1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Onshore Oil & Gas development drilling and production in Dibrugarh district under Dibrugarh, Chabua, Hugrijan and Tinsukia PMLs | (b)Name of the Company / Organisation | OIL INDIA LIMITED | (c)Registered Address | OIL INDIA LIMITED
DULIAJAN
District : Dibrugarh ,,Dibrugarh,Assam-786602 | (d)Legal Status of the Company | Central PSU | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Ajit Chandra Haloi | (b)Designation (Owner/ Partner/ CEO) | CGM(HSE) | (c)Address | Safety & Environment Department , Oil India Limited,
Duliajan,,,Dibrugarh,Assam-786602 | (d)Pin code | 786602 | (e)E-mail | safety@oilindia.in | (f)STD Code. | 374(f)Telephone No. | 2800542 | (g)Fax No. | 03742801796 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(b) Offshore and onshore oil and gas exploration, development & production
| Minor Activity | 8(a) Building and Construction projects
| (b)Category | A | (c)Proposal Number | IA/AS/IND2/139270/2007 | (d)Master Proposal Number(Single Window) | SW/139223/2020 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Dibrugarh | (b)Pincode | 786001 | (c)Bounded Latitudes (North) | | From | | Degree | 27.300000 | Minutes | | Second | | From | | Degree | 27.533333 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 94.850000 | Minutes | | Second | | From | | Degree | 95.083333 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 83I14, 83I15, 83M2, 83M3 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 130 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 5 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Assam | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/1253/2007 IA II (I) | (c)Date of Issue of TOR | 16 Nov 2017 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 12 Oct 2020 | (c)Date of Issue of EC | 28 Dec 2020 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 05 Sep 2019 | Distance of Public Hearing Venue from the Proposed Project : | 9.5 |
| Tengakhat Public Hall | State : | Assam | District : | Dibrugarh | Tehsil : | Tengakhat | Village : | Tengakhat |
| 59 | Control of pollution, CSR activities in the area, safety of locals from OIL India vehicles, Development projects in the area | Others | Additional Deputy Commissioner | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Shillong | (iii)Letter No. | RO-NE/E/IA/AS/MI/60/1800-1801 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jun 9 2016 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Wells | 4 | 21 | 25 | Others | No of wells | Others | Wells | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Wells | 4 | 21 | 25 | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 08 Oct 2015 | (iv)Valid Upto | 31 Mar 2016 | (v)File No. | WB/DIB/T-579/15-16/36/837 | (vi)Application No. | S&E/E/20/481 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 823.30 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 1.335 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 4.135 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.9451 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 3.5 | (b)Existing quantity of raw material/fuel | 0 | (c)Total quantity of raw material/fuel | 3.5 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | diesel | 3.5 | Kilo Litre per Day | | Local Supplier | Road | | 50 | Others | through supplier | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 06 Oct 2017 To 04 Jan 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 128 | 32 | 97.18 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 73 | 4 | 8.5 | 80 | (3.) | NOx | | Micro Gram per Meter Cube | 28 | 10.2 | 26.6 | 80 | (4.) | Others | CO | Mili Gram per Meter Cube | 0.88 | 0.13 | 0.74 | 2 | (5.) | PM2.5 | | Micro Gram per Meter Cube | 72 | 16 | 56.18 | 60 | |
14.2. No. of Ground Water monitoring locations : 5 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TDS | | | mg/l | | 135 | 56 | 500 | 2000 | (2.) | Fluoride | | | mg/l | | 0.17 | 0.1 | 1 | 1.5 | (3.) | Heavy Metals | | Lead | mg/l | | 0.01 | 0.01 | 0.01 | 0.01 | (4.) | TSS | | | Others | Not Analyzed | 0 | 0 | 0 | 0 | (5.) | pH | | | Others | No Unit | 6.73 | 6.39 | 6.5 | 8.5 | (6.) | Total Hardness | | | mg/l | | 78 | 31 | 200 | 600 | (7.) | Chlorides | | | mg/l | | 43 | 24 | 250 | 1000 | (8.) | Others | Alkalinity | | mg/l | | 78 | 31 | 200 | 600 | |
