Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Limestone Mine {Mudhvay Sub-Block D, Area- 107.00 ha} with Limestone Production Capacity of 1.6 Million TPA, Top Soil 0.32 Million TPA & Overburden -0.515 Million TPA Near Village Mudhvay, Ta
(b)Name of the Company / Organisation JSW CEMENT LTD
(c)Registered Address JSW Cement Ltd., JSW Centre, Bandra Kurla Complex Bandra (East), MUMBAI,,Mumbai City,Maharashtra-400051
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Manoj Kumar Rustagi Kumar Rustagi
(b)Designation (Owner/ Partner/ CEO) Executive Vice President
(c)Address JSW Cement Limited JSW Centre MM RDA Ground, Bandra Kurla Complex, Bandra East Mumbai,,,Nagaur,Rajasthan-400051
(d)Pin code 400051
(e)E-mail ceo.cement@jsw.in
(f)STD Code. 22(f)Telephone No. 42861000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/MIN/85230/2018
(d)Master Proposal Number(Single Window) SW/139302/2020
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. khasra map uploaded with EIA report
(b)Pincode 400051
(c)Bounded Latitudes (North)
From
Degree 234212.1144
Minutes
Second
From
Degree 234257.7472
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 684007.4650
Minutes
Second
From
Degree 684059.0367
Minutes
Second
(e)Survey of India Topo Sheet No. 41A/9,41A/10,41A/13,41A/14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 28.44
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratkutchLakhpat
(2.)GujaratJamnagarJamnagarSikka
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11015/187/2018-IA-II(M)
(b)Date of Apply of TOR 14 Nov 2018
(c)Date of Issue of TOR / Standard ToR 28 Jun 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :30 Sep 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :05 Jul 2019
Distance of Public Hearing Venue from the Proposed Project :2
At Moti Mudhvay, Common plot, Beside primary school, Moti Mudhvay,PO.Koriyani,Taluka:Lakhpat,District : Kutch
State :Gujarat
District :kutch
Tehsil :Lakhpat
Village :Moti Mudhvay
275Issues raised were regarding employment, health & educational facilities, infrastructural facilities,training programmes for employment,fencing, rain water harvesting facilities.OthersAdditional Collector & Additional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Surface Miner(Drum width 2500 mm)1
(2.)Dumpers (Capacity:35 tones)7
(3.)Dozer(D-8L)2
(4.)Shovel(6 CuM)2
(5.)Drill Machine(15m/hr)1
(6.)Mobile service van & garage equipment1
(7.)Explosive Van1
(8.)Ambulance Van1
(9.)Front End Loader(5.76 CuM)2
(10.)Water Tankers/Sprinklers(20000 lit)3
(11.)Diesel Jeeps3
(12.)Diesel Tanker (Truck mounted)1
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)ML Area107HectaresOthers-
(2.)Limestone1600000Tons per AnnumRoadHaul road
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 47.58
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.28
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.3
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3.6
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 3.6
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HSD3.6Kilo Litre per DayOpen marketRoad150 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube52.2422.1649.0560
(2.)SO2Micro Gram per Meter Cube16.436.1816.1880
(3.)NOxMicro Gram per Meter Cube24.128.4123.4580
(4.)PM10Micro Gram per Meter Cube83.1240.9081.72100
    14.2.     No. of Ground Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Heavy MetalsLeadNA000.010
(2.)TDSmg/l4223.65565002000
(3.)pHNA7.617.386.58.5
(4.)TSSmg/l0000
(5.)Total Hardnessmg/l946268.3200600
(6.)Chloridesmg/l2076124.192501000
(7.)Fluoridemg/l1.800.3211.5
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.606.60D
(2.)BODmg/l0.850.85D
(3.)CODmg/l56.1856.18D
(4.)pHNA7.927.92D
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))43.640.2I-70to 75, C-55 to 65, R-45 to 55, S-40 to 50
(2.)Leq(Day)A-weighted decibels(dB(A))54.147.1I-70 to 75, C- 55 to 65, R- 45 to 55, S- 40 to 50
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Kilogram per hectare287.45201.41
(2.)Electric ConductivityOthersµs/cm0.680.51
(3.)N(Nitrogen)Kilogram per hectare156.37115.36
(4.)pH7.817.56
(5.)P(Phosphorus)Kilogram per hectare23.4718.56
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 05 To 13
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 04 To 10
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4/5456/GJ/MIN/2019
(f)Date of Issue 30 Oct 2019
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Sea1006 Not Appliacble PipelineOthersPumpingNIL28 Jan 2020200
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Workshop1315Oil & Grease Separator followed by sedimentation tankOthersUsed for dust suppression130
(2.)Domestic00Oil & Grease Separator followed by sedimentation tank & septic tankOthersOil & Grease Separator septic tank00
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 13
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 13
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)OverburdenOthersMine waste515000Tons0RoadOthersFor making bund,for backfilling
(2.)Top soliOthersMine waste320000Tons0RoadOthersTo make earthen bund for plantation
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube83.1201.3384.46100
(2.)SO2Microgram per Meter Cube16.4301.4617.9080
(3.)NOxMicrogram per Meter Cube24.1201.8525.9880
(4.)PM2.5Microgram per Meter Cube52.2400.4552.7060
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
(2.)0000SO20
(3.)0000NOx0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 100
(b)Source State Electricity Board
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) backup from DG set capacity of 200KVA
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 12.69
(c)Government Land (ha.) 94.31
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 107
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 89.31
(d)Surface Water Bodies (ha.) 5
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Private Land 12.69
    Total (ha.) 107
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area37.353.44ha-Water reservoir & 33.91ha-backfliied
(2.)Green belt9.50
(3.)Built Up Area0.120.02ha-builtup area & 0.10ha-haulage road
(4.)OthersNallah & unexplored area60.0355.03ha-unexplored area & 5ha-Nallah
Total (ha.) 107
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANone0None
(2.)ESAsNone0None
(3.)WLSNarayan Sarovar Wildlife Sanctuary3None
(4.)Critically Polluted AreaNone0None
(5.)ESZsNone0None
(6.)CorridorsNone0None
(7.)Wildlife CorridorsNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestGohatad RF5None
(2.)OthersReserve ForestKaiyari RF2None
(3.)Archaeological SitesNone0None
(4.)Defence InstallationsNone0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 12.69
(c)Status of Land acquisition if not acquired Yet to start
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 1
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 9
(e)Funds Allocated for R&R(in INR) (in Lacs) 457
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Peafowl,Chinkara, Monitored Lizard
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 94 lakhs
(iii)Period of Implementation 10 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. WLP/32/B/8706-07/2019-20
(iii)Date of issue 20 Jan 2020
(iv)Recommendation Approved
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area There are two seasonal Nallah out of which one is entering the areafrom east side and meanders south to southwest and finally towards northwest and get discharged in the nearby area. Second seasonal Nallah meets the big Nallah near boundary pillar D-04.
