1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Tubachi Bableshwara LIS | (b)Name of the Company / Organisation | KARNATAKA NEERAVARI NIGAM LTD | (c)Registered Address | Chief Engineer KNNL Irrigation North Zone Club Road Belgaum Karnataka,,Belgaum,Karnataka-590001 | (d)Legal Status of the Company | State Government | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Chief Engineer Chief | (b)Designation (Owner/ Partner/ CEO) | Chief Engineer | (c)Address | Chief Engineer KNNL Irrigation North Zone Club road Belgaum Karnataka,,Bangalore South,Bangalore Urban,Karnataka-560001 | (d)Pin code | 590001 | (e)E-mail | tubachilis@gmail.com | (f)STD Code. | 831(f)Telephone No. | 2422639 | (g)Fax No. | 22267314 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(c) River Valley projects
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/KA/RIV/70372/2017 | (d)Master Proposal Number(Single Window) | SW/135899/2020 | (e)EAC concerned (for category A Projects only) | River Valley and Hydroelectric Projects | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Kavatagi village | (b)Pincode | 590001 | (c)Bounded Latitudes (North) | | From | | Degree | 1640.634 | Minutes | | Second | | From | | Degree | 1659.956 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 7537.62 | Minutes | | Second | | From | | Degree | 7541.28 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 47 P2 P3 P5 P6 P7 P9 P10 P11 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 650 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.5 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Karnataka | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Jharkhand | Chatra | Tandwa | Tandwa | (2.) | Karnataka | Belgaum | Athni | | (3.) | Karnataka | Bagalkot | Jamkhandi | | (4.) | Karnataka | Bijapur | Bijapur | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | J-12011/33/2017-IA.I (R) | (b)Date of Apply of TOR | 17 Oct 2017 | (c)Date of Issue of TOR / Standard ToR | 29 Nov 2017 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | The new command area added in the project is withi | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | 52700 ha | command area | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | command area | 52700 | Hectares | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 3572 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 358.50 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 9.83 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 58.22 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 28188 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 28188 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Cement | 28188 | Others | MT | Bagalkot | Road | | 130 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Jan 2018 To 30 Sep 2018 | (b)Season | Three-Sesions | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 70 | 58 | 69.54 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 14.79 | 10.56 | 14.71 | 80 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 25 | 20 | 24.54 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 8.77 | 4.1 | 8.59 | 80 | |
14.2. No. of Ground Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.44 | 7.12 | 6.5 | 8.5 | (2.) | TSS | | | NA | | 0 | 0 | 0 | 0 | (3.) | TDS | | | mg/l | | 2680 | 686 | 500 | 2000 | (4.) | Total Hardness | | | mg/l | | 1040 | 272 | 200 | 600 | (5.) | Chlorides | | | mg/l | | 0.79 | 0.29 | 1 | 1.5 | (6.) | Heavy Metals | | pb | mg/l | | 0.01 | 0 | 0.01 | 0.01 | (7.) | Others | iron | | mg/l | | 0 | 0 | 5 | 15 | (8.) | Fluoride | | | mg/l | | 0.75 | 0 | 1 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 5.5 | 5.4 | C | (2.) | COD | | mg/l | | 40 | 16 | C | (3.) | BOD | | mg/l | | 6 | 5 | C | (4.) | pH | | NA | | 8.19 | 7.89 | C | |
14.4. No. of Ambient Noise monitoring locations : 2 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 48.69 | 46.7 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 36.9 | 35.8 | 45 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 182.62 | 48.15 | (2.) | Electric Conductivity | Millisiemens per Centimetre | | 492 | 305 | (3.) | pH | | | 7.65 | 7.6 | (4.) | P(Phosphorus) | Kilogram per hectare | | 56.01 | 4.3 | (5.) | K(Potassium) | Kilogram per hectare | | 113.56 | 4.28 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 130 To 55 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 130 To 55 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 2.25 | 1.5 | Not Appliacble | Canal | | Jack Well | | WRD 52 VBE 2014 | 28 Feb 2014 | 2.25 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | waste water from labour colonies | 20 | 22 | septic tank | Others | septic tank | 18 | 2 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 20 | (b)Total Discharged Water (Kilolitre per Day) | 2 | (c)Total Reused Water (Kilolitre per