Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Amendment in EC of 5.1 Sq. Mile Mining Lease (1321.45 ha) of Bolani Ores Mines, SAIL for change in excavation and despatch pattern of fines from Fines Dumps keeping total production within approved EC
(b)Name of the Company / Organisation Rourkela Steel Plant, Steel Authority of India Limited (SAIL)
(c)Registered Address AREA 11, ROURKELA,Kolkata,Sundargarh,Sikkim-769011
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Joydev Chattopadhyay
(b)Designation (Owner/ Partner/ CEO) Chief General Manager
(c)Address Bolani Ores Mines, Rourkela Steel Plant, SAIL, At/Po- Bolani,,,Keonjhar,Orissa-758037
(d)Pin code 769011
(e)E-mail bolanifc2016@gmail.com
(f)STD Code. 6767(f)Telephone No. 260211
(g)Fax No. 06767260172
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/OR/MIN/139447/2020
(d)Master Proposal Number(Single Window) SW/215496/2021
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Change of Product Mix under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Bolani-149,121,129,17,109 Balagoda-96,38,93,60
(b)Pincode 758037
(c)Bounded Latitudes (North)
From
Degree 22.086572
Minutes
Second
From
Degree 22.129525
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 85.281337
Minutes
Second
From
Degree 85.337181
Minutes
Second
(e)Survey of India Topo Sheet No. F45H8
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 920
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Orissa
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhubaneswar
(iii)Letter No. 101-570/09/EPE
(iv)Status of Compliance Partially Complied
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Nov 19 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)ROM & fines excavation12012OthersMTPARoad,Rail,Conveyor Belt,OthersTotal excavation within 12 MTPA
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Fines excavation from dumps 3MTPA for saleFines Dumps-0.5 MTPA/Benef.-12 MTPA&Pellet-4 MTPA3 MTPA from Fine Dumps for sale/for Pellet9MPTA ROM+3MTPA dump fines till fines liquidationTotal ROM+Fines from Dumps will be within 12MTPA
(2.)Dispatch of excavated fines from Fines DumpsThru SAIL Own siding after conversion to Pellets1MTPA by own Siding & 2MTPA by road/public Siding1MTPA by own Siding & 2MTPA by road/public SidingOnly till complete fines liquidation from dumps
(3.)Mineral reserve in the 5.1 Sq. Mile Lease137.72 MT (with life of mine 12 years)315 MT (with life of mine 26 years)315 MT (with life of mine 26 years)Reserve increased from exploration
(4.)Area for waste dumping till conceptual period38.02 ha64.81 ha to accommodate additional waste64.81 ha to accommodate additional wastelanduse change for OB dump approved in StageII FC
(5.)Crushing & Screening (C&S) PlantsPit Head Crushing Plant at D &Panposh QuarriesFixed/mobile Pithead 300tph Plants at all quarriesFixed/mobile Pithead 300tph Plants at all quarriesMaximizing prod. keeping total prod. within 12MTPA
(6.)Waste generation till conceptual period13.729 Mm356.042 Mm356.042 Mm3Increase in waste generation as per recent exploration
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 28 Mar 2019
(iv)Valid Upto 31 Mar 2020
(v)File No. IND-I-CON-242
(vi)Application No. 2359974
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 24.0283711
(b) Funds Allocated for Environment Management (Capital) (in Crores) 2.5
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.04
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.6
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1.5
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HSD1.5Kilo Litre per DayBarbilRoad11 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 6.08 To 6.84
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.14 To 4.1
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface5001.5Copy of Permission LetterPipelineOthersPumping42423 Feb 201917126
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Equipment and vehicle washing80100Oil Catch PitReuse within the Plant & Recycling80
(2.)Domestic & drinking40100Primary Septic tank and secondary Soak PitOthersSoak pit040
(3.)Wheel washing290350Sedimentation pitReuse within the Plant & Recycling290
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 410
(b)Total Discharged Water (Kilolitre per Day) 40
(c)Total Reused Water (Kilolitre per Day) 370
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Over burden/Inter burdenOthersExcavation waste5400000Tons1RoadOthersDumped in designated areas within lease
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube81.890.057.1289.02100
(2.)SO2Microgram per Meter Cube11.890.050.6112.5180
(3.)PM2.5Microgram per Meter Cube51.990.150.9352.9360
(4.)NOxMicrogram per Meter Cube34.560.058.3442.9480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NoneNone00OthersNo stack0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 50