14.3. No. of Surface Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | Others | No Unit | 6.38 | 6.24 | C | (2.) | BOD | | mg/l | | 2 | 2 | A | (3.) | Others | Total Coliform | mg/l | | 49 | 1.8 | A | (4.) | COD | | mg/l | | 4 | 4 | A | (5.) | DO | | mg/l | | 6.7 | 6.2 | A | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 43.5 | 40.1 | 45 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 54.6 | 53.4 | 55 | |
14.5. No. of Soil Sample Monitored locations : 5 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | Electric Conductivity | Others | Microsiemens per Centimeter | 266 | 33 | (2.) | pH | Others | No Unit | 5.17 | 4.02 | (3.) | N(Nitrogen) | Milligram per Kilogram | | 417 | 347 | (4.) | P(Phosphorus) | Milligram per Kilogram | | 3 | 3 | (5.) | K(Potassium) | Milligram per Kilogram | | 156 | 16 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.16 To 4.23 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.14 To 5.69 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 39 | 0 | Copy of Permission Letter | modeOthers | Well at site | Tube Well | | S&E/E/98/1938 | 19 Dec 2019 | 40 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Drilling and Wash wastewater | 13.8 | 50 | Effluent Treatment Plant | Others | Zero Discharge | 13.8 | 0 | (2.) | Domestic Wastewater | 8 | 8 | Septic tank and soak pit | Others | Soak pit | 8 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 21.8 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 21.8 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Drill Cuttings | Industrial Waste | | 2640 | Tons | 0 | Others | Disposed at HDPE lined pits within site | Others | Disposed at HDPE lined pits within site | (2.) | Drilling Mud | Industrial Waste | | 5760 | Tons | 0 | Others | Disposed at HDPE lined pits within site | Others | Disposed at HDPE lined pits within site | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | NOx | | Microgram per Meter Cube | 18.07 | 0.6 | 16.20 | 34.27 | 80 | (2.) | PM10 | | Microgram per Meter Cube | 62.36 | 0.59 | 0.05 | 62.42 | 100 | (3.) | Others(Specify) | HC | Microgram per Meter Cube | 1.51 | 0.61 | 0.21 | 1.73 | no standard | (4.) | PM2.5 | | Microgram per Meter Cube | 33.49 | 0.59 | 0 | 33.50 | 60 | (5.) | SO2 | | Microgram per Meter Cube | 6.57 | 0.59 | 0.98 | 7.56 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG set-250 kVA | diesel | 3 | 0.3 | NOx | | 0.188 | (2.) | DG set-1250 kVA | diesel | 7 | 3 | NOx | | 1.836 | (3.) | DG set-250 kVA | diesel | 3 | 3 | Others | HC | 0.008 | (4.) | DG set-250 kVA | diesel | 3 | 0.3 | SO2 | | 0.026 | (5.) | DG set-1250 kVA | diesel | 7 | 0.3 | PM10 | | 0.007 | (6.) | DG set- 250 kVA | diesel | 3 | 0.3 | PM10 | | 0.003 | (7.) | DG set-1250 kVA | diesel | 7 | 0.3 | SO2 | | 0.039 | (8.) | DG set-1250 KVA | diesel | 7 | 3 | Others | HC | 0.004 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 2500 | (b)Source | Diesel generator Sets | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | one additional 1250 KVA | (e)Stack Height (in m) | 7 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 70 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 70 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 19848 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 9086 | (e)Settlements (ha.) | 15065 | (f)Industrial (ha.) | 359 | (g)Forest (ha.) | 3775 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Tea Garden, Government Land, Marshy Land, Road, Ra | 11533 | Total (ha.) | 59666.