Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Onshore Oil & Gas development drilling and production in Tengakhat-Kathaloni-Dikom area
(b)Name of the Company / Organisation OIL INDIA LIMITED
(c)Registered Address OIL INDIA LIMITED DULIAJAN District : Dibrugarh ,,Dibrugarh,Assam-786602
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ajit Chandra Haloi
(b)Designation (Owner/ Partner/ CEO) CGM(HSE)
(c)Address Safety & Environment Department , Oil India Limited, Duliajan,,,Dibrugarh,Assam-786602
(d)Pin code 786602
(e)E-mail safety@oilindia.in
(f)STD Code. 374(f)Telephone No. 2800542
(g)Fax No. 03742801796
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(b) Offshore and onshore oil and gas exploration, development & production
Minor Activity8(a) Building and Construction projects
(b)Category A
(c)Proposal Number IA/AS/IND2/88258/2018
(d)Master Proposal Number(Single Window) SW/138877/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Dibrugarh district of Assam
(b)Pincode 786001
(c)Bounded Latitudes (North)
From
Degree 27.257005
Minutes
Second
From
Degree 27.542556
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 94.978492
Minutes
Second
From
Degree 95.237589
Minutes
Second
(e)Survey of India Topo Sheet No. 83I14, 83I15, 83M2, 83M3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 120
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Assam
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)AssamDibrugarhDibrugarh East
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/1257/2007-IA II (I)
(b)Date of Apply of TOR 11 Dec 2018
(c)Date of Issue of TOR / Standard ToR 14 Jan 2019
(d)Date of Apply of EC
(e)Date of Issue of EC
(f)Previous TOR Letter Copy of Previous TOR letter
(g)Previous EC Letter NA
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 Aug 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :05 Sep 2019
Distance of Public Hearing Venue from the Proposed Project :1
Tengakhat Public Hall, Tengakhat
State :Assam
District :Dibrugarh
Tehsil :Tengakhat
Village :Tengakhat
59Control of pollution, CSR activities in the area, safety of locals from oil vehicles, Development projects in the areaOthersAdditional Deputy Commissioner
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Shillong
(iii)Letter No. RO-NE/E/IA/AS/MI/60/1800-1801
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 9 2016 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)167 wells and 7 production wells31174205OthersNo of wellsOtherswell drilling
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)167 wells and 7 production wells31174205
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 07 Dec 2011
(iv)Valid Upto 31 Mar 2012
(v)File No. WB/DIB/T-247/10-11/100/1409
(vi)Application No. S&E/E/20/465
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 5655
(b) Funds Allocated for Environment Management (Capital) (in Crores) 4.07
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1415
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 4.357
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3.5
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 3.5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)diesel3.5Kilo Litre per DayLocal SupplierRoad50 Othersthrough supplierCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 05 Oct 2017 To 07 Jan 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube13334101.24100
(2.)SO2Micro Gram per Meter Cube9.648.580
(3.)NOxMicro Gram per Meter Cube28.610.226.7280
(4.)PM2.5Micro Gram per Meter Cube691662.5460
(5.)OthersCOMili Gram per Meter Cube1.060.120.882
    14.2.     No. of Ground Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l12231200600
(2.)Chloridesmg/l71122501000
(3.)TDSmg/l198565002000
(4.)Heavy MetalsTotal Chromiummg/l0.010.010.050.05
(5.)pHOthersNo Unit6.896.226.58.5
(6.)Fluoridemg/l0.10.111.5
(7.)TSSOthersNot Analyzed0000
(8.)OthersAlkalinity as CaCO3mg/l12231200600
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHOthersNo Unit7.36.67A
(2.)OthersTotal ColiformOthersMPN/100 ml794.5B
(3.)DOmg/l86.2A
(4.)BODmg/l2.42B
(5.)CODmg/l184A
    14.4.     No. of Ambient Noise monitoring locations : 13
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))54.7153.2255
(2.)Leq(Night)A-weighted decibels(dB(A))48.4339.9745
    14.5.     No. of Soil Sample Monitored locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityOthersMicrosiemens per Centimeter8533
(2.)K(Potassium)Milligram per Kilogram11516
(3.)N(Nitrogen)Milligram per Kilogram437230
(4.)pHOthersNo Unit6.274.68
(5.)P(Phosphorus)Milligram per Kilogram293
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.16 To 4.23
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.14 To 5.69
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater390Copy of Permission LettermodeOthersWell at siteTube WellS&E/E/98/194721 Dec 201940
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Drilling and Wash wastewater13.850Effluent Treatment PlantOtherszero discharge13.80
(2.)Domestic Wastewater88Septic tank and soak pitOtherssoak pit80
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 21.8
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 21.8
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Drill cuttingsIndustrial Waste20064Tons0OthersDisposed at HDPE lined pits within siteOthersDisposed at HDPE lined pits within site
(2.)Waste drilling mudIndustrial Waste46080Tons0OthersDisposed at HDPE lined pits within siteOthersDisposed at HDPE lined pits within site
