Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion in Existing Unit
(b)Name of the Company / Organisation SHIMMER CHEMICALS PVT LTD
(c)Registered Address Survey No. 313, Padra - Borsad state highway, village - Mujpur, Tal - Padra, Dist. Vadodara, Gujarat,,Vadodara,Gujarat-391440
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ramanbhai Patel
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address E-14, Sardar Estate, Ajwa road, Vadodara 390019, Gujarat,,Vadodara,Vadodara,Gujarat-390019
(d)Pin code 390019
(e)E-mail info@shimmerchem.com
(f)STD Code. 265(f)Telephone No. 2561026
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Category A
(c)Proposal Number IA/GJ/IND2/140871/2007
(d)Master Proposal Number(Single Window) SW/140850/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey No. 313, Padra - Borsad state highway, Vill
(b)Pincode 391440
(c)Bounded Latitudes (North)
From
Degree 22.150709
Minutes
Second
From
Degree 22.151039
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 73.000749
Minutes
Second
From
Degree 73.001177
Minutes
Second
(e)Survey of India Topo Sheet No. F43G15, F43G16, F4H3, F4H4
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 30.60
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 13
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratkutchLakhpatMudhvay, Maldo, Koriyani, Kapurashi
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/763/2008-IAII(I)
(c)Date of Issue of TOR 19 Feb 2008
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 12 Mar 2020
(c)Date of Issue of EC 25 Jan 2021
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :29 Nov 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :31 Dec 2019
Distance of Public Hearing Venue from the Proposed Project :0
Survey No. 313, Padra - Borsad state highway, Village-Mujpur, Taluka - Padra, Vadodara
State :Gujarat
District :Vadodara
Tehsil :Padra
Village :Mujpur
126Issues raised were implementation of Padra Policy, Employment to local people, installation of Rainwater Harvesting System, CSR Activity, Air Emission and effective control measures, etc.OthersResident Addl. Collector and Additional District Magistrate, Vadodara
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. 5-111/2009(ENV)/020
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 5 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Benzyl Alcohol72228300Tons per Annum(TPA)Road
(2.)Ortho Chloro Benzyl Chloride48028203300Tons per Annum(TPA)Road
(3.)Benzyl Chloride18031203300Tons per Annum(TPA)Road
(4.)Para Chloro Benzyl Chloride033003300Tons per Annum(TPA)Road
(5.)2-Methyl Benzyl Chloride033003300Tons per Annum(TPA)Road
(6.)N-Butyl Chloride44434563900Tons per Annum(TPA)Road
(7.)Dichloro Ortho Xylene033003300Tons per Annum(TPA)Road
(8.)2,4 Dichloro Benzyl Chloride033003300Tons per Annum(TPA)Road
(9.)Meta Chloro Benzyl Chloride033003300Tons per Annum(TPA)Road
(10.)Ortho Chloro Benzaldehyde4835523600Tons per Annum(TPA)Road
(11.)Para Chloro Benzaldehyde036003600Tons per Annum(TPA)Road
(12.)Benzaldehyde105625443600Tons per Annum(TPA)Road
(13.)2,4 Dichloro Benzaldehyde036003600Tons per Annum(TPA)Road
(14.)N-Hexyl Chloride039003900Tons per Annum(TPA)Road
(15.)1,6 Dichloro Hexane44434563900Tons per Annum(TPA)Road
(16.)Benzylidine Acetone240360600Tons per Annum(TPA)Road
(17.)N-Chloro Pentane44434563900Tons per Annum(TPA)Road
(18.)Ortho or Para Chloro Benzyl Alcohol0300300Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Separation Units1 KL/day x 10 Nos.1 KL/day x 15 Nos.1 KL/day x 25 Nos.
(2.)S.S. Vessel3.5 KL x 2 Nos.3.5 KL x 3 Nos.3.5 KL x 5 Nos.
(3.)BDA Rectors2 KL/day x 2 Nos.---2 KL/day x 2 Nos.
(4.)BDA Distillation0.8 KL x 2 Nos.0.8 KL x 2 Nos.0.8 KL x 4 Nos.
(5.)BHY Distillation1.5 KL/day x 3 Nos.1.5 KL/day x 2 Nos.1.5 KL/day x 5 Nos.
(6.)Sepration Bcl21 KL/day x 8 Nos.1 KL/day x 12 Nos.1 KL/day x 20 Nos.
(7.)Ref. Unit/ (gas) F2220 TR x 1 No.40 TR x 1 No.20 TR x 1 No., 40 TR x 1 No.
(8.)Vacuum System2 Nos.2 Nos.4 Nos.
(9.)N. Chloro Butane1.6 KL x 4 Nos.1.6 KL x 4 Nos.1.6 KL x 8 Nos.
(10.)P.C.B, O.C.B Distillation1 KL/day x 2 Nos.1 KL/day x 6 Nos.1 KL/day x 8 Nos.
(11.)Distillation Units1 KL/day x 8 Nos.1 KL/day x 15 Nos.1 KL/day x 23 Nos.
(12.)HCl Scrubber20 KL x 16 Nos.20 KL x 16 Nos.20 KL x 32 Nos.
(13.)Glass Line Reactors (BHY)1.6 KL x 4 Nos.1.6 KL x 4 Nos.1.6 KL x 8 Nos.
(14.)Boiler2 MT x 2 Nos.3 MT x 1 No.2 MT x 2 Nos., 3 MT x 1 No.
(15.)N. Chloro Pantane1.6 KL x 5 Nos.1.6 KL x 4 Nos.1.6 KL x 9 Nos.
(16.)Cooling Tower100 TR x 2 Nos. + 40 TR x 3 Nos.100 TR x 5 Nos.100 TR x 7 Nos. + 40 TR x 3 Nos.
(17.)R.O Plant1 KL/hr. x 1 No.1 KL/hr. x 1 No.1 KL/hr. x 2 Nos.
(18.)Caustic Scrubber1 KL/day x 2 Nos.1 KL/day x 3 Nos.1 KL/day x 5 Nos.
(19.)Reactors O.C Bcl + O Bcl + Bcl21 KL/day x 7 Nos.1 KL/day x 10 Nos.1 KL/day x 17 Nos.
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 14 May 2018
(iv)Valid Upto 31 Mar 2023
(v)File No. AWH-94789
(vi)Application No. 137302
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 7.3
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.42
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.18
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.084
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 74422.78
(b)Existing quantity of raw material/fuel 4793.72
(c)Total quantity of raw material/fuel 79216.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)refer attachment79216.5Tons per AnnumOpen MarketRoad80 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2018 To 28 Feb 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube47.37.234.1880
(2.)PM10Micro Gram per Meter Cube117.346.8102.6100
(3.)SO2Micro Gram per Meter Cube38.65.328.780
(4.)OthersCOMili Gram per Meter Cube1.30.41.1702
(5.)PM2.5Micro Gram per Meter Cube66.715.156.1960
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Fluoridemg/l0.680.3611.5
(2.)Chloridesmg/l9641342501000
(3.)OthersSulphatemg/l16448200400
(4.)pHNA8.536.776.58.5
(5.)TDSmg/l369112245002000
(6.)Total Hardnessmg/l1405403200600
(7.)TSSmg/l14800
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l7.24.9C
(2.)BODmg/l2006D
(3.)pHNA8.937.69D
(4.)CODmg/l8221C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))655255
(2.)Leq(Night)A-weighted decibels(dB(A))524445
    14.5.     No. of Soil Sample Monitored locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.697.64
(2.)K(Potassium)Milliequivalents per 100 Gram0.390.28
(3.)Electric ConductivityMillisiemens per Centimetre0.330.1
(4.)N(Nitrogen)Milligram per Kilogram144126
(5.)P(Phosphorus)Milligram per Kilogram2610
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 35 To 55
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 25 To 50