(b)Source NESCO
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) Nil
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 87.09
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 8.59
    Total Land (ha.) 95.67999
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 2.21
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 1312.86
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Non-forest land 6.38
    Total (ha.) 1321.45
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area322.64
(2.)OB Dump Area64.81
(3.)Tailing Pond0.34
(4.)Green belt51.21Including Safety Zone
(5.)Township15.10
(6.)Main Plant59.28Mineral Separation Plant
(7.)Area for Solid Waste Management7.25Mineral Reject dumps
(8.)Built Up Area50.22Infrastructure & Roads
(9.)OthersMineral storage1.16
Total (ha.) 572.01
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Wildlife CorridorsKaro-Karampada elephant corridor8Towards SW direction
(2.)NPANone0Not applicable
(3.)Critically Polluted AreaNone0Not applicable
(4.)WLSNone0Not applicable
(5.)ESAsNone0Not applicable
(6.)ESZsNone0Not applicable
(7.)CorridorsNone0Not applicable
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNone0Not applicable
(2.)ForestKaro RF0Within ML area
(3.)OthersReserved ForestKarampada RF0Adjacent to western ML Boundary
(4.)Archaeological SitesNone0Not Applicable
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Core Zone- none, Buffer Zone- Palm Civet, Indian Elephant, Sloth Bear, Wolf, Mouse deer
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 1676.41 lakhs
(iii)Period of Implementation 10 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. 4056/1WL(C)SSP-126/2012
(iii)Date of issue 23 Jun 2014
(iv)Recommendation NA
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Sapua Nala, Jhinkaria Nala, Panposh Nala, Balagoda Nala. all flow from NW to SE
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Karo River
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 1
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 309
(f)Total Manpower 0
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt610.38665.231275.6100000000001
(2.)Percentage of Total Project Area465096
(3.)No. of Plants90876010643681973128
(4.)Funds Allocated5000000055000000105000000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmental- Liquidation of Fines Dump over Diverted Forest Land will completely eliminate environmental hazards. The land can be eco-restored.
(2.)SocialGenerate employment mostly locals.
(3.)Financial- Meet the rising demand of Iron ore in the country during the scarcity period. Low-grade Iron ore which cannot be used by SAIL will become available for others’ use.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)Iron oreMajor
2.
Mine Capacity in ROM (Run of Mine) 12 MTPA
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. RMP/A/19-ORI/BHU/2019-20
(b)Date of Approval 13 Nov 2019
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 1321.45
(f)Approved Capacity 12000000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 384.67
(b)Mineable Reserves (Million Ton) 315.12
(c)Extractable Reserves(Million Ton) 313.52
(d)Percent(%) of Extraction 99.5
(e)Grade of Coal /Ore /Mineral Avg. 62% Fe content
(f)Stripping Ratio 1 : 0.18
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 26
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area Yes
(c)No. of crushers 5
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)1300 D area (temporary)
(2.)2300 F area (temporary)
(3.)3300 G area (temporary)
(4.)4300 Panposh (temporary)
(5.)5300 B & C area (temporary)
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 1321.45
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 29 May 2014
(iii)Validity of LOI 0.25
(iv)Reference No. of LOI 4000/SM III(A)SM-1/97-10731/SM
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 1321.45
(iii)Validity of the lease deed From : 10 Apr 2010 To : 09 Apr 2030
(iv)Date of Execution of Mining Lese 14 Nov 2014
(v)Reference Number e-regn. no. 11031400379
(d)Whether Lease Deed Renewed ? Yes
     8.1.    Earlier Renewals:
S. No.Lease Details Date of Renewal Period Copy of Earlier Lease Letter No.Area Remarks
(1.)Renewal 10 Apr 1990 From : 10 Apr 1990 To : 09 Apr 2009 Copy of Earlier Lease993/970 1321.45 Executed on 11/03/2002
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 05
(ii)Total Area (in Hectare) 28.43
(iii)Height (in meter) 45
(iv)Quantity (in Million Cubic meter) 10.66
(v)No. of year back fill up 21
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.06
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.06
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 359.98
(b)Depth (in meter) 120
(c)Volume (in Million Cubic meter) 43
12.