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Others | Wells and production facility | 70 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | Bherjan Borjan Podumoni WLS | 30.1 | Distance from nearest proposed well | (2.) | Corridors | None | 10 | No corridors within 10 km | (3.) | ESZs | None | 10 | No ESZs within 10 km | (4.) | Wildlife Corridors | None | 10 | No wildlife corridors within 10 km | (5.) | Critically Polluted Area | None | 10 | No critically polluted area within 10 km | (6.) | ESAs | None | 10 | No ESA within 10 km | (7.) | NPA | Dibru Saikhowa National Park | 18.6 | Distance from nearest proposed well | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Telpani R.F., Jokai R.F., Namdang R.F. | 0 | No wells in forest land | (2.) | Archaeological Sites | | None | 10 | No archaeological sites within 10 km | (3.) | Defence Installations | | None | 10 | No major defense installations within 10 km | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 70 | (c)Status of Land acquisition if not acquired | In process | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | 12 | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | INR 19.5 lakhs | (iii)Period of Implementation | 7 years | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Brahmaputra River, Burhi Dehing River, Sesa River | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Brahmaputra River | (ii)Direction of Water Bodies in Buffer Area | North West | (iii)Distance of Water Bodies in Buffer Area | 0 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 20 | (b)Permanent Employment-During Operation | 40 | (c)Temporary Employment- During Construction | 80 | (d)Temporary Employment- During Operation | 40 | (e)No. of working days | 120 | (f)Total Manpower | 180 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 0 | 1.75 | 1.75 | (2.) | Percentage of Total Project Area | 0 | 2.5 | 2.5 | (3.) | No. of Plants | 0 | 2800 | 2800 | (4.) | Funds Allocated | 0 | 1.75 | 1.75 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Provision of more employment opportunity to local people Development of
infrastructure (roads, culverts, bridges, schools etc.) in the area Increase in business
opportunity for the local people Programs related to livelihood generation, health
improvement as per OIL’s Corporate Social Responsibility (CSR) programs and Corporate Environmental Responsibility (CER) Programs | (2.) | Financial | Provision of more royalty to Assam Government and more cess to Govt. of India
Energy security for the country | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1922/RA/0177 | (ii)Name of the EIA Consultant | ERM India Pvt. Ltd. | (iii)Address | Building 10, Tower A, 4th Floor, DLF Cyber City Gurgaon 122002 | (iv)Mobile No. | 9830094463 | (v)Landline No. | 0124417030 | (vi)Email Id | debanjan.bandyopadhyay@erm.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 30 Oct 2022 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | (i) This is an expansion case. The certified compliance report of earlier EC needs to be uploaded.
(ii) Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation has not been submitted. Kindly upload the requisite documents. Form 2 (Sno. 7.1)
(iii) All old CTOs not uploaded to verify the violation, if any done by PP.
(iv) Copy of earlier EC is not uploaded in at S. No. 6 of Form 2.
(v) TOR compliance is not adequate in EIA/EMP report and need to revise as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006.
(vi) Status of Conservation Plan approval from CWLW.
(vii) Details of green belt mentioned Zero in form 2.
(viii) Valid Accreditation of Consultant need to be uploaded.
(ix) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Report. The EIA/EMP Report shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submitted the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. | 05 Mar 2020 | 2. | NA | The correction have been made as per the instruction received | 25 Jul 2020 | 3. | NA | 1. Please upload complete Public hearing report long with response of each observation raised during that.
2.Please confirm whether pipeline passing through National Park/Wildlife sanctuaries. | 02 Sep 2020 | 4. | NA | The correction have been made as per the instruction received | 12 Oct 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Ajit Chandra Haloi | Designation | CGM(HSE) | Name of Company (Applicant Name should not be given here) | OIL INDIA LIMITED | Address | OIL INDIA LIMITED
DULIAJAN
District : Dibrugarh |
|