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube5.910.60.646.5680
(2.)NOxMicrogram per Meter Cube19.220.616.7135.9480
(3.)PM10Microgram per Meter Cube66.160.60.0166.18100
(4.)Others(Specify)HydrocarbonMicrogram per Meter Cube954.870.60.12955.000
(5.)PM2.5Microgram per Meter Cube35.880.6035.8960
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG set 1250 kVAdiesel70.3OthersHC0.004
(2.)DG set 250 kVAdiesel30.3PM100.003
(3.)DG set 250 kVAdiesel30.3SO20.026
(4.)DG set 250 kVAdiesel30.3OthersHC0.008
(5.)Flare stack well testingNatural Gas90.5NOx0.006
(6.)DG set 1250 KVAdiesel70.3PM100.007
(7.)DG set 1250 kVAdiesel70.3NOx1.836
(8.)DG set 250 kVAdiesel30.3NOx0.188
(9.)DG set 1250 kVAdiesel70.3SO20.039
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2500
(b)Source Diesel Generator Set
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1250
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 550
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 550
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 35003
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1925
(e)Settlements (ha.) 22654
(f)Industrial (ha.) 147
(g)Forest (ha.) 2615
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : River bed, bil, brick kiln, defense installation, 20462
    Total (ha.) 82806.0000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersWells and production installations550
Total (ha.) 550
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsDibru Saikhowa National Park9.7Approved ESZ of Dibru Saikhowa national Park from nearest well
(2.)Wildlife CorridorsNone10No wildlife corridors within 10 km
(3.)CorridorsNone10No corridors within 10 km
(4.)Critically Polluted AreaNone10No critically polluted area within 10 km
(5.)ESAsNone10No ESA within 10 km
(6.)WLSBherjan Borjan Podumoni WLS10.1Distance from nearest proposed well
(7.)NPADibru Saikhowa National Park10.1Distance from nearest proposed well
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone10No archaeological sites within 10 km
(2.)Defence InstallationsMohanbari Helipad, Air Force Station0No wells located in Defense installation
(3.)ForestTelpani Reserve Forest, Namdang Reserve Forest0No wells in forest land
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 550
(c)Status of Land acquisition if not acquired In process
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species 17 species
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 19.5 lakhs
(iii)Period of Implementation 7 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Buri Dihing River
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Brahmaputra River
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 1.47
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 20
(b)Permanent Employment-During Operation 40
(c)Temporary Employment- During Construction 80
(d)Temporary Employment- During Operation 40
(e)No. of working days 120
(f)Total Manpower 180
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt012.2512.25
(2.)Percentage of Total Project Area02.222.22
(3.)No. of Plants01960019600
(4.)Funds Allocated012.2512.25
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialProvision of more employment opportunity to local people Development of infrastructure (roads, culverts, bridges, schools etc.) in the area Increase in business opportunity for the local people Programs related to livelihood generation, health improvement as per OIL’s Corporate Social Responsibility (CSR) programmes and Corporate Environmental Responsibility (CER) programmes.
(2.)FinancialProvision of more royalty to Assam Government and more cess to Govt. of India Energy security for the country
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA 0177
(ii)Name of the EIA Consultant ERM India Pvt. Ltd.
(iii)Address Building 10, Tower A, 4th Floor, DLF Cyber City Gurgaon 122002
(iv)Mobile No. 9830094463
(v)Landline No. 9112441703
(vi)Email Id debanjan.bandyopadhyay@erm.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 30 Oct 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) This is an expansion case. The certified compliance report of earlier EC needs to be uploaded. (ii) Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation has not been submitted. Kindly upload the requisite documents. Form 2 (Sno. 7.1) (iii) All old CTOs not uploaded to verify the violation, if any done by PP. (iv) Copy of earlier TOR/EC is not uploaded in at S. No. 6 of Form 2. (v) TOR compliance is not adequate in EIA/EMP report and need to revise as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006. (vi) Status of Conservation Plan approval from CWLW. (vii) Details of green belt mentioned Zero in form 2. (viii) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Report. The EIA/EMP Report shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submitted the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. 05 Mar 2020
2.NAThe correction have been made as per the instruction received 26 Jul 2020
3.NA1. Please upload complete Public hearing report. 2. Latest certified compliance report is still not submitted/uploaded. 02 Sep 2020
4.NAThe correction have been made as per the instruction received 16 Oct 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAjit Chandra Haloi
DesignationCGM(HSE)
Name of Company (Applicant Name should not be given here)OIL INDIA LIMITED
AddressOIL INDIA LIMITED DULIAJAN District : Dibrugarh
Print