Details of Quarry:
(a)Final Void of 359.98 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 544.19
13.
Details of Transportation:
(a)In Pit/Underground to Surface Dumper trucks
(b)Surface to Siding/Loading Covered conveyors
(c)Transportation / Conveyor Details Saleable ore to be dispatched by railway wagons
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND2.2102.21
(2.)FOREST LAND1312.8601312.86
(3.)OTHERS(Specify)Non-forest land6.3806.38
(4.)WASTE LAND000
(5.)GRAZING LAND000
(6.)SETTLEMENTS000
(7.)SURFACE WATER BODIES000
TOTAL1321.4501321.45
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)BUILT UP AREA (COLONY/OFFICE)0029.1329.13
(2.)GREEN BELT40.920040.92
(3.)INTERNAL OB DUMPS184.2100184.21
(4.)OtherSubgrade storage/tailing pond/processing plants76.210076.21
(5.)EXTERNAL OB DUMPS53.830053.83
(6.)ROADS90918
(7.)VIRGIN AREA559.1700559.17
(8.)TOP SOIL STORAGE0000
(9.)EXCAVATION/QUARRY352.277.710359.98
TOTAL1275.617.7138.1301321.45
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 53.83
(b)Internal Dump(in hectare) 184.21
(c)Quarry(in hectare) 352.27
(d)Safety Zone(in hectare) 12.97
(e)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 113.16
(h)Total afforestation plant (in hectare) 716.44
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20181212125.2366710
(2.)20023.443.443.07362.7996770
(3.)20043.443.443.47363.3147090
(4.)20063.443.445.653.4272780
(5.)20095.655.655.653.4725010
(6.)20073.443.445.653.4394640
(7.)20085.654.645.653.8785840
(8.)20105.655.65123.8181080
(9.)20125.655.65123.5667520
(10.)20115.655.65123.7465410
(11.)2013125.65122.9474020
(12.)2014125.65123.6933170
(13.)20151212124.1036190
(14.)20161212125.2715540
(15.)20191212125.6250530
(16.)20013.443.442.82362.7758740
(17.)20033.443.443.27063.0808940
(18.)20053.443.443.67363.3241880
(19.)20171212125.5848580
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court High Courts
(c)Name of the Sub Court Orissa
(d)Case No. WP(C) No. 24279/2017
(e)Orders/Directions of the court ,if any and its relevance with the proposed project Nil
(f)Case Details Matter pending before High Court of Orissa
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0068
(ii)Name of the EIA Consultant MECON Limited
(iii)Address MECON Limited, Vivekananda Path, Doranda, Ranchi, JH - 834002
(iv)Mobile No. 9470193793
(v)Landline No. 0651248324
(vi)Email Id envenggranchi@meconlimited.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 29 Mar 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan
(b)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(c)Uploaded Cover Letter Copy of Cover Letter
(d)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(e)Uploaded Additional File Copy of Additional File
(f)Uploaded Updated Form1 Copy of Updated Form1
(g)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterThe reply against the ADS in respect of EC amendment of Bolani Ores Mines (5.10 Sq Mile Mining Lease) by MOEFCC DATED 26.03.2020 is enclosed herewith for further consideration. 29 May 2020
2.NA

Deferred

26 Mar 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantJoydev Chattopadhyay
DesignationChief General Manager
Name of Company (Applicant Name should not be given here)Rourkela Steel Plant, Steel Authority of India Limited (SAIL)
AddressAREA 11, ROURKELA