Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion in Cement Production Capacity (1.5 MTPA to 2.2 MTPA) of Existing Stand-alone Grinding Unit at Village: Navagraon, P.O.: Jajhra, Tehsil: Nalagarh, District: Solan (Himachal Pradesh) by M/s. A
(b)Name of the Company / Organisation AMBUJA CEMENT LIMITED
(c)Registered Address 228. Udyog Vihar, Phase-I,Gurgaon,Gurgaon,Haryana-122016
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sanjeew Kumar Singh
(b)Designation (Owner/ Partner/ CEO) Manager - Environment
(c)Address 228, Udyog Vihar, Phase-I,,,Gurgaon,Haryana-122016
(d)Pin code 122016
(e)E-mail sanjeewkumar.singh@adani.com
(f)STD Code. 124(f)Telephone No. 4565328
(g)Fax No. 01244531180
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(b) Cement plants
Minor Activity
(b)Category A
(c)Proposal Number IA/HP/IND/136337/2008
(d)Master Proposal Number(Single Window) SW/136318/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khasra Map enclosed with PFR
(b)Pincode 174101
(c)Bounded Latitudes (North)
From
Degree 31.06.39.21
Minutes
Second
From
Degree 31.07.03.72
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 76.38.20.19
Minutes
Second
From
Degree 76.38.50.63
Minutes
Second
(e)Survey of India Topo Sheet No. 53 A/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 375
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 6.0
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Himachal Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/173/2008-IA.II(I)
(c)Date of Issue of TOR 22 Aug 2008
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 21 Jan 2020
(c)Date of Issue of EC 28 Apr 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :21 Nov 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :22 Dec 2018
Distance of Public Hearing Venue from the Proposed Project :0.5
Panchayat Bhawan,
State :Himachal Pradesh
District :Solan
Tehsil :Nalagarh(T)
Village :Navagraon, P.O.: Jajhra
224Employment, Environment, C.S.ROthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Dehradun
(iii)Letter No. 6-93/2008-RO(NZ)/1964
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Nov 20 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Cement(opc/ppc)1.50.72.2OthersMTPARoad,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Clinker grinding Unit (VRM)250 TPHNil250 TPH
(2.)Truck tippler for clinker unloading 2 Nos100 TPH eachNil100 TPH
(3.)Truck loading machines - 06 Nos2400 Bags/hour (50 kg)Nil2400 Bags/hour (50 kg)
(4.)Gypsum Crusher - 01 No.75 TPHNil75 TPH
(5.)Flyash unloading - 01 No.100 TPHNil100 TPH
(6.)Packing machines - 2 Nos240 TPH eachNil240 TPH each
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 03 Oct 2018
(iv)Valid Upto 31 Mar 2020
(v)File No. HPSPCB/PCB-ID 14049 20132-34
(vi)Application No. Online application inward No: 71396
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 0
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.44
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.8
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1.02
(b)Existing quantity of raw material/fuel 1.95
(c)Total quantity of raw material/fuel 2.9699999999999998
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Clinker2.04OthersMTPAAmbuja’s Rauri / Darlaghat Unit, H.PRoad90 CaptiveCCopy of Linkage
(2.)GYPSUM0.15OthersMTPADabwaliRoad250 OthersPOCopy of Linkage
(3.)Furnace oil210Tons per AnnumIOCL,PanipatRoad220 OthersPOCopy of Linkage
(4.)Fly ash0.77OthersMTPAGuru Govind Singh TPP, H.P/Haryana/PunjabRoad275 OthersPOCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube14.35.413.480
(2.)NOxMicro Gram per Meter Cube23.27.622.680
(3.)PM10Micro Gram per Meter Cube92.461.890.7100
(4.)PM2.5Micro Gram per Meter Cube41.922.740.660
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)TDSmg/l5402325002000
(3.)Chloridesmg/l111.5411.742501000
(4.)Fluoridemg/l0.840.231.01.5
(5.)pHNA7.617.196.58.5
(6.)Total Hardnessmg/l356156200600
    14.3.     No. of Surface Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.177.73E
(2.)BODmg/l15.381.10E
(3.)CODmg/l50.804.08E
(4.)DOmg/l5.905.20E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))52.740.370
(2.)Leq(Day)A-weighted decibels(dB(A))61.449.175
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare34.5116.96
(2.)Electric ConductivityMillisiemens per Centimetre0.460.11