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater62.70Copy of Permission LetterPipelineOthersBorewell21-4/5699/GJ/IND/202006 Feb 202062.7
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic1010STPGreen Belt Renewal Plant10
(2.)Industrial6.46.4Recycling & ReuseReuse within the Plant & Recycling6.4
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 16.4
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 16.4
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Process WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)144Tons00RoadOthersDistillation and recovered martial is used as RM
(2.)Calcium Chloride SolutionIndustrial Waste647.76Tons50RoadOthersSold to actual users under Rule-9
(3.)Sodium Hypochlorite (10% Sol.)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)5562Tons50RoadOthersSold to actual users under Rule-9
(4.)Fly AshIndustrial Waste120Tons45RoadOthersSale to brick manufacturers
(5.)Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)74Tons30RoadOthersSent for Incineration at M/s. NECL, Nandesari
(6.)Used or Spent OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1Kilolitre0RoadOthersSelling to registered re-refiner / reuse.
(7.)Sodium Benzoate (10% Sol.)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons50RoadOthersSold to actual users under Rule-9
(8.)Spent CatalystHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1Tons30RoadOthersSent for Incineration at M/s. NECL, Nandesari
(9.)Discarded Containers/Barrels/LinersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)23Tons30RoadAuthorized Recyclers
(10.)Spent HCl (30% Sol.)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)16560Tons50RoadOthersSold to actual users under Rule-9
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube19.71.010.4820.280
(2.)NOxMicrogram per Meter Cube23.81.180.162480
(3.)PM10Microgram per Meter Cube90.603.570.1890.8100
(4.)PM2.5Microgram per Meter Cube0000.10
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)BoilerBriquette/Agro-waste300.5SO20.60
(2.)BoilerBriquette/Agro-wsate300.5NOx0.25
(3.)Process vent of Benzyl chlorideNone150.23OthersHCl0.0006
(4.)Process vent of BenzaldehydeNone170.23OthersHCl0.0007
(5.)Process vent of BenzaldehydeNone170.23OthersCl20.0002
(6.)BoilerBriquette/Agro-waste300.5PM100.39
(7.)Process vent of Benzyl chlorideNone150.23OthersCl20.0001
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 500
(b)Source Madhya Gujarat Vij Company Limited
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 175 KVA x 1 No. + 75 KVA x 1 No.
(e)Stack Height (in m) 3
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 1.6
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1.6
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 21895
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 436
(e)Settlements (ha.) 983
(f)Industrial (ha.) 304
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 8462
    Total (ha.) 32080
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersOpen and Road Area0.4
(2.)Green belt0.5
(3.)Built Up Area0.7
Total (ha.) 1.6
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsThol Bird Sanctuary115NNW
(2.)ESAsJambughoda Wild Life Sanctuary74ENE
(3.)CorridorsGir National Park257SW
(4.)NPAJambughoda Wild Life Sanctuary74ENE
(5.)Critically Polluted AreaNandesari & PCCI Estate20NNE
(6.)WLSJambughoda Wild Life Sanctuary74ENE
(7.)Wildlife CorridorsGir National Park257SW
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesFresco Rooms in Bhau Tambekar's Wada21ENE
(2.)ForestShoolpaneshwar Wildlife Sanctuary98SE
(3.)Defence InstallationsMakarpura AFS20ESE
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.6
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 150000
(iii)Period of Implementation 5 Years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 1. Narmada Canal 2. Mahi River
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Muval
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 9.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 15
(c)Temporary Employment- During Construction 10
(d)Temporary Employment- During Operation 20
(e)No. of working days 340
(f)Total Manpower 50
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)No. of Plants9362801216
(2.)Total Area of Green Belt53461.495347.49
(3.)Percentage of Total Project Area330.133.1
(4.)Funds Allocated100000600000700000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialDue to proposed expansion activity, Social Infrastructure will improve by means of Civilization, Vocational Training and Basic Amenities. Sports activities and other similar programmes will be carried out in the surrounding area under CSR programme. This will indirectly contribute to significant positive changes in the socioeconomic scenario of the area. Civilization: Due to expansion; employment and other infrastructural facilities will boost up income of surrounding people and improve quality
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay Order against the NABET/QCI
(ii)Name of the EIA Consultant Aryan Greens
(iii)Address 401, Sakar Complex, Above Union Bank, Near Saradar Estate, New VIP Road, Vadodara
(iv)Mobile No. 9712000535
(v)Landline No. 0265251615
(vi)Email Id info@aryangreens.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 29 Mar 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation has not been submitted. Kindly upload the requisite documents. Form 2 (Sno. 7.1) (ii) All old CTOs not uploaded to verify the violation, if any done by PP. (iii) Copy of earlier EC is not uploaded in at S. No. 6 of Form 2. (iv) TOR compliance is not adequate in EIA/EMP report and need to revise as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006. (v) Status of Conservation Plan approval from CWLW. (vi) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Report. The EIA/EMP Report shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submitted the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. 05 Mar 2020
2.NAThe correction have been made as per the instruction received 12 Mar 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterRevised query reply with all complete details are attached. 08 Dec 2020
2.NAThe information submitted by you was examined and as PP informed that still the information is incomplete. Please submit the complete reply so that the same can be placed before the EAC quickly. 07 Dec 2020
3. ADS Reply LetterAs per the query, all other replies were ready but we had applied to MOEF&CC, Bhopal for the closer report of partly complied points received in earlier compliance report. Hence, submission of query reply has taken long time. Considering above reasons, kindly re-list our proposal. Reply is attached. 04 Dec 2020
4.NA

