Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Vijayanagar Sugar Pvt. Ltd.,
(b)Name of the Company / Organisation M/S. VIJAYANAGAR SUGAR PVT. LTD.,
(c)Registered Address M/s. Vijayanagar Sugar Pvt. Ltd., Plot No.359, Road No. 80, Jubilee Hills, Hyderabad,,Gadag,Karnataka-582118
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant SivaramiReddy B
(b)Designation (Owner/ Partner/ CEO) Directoroperations
(c)Address M/s. Vijayanagar Sugar Pvt. Ltd., Gangapur Village, Mundargi Taluk, Gadag District,,Mundargi,Gadag,Karnataka-582118
(d)Pin code 582118
(e)E-mail em@vspl.in
(f)STD Code. 8371(f)Telephone No. 265100
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity
(b)Category A
(c)Proposal Number IA/KA/IND2/137096/2020
(d)Master Proposal Number(Single Window) SW/137091/2020
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey No. 32, 33, 34 of Gangapur and Survey No.13
(b)Pincode 582118
(c)Bounded Latitudes (North)
From
Degree 15.0521
Minutes
Second
From
Degree 75.5203
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 15.0517
Minutes
Second
From
Degree 75.5241
Minutes
Second
(e)Survey of India Topo Sheet No. D43D16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 522
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bangalore
(iii)Letter No. EP/12.1/548/Karnataka dated 2nd March 2020
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jan 23 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Distillery120180300Kilo Litre per Day(KLD)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Incineration Bolier32840TPH
(2.)Distillation7714Columns
(3.)Evaporation5407401280TPD
(4.)Biocomposting01010Acres
(5.)Fermentation6612Tanks
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 30 Nov 2016
(iv)Valid Upto 30 Jun 2021
(v)File No. AW-301529
(vi)Application No. 10666
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 225
(b) Funds Allocated for Environment Management (Capital) (in Crores) 9.75
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.7
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 3.18
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 604
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 604
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Grains – Maize, jowar, broken rice800OthersTPDProcured from local farmersRoad30 Open MarketCopy of Linkage
(2.)Molasses as raw material for distillery604OthersTPDcaptivePipe Conveyor0 CaptiveCopy of Linkage
(3.)Sugarcane Juice1720Kilo Litre per DaycaptivePipe Conveyor0 CaptiveCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.22 To 5.3
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 23.6 To 24.7
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface37558.5Copy of Permission LetterPipelineJack WellWRD151MTP201824 Jul 201915750
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Condensate, spent lees and utility effluents23242500Biological treatmentReuse within the Plant & Recycling23240
(2.)Spent wash10201200MEE and incineration boilerOthersZLD10200
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 3344
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 3344
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Boiler ashIndustrial Waste12000Tons0Conveyor Belt,OthersTrolleyOthersBrick making,given to farmers after bio composting
(2.)DDGSIndustrial Waste84000Tons0OthersTrucksOthersCattle feed
(3.)Yeast sludgeIndustrial Waste4500Tons0OthersTractorsOthersComposting
(4.)ETP sludgeIndustrial Waste300Tons0OthersTractorOthersComposting
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube45.32.841460100
(2.)PM2.5Microgram per Meter Cube29.82.678.73960
(3.)NOxMicrogram per Meter Cube9.92.862.981380
(4.)SO2Microgram per Meter Cube4.32.781.385.980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boiler - 20 TPHCoal /bagasse301.1OthersPM100
(2.)Boiler - 60 TPHCoal/bagasse603OthersPM100
(3.)Incineration boiler - 40 TPHslop and coal453OthersPM45
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 6200
(b)Source Captive
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2 x 1250 kVA and 1 x 250 kVA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 53.82
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 53.82
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 53.82
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Industrial 0
    Total (ha.) 53.82
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersIndustrial53.82
Total (ha.) 53.82
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNone0None
(2.)CorridorsNone0None
(3.)ESZsNone0None
(4.)Critically Polluted AreaNone0None
(5.)WLSNone0None
(6.)NPANone0None
(7.)Wildlife CorridorsNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone0None
(2.)ForestKappatagudda Reserve forest3Reserve forest
(3.)Defence InstallationsNone0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 53.82
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Tungabhadra River
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 2
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 60
(c)Temporary Employment- During Construction 40
(d)Temporary Employment- During Operation 10
(e)No. of working days 300
(f)Total Manpower 110
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt85590
(2.)Percentage of Total Project Area633.766.7
(3.)No. of Plants42070500047070
(4.)Funds Allocated23520255
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment Opportunities
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/IA0051
(ii)Name of the EIA Consultant Samrakshan
(iii)Address F4, 1st floor, Swastik Manandi Arcade, S C Road, Sheshadripuram, Bangalore
(iv)Mobile No. 9845381819
(v)Landline No. 0802346010
(vi)Email Id samrakshanblr@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 24 Jul 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) Copy of earlier EC in SNo. 6 of Form 2 has not been uploaded. (ii) Details of old Consent to Operate not uploaded to check the violation if any. (iii) This is an expansion case kindly upload the latest certified compliance report of RO MoEFCC. (iv) Details of Court case if any. (v) Air Quality Impact Prediction mentioned (18.1 of form 2) is inadequate kindly correct it. (vi) Certificate of MOPNG as per Ministry notification dated 17.01.2019 needs to be uploaded. (vii) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Report. The EIA/EMP Report shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submitted the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. 05 Feb 2020
2.NAThe correction have been made as per the instruction received 02 Mar 2020
3.NAThe matter has been examined and it is noted that PP has not revised the Form 2. PP has only attached the earlier EDS in additional documents. It seems that PP/consultant is not serious about the instruction given in earlier EDS. Further this is an expansion case, PP has not uploaded the certified compliance report and only uploaded a communication letter of RO MoEFCC wherein no certified compliance report is uploaded. Consultant while uploading the complete information read the instruction carefully and upload the requisite documents other wise necessary action against the consultant will be taken by the Ministry. In view of the above please read the instruction carefully and upload all the documents and revise Form 2 as in the Ministry the processing of the EC proposals are through Parivesh Portal only. 23 Mar 2020
4.NAThe correction have been made as per the instruction received 24 Apr 2020
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSivaramiReddy B
DesignationDirectoroperations
Name of Company (Applicant Name should not be given here)M/S. VIJAYANAGAR SUGAR PVT. LTD.,
AddressM/s. Vijayanagar Sugar Pvt. Ltd., Plot No.359, Road No. 80, Jubilee Hills, Hyderabad
Print