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kori Creek
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 96
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 96
32.
Green Belt in Ha:
(a)Total Area of Green Belt 43.31
(b)Percentage of Total Project Area 40.48
(c)No. of Plants to be Planted 64965
(d)Funds Allocated for Plantation 14360000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreen belt development / Plantation will be done on 43.41 ha including 3.50 ha along the boundary greenbelt, 33.91 ha on backfilling and 6.00 ha within the Nallah barrier.
(2.)FinancialThe Project will contribute additional revenue to the State and Central Govt. in the form of royalty, cess and other taxes etc.
(3.)SocialProposed project will result in growth of the surrounding areasby increased direct and indirect employment opportunities.Company has allocated Rs. 96 Lakh towards CER activities.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)LimestoneMajor
2.
Mine Capacity in ROM (Run of Mine) 1.6 million tonnes
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 684(4)(1)/MP-165/2018-GNR
(b)Date of Approval 07 Sep 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 107
(f)Approved Capacity 1.6
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 112.725
(b)Mineable Reserves (Million Ton) 32.874
(c)Extractable Reserves(Million Ton) 32.874
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral 44
(f)Stripping Ratio 1 : 0.16
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 23
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 107
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 21 Jun 2017
(iii)Validity of LOI 0.5
(iv)Reference No. of LOI MCR-102016-2146-CHH
(c)Whether Lease Deed Executed ? No
(i)Reason thereof Lease will be executed after grant of EC
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof This is a fresh lease area
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 33.91
(iii)Height (in meter) 69
(iv)Quantity (in Million Cubic meter) 23.40
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 1
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 1
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 3.44
(b)Depth (in meter) 67
(c)Volume (in Million Cubic meter) 2.33
12.
Details of Quarry:
(a)Final Void of 3.44 (hectare) at a Depth of 67 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 37.35
13.
Details of Transportation:
(a)In Pit/Underground to Surface by dumpers/tippers
(b)Surface to Siding/Loading Loading will be done by Hydraulic Excavators/wheel
(c)Transportation / Conveyor Details Transportation of limestone from working face to p
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND12.69012.69
(2.)GRAZING LAND000
(3.)FOREST LAND000
(4.)WASTE LAND000
(5.)SETTLEMENTS000
(6.)SURFACE WATER BODIES505
(7.)OTHERS(Specify)Barren Land(Govt. Land excluding area of nallah)89.31089.31
TOTAL1070107
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY33.913.44037.35
(2.)INTERNAL OB DUMPS0000
(3.)TOP SOIL STORAGE0000
(4.)ROADS000.100.1
(5.)VIRGIN AREA0505
(6.)OtherUnexplored (undisturbed)0055.0355.03
(7.)GREEN BELT9.50009.5
(8.)BUILT UP AREA (COLONY/OFFICE)000.020.02
(9.)EXTERNAL OB DUMPS0000
TOTAL43.418.4455.150107
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 37.35
(d)Safety Zone(in hectare) 3.50
(e)Final Void of 3.44 (hectare) at a Depth of 67 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 60.03
(h)Total afforestation plant (in hectare) 43.41
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/SA 097
(ii)Name of the EIA Consultant J.M. EnviroNet Pvt. Ltd.
(iii)Address 202-A, ABW Tower, MG Road, IFFCO Chowk, Sector 25, Gurugram 122001 (Haryana) INDIA
(iv)Mobile No. 9509267011
(v)Landline No. 0124414192
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 05 May 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPP is requested to submit the following: (i) Approved Schedule-I Species conservation Plan (ii) KML file of the Mine lease area. (iii)NOC for the Ground Water inter section from the Competent Authority. (iv) Authorization given to consultant but power of authority didn't submit by the PP 13 Feb 2020
2.NAThe correction have been made as per the instruction received 29 Feb 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe are herewith submitting the ADS Reply for your kind consideration. 31 Jan 2021
2.NA

Deferred

24 Apr 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantManoj Kumar Rustagi Kumar Rustagi
DesignationExecutive Vice President
Name of Company (Applicant Name should not be given here)JSW CEMENT LTD
AddressJSW Cement Ltd., JSW Centre, Bandra Kurla Complex Bandra (East), MUMBAI
Print