(3.)N(Nitrogen)Kilogram per hectare209.34142.78
(4.)pH8.257.14
(5.)K(Potassium)Kilogram per hectare431.92235.62
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 22.30 To 23.50
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 18.90 To 21.10
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater4000Copy of Permission LetterPipelineOthersBorewellIPH-SE-P&I-II-EE-CGWA/2015:- 1366-6905 Dec 2015400
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic Waste water5555STPOthersused for greenbelt development/plantation550
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 55
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 55
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)FO SludgeIndustrial Waste216Kilolitre50RoadAuthorized Recyclers
(2.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)10Kilolitre50RoadAuthorized Recyclers
(3.)STP SludgeMunicipal Solid Waste0.05Tons0RoadOthersMannure in Greenbelt development/ Plantation
(4.)Empty Paint DrumsIndustrial Waste300Kilolitre50RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube79.5010.6580.16100
(2.)SO2Microgram per Meter Cube9.3009.3180
(3.)PM2.5Microgram per Meter Cube32.90032.9160
(4.)NOxMicrogram per Meter Cube14.20014.2180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Cement Mill Bag houseNA541.7PM100.225
(2.)Packing Plant - 1 Bag FilterNA31.61PM100.152
(3.)Clinker Dump Hopper - 1 Bag FilterNA321PM100.161
(4.)Clinker Dump Hopper -2 Bag FilterNA321PM100.177
(5.)Packing Plant - 2 Bag FilterNA31.61PM100.163
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 9300
(b)Source HPSEBL & D.G Set
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 10 MW (1 nos) & 1 MW(1 nos)
(e)Stack Height (in m) 66
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 29.09
    Total Land (ha.) 29.09
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 29.09
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 29.09
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt10.3
(2.)Othersopen area6.8
(3.)Main Plant11.99
Total (ha.) 29.09
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsNA0No ESZs within 10 km radius
(2.)Wildlife CorridorsNA0No Wildlife Corridors within 10 km
(3.)CorridorsNA0No Corridors within 10 km
(4.)Critically Polluted AreaNA0No critically Polluted Area within 10 km
(5.)WLSNA0No WLS within 10 km radius
(6.)NPANA0No NPA within 10 km radius
(7.)ESAsNA0No ESAs within 10 km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestHatra PF0.7in SE direction
(2.)Defence InstallationsNot Applicable0No defence installation within 10 km
(3.)Archaeological SitesNot Applicable0No Archaeological site within 10 km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species • Indian Peafowl (Pavo Cristatus), • Leopard (Panthera Pardus) • Monitor Lizard (Varanus Bengalensis)
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 27.5 Lacs
(iii)Period of Implementation 5 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. WL (MISC.)73/ Mining/Vol- X/1155
(iii)Date of issue 03 May 2019
(iv)Recommendation NA
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Satluj River
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 6.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 69
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 144
(e)No. of working days 330
(f)Total Manpower 213
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt10.3010.3
(2.)Percentage of Total Project Area33033
(3.)No. of Plants41455041455
(4.)Funds Allocated50050
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreenery of the area will be maintained
(2.)SocialEmployment generation and upliftment of the nearby villagers through CER
(3.)FinancialRevenue generation for State and Centre in terms of taxes etc.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/SA 097
(ii)Name of the EIA Consultant J.M. EnviroNet Pvt. Ltd.
(iii)Address 202-A, ABW Tower, MG Road, IFFCO Chowk, Sector 25, Gurugram (Haryana) – 122001
(iv)Mobile No. 9910494521
(v)Landline No. 0124414192
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 07 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSanjeew Kumar Singh
DesignationManager - Environment
Name of Company (Applicant Name should not be given here)AMBUJA CEMENT LIMITED
Address228, Udyog Vihar, Phase-I, Gurgaon, Haryana - 122016