The EAC, after detailed deliberations decided to defer the proposal for want of requisite information as under and have asked the PP to revise the Report along with following clarification/information: -

                                             

(i)           Submit the permission for fresh water withdrawal and submit clarification for operating the existing unit without prior permission for fresh water withdrawal.

 

(ii)         Action Taken Report on non-compliance points in the existing EC conditions which needs to be forwarded by the Regional Office of the Ministry.

 

(iii)        Submit the copy of public hearing report forwarded by the Head office of Gujarat Pollution Control Board as the said report uploaded on the PARIVESH portal is not opening. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation and its time lines needs to be submitted.

 

(iv)        The Committee observed that District Vadodara comes under Critically Polluted area, however PP mentioned that this is away from CPA. In this context, the Committee suggested that PP shall submit the copy of letter either from CPCB or SPCB about the location of project in Critically Polluted area or not as there are different provisions of appraisal of projects which comes under CPA.

 

(v)         Detailed effluent analysis report needs to be submitted.

 

(vi)        Status of TSDF membership needs to be submitted.

26 May 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRamanbhai Patel
DesignationDirector
Name of Company (Applicant Name should not be given here)SHIMMER CHEMICALS PVT LTD
AddressSurvey No. 313, Padra - Borsad state highway, village - Mujpur, Tal - Padra, Dist. Vadodara, Gujarat