Parivesh Portal, however updated status of approval of conservation plan from State Govt. (CWLW)/ submission proof to CWLW needs to be submitted for further necessary action. 05 May 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAshvin Gadara
DesignationPartner
Name of Company (Applicant Name should not be given here)AARADHYA INDUSTRIES
AddressSurvey no. 50 paiki 2, Village: Dhroliya, Taluka: Tankara, District: Morbi, Gujarat.