Day) | 18 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | LABOUR CAMPS | Municipal Solid Waste | | 15 | Tons | 1.5 | Road | | Authorized Recyclers | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 64.77 | 0 | 58 | 130 | 100 | (2.) | NOx | | Microgram per Meter Cube | 12.09 | 0 | 10.56 | 35 | 80 | (3.) | PM2.5 | | Microgram per Meter Cube | 22.08 | 0 | 20 | 45 | 60 | (4.) | SO2 | | Microgram per Meter Cube | 5.98 | 0 | 4.1 | 12 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG | HSD | 4 | 0.01 | PM10 | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 52 | (b)Source | HESCOM | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 125 | (e)Stack Height (in m) | 4 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0.73 | (b)Private Land (ha.) | 2418.27 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 2419 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 96400.62 | (b)Waste/Barren Land (ha.) | 18469.20 | (c)Grazing/ Community Land (ha.) | 2314.06 | (d)Surface Water Bodies (ha.) | 1645.95 | (e)Settlements (ha.) | 2499.53 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 187.58 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : scrub forest | 3643.50 | Total (ha.) | 125160.43999999999 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Others | Project components | 2419 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Wildlife Corridors | NA | 0 | NA | (2.) | ESZs | NA | 0 | NA | (3.) | Corridors | NA | 0 | NA | (4.) | Critically Polluted Area | NA | 0 | 0 | (5.) | WLS | NA | 0 | NA | (6.) | NPA | NA | 0 | NA | (7.) | ESAs | NA | 0 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Defence Installations | | NA | 0 | NA | (2.) | Archaeological Sites | | NA | 0 | NA | (3.) | Forest | | Jamakhandi Reserve forest | 6.18 | RF | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 97 | (b)Land yet to be acquired(Ha) | 2322 | (c)Status of Land acquisition if not acquired | Under progress | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Indian Peafoul | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 300000 | (iii)Period of Implementation | 2 | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 150 | (b)Permanent Employment-During Operation | 50 | (c)Temporary Employment- During Construction | 80 | (d)Temporary Employment- During Operation | 20 | (e)No. of working days | 1095 | (f)Total Manpower | 300 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 30 | (b)Percentage of Total Project Area | 1.24 | (c)No. of Plants to be Planted | 102216 | (d)Funds Allocated for Plantation | 1074000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Agro forestry will be taken up in command area and it improves the ecosystem services.
Canal Bank plantation improves local biological diversity. | (2.) | Social | No Rehabilitation and Resettlement.
Direct employment opportunities for 300 peoples (50 Technical and 250 construction labourers) are expected to get employment for the construction of intake channel, jack well cum pump house, raising main, delivery chambers and distribution network consisting of Lift cum Flow Irrigation System. During operation phase indirectly labourers will be appointed operation and maintenance of the jack well. | (3.) | Financial | Agricultural linkages will be considerably improved.
The project improves total farm output and hence raises farm income.
Project improves yields through reduced crop loss due to erratic, unreliable or insufficient rainfall.
Extensive agricultural production supplies raw materials to the nearby small scale industries thereby increasing the economy in the region. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For River Valley and Hydroelectric Projects |
|
1. | Project Sub Sector | Irrigation Project | 2. | Name of the River | Krishna | 3. | Whether Cumulative Impact Assessment and Carrying Capacity Study of River Basin is Carried Out? | No |
|
|
4. Type of Project: (Construction of Dam/ Barrage/ Run of the River/ Lift Irrigation Scheme) |
---|
S. No. | Project Type | Dam Height (in meters) | Dam Length (in meters) | Total Submergence Area (in hectare) | Gross Command Area (GCA) (in hectare) | Irrigable Command Area (ICA) (in hectare) | Culturable Command Area (CCA) (in hectare) | Total Command Area (in hectare) |
---|
(1.) | Lift Irrigation Scheme | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
5. | Powerhouse Installed Capacity | No | (a) Type of Powerhouse | Underground | (b) Capacity (in megawatts) | 0 | (c) No. of Tunnels | 0 | (d) No. of Units | 0 | (e) Bank of River | Right |
|
|
6. | Generation of Electricity Annually. | (a) Quantity of Generation of Electricity Annually (in giga watt hours) | 0 | (b) Water Availability at Various percentage | S. No. | Percentage | Water availability (in cusecs) | Dependable year | Remarks |
---|
(1.) | 50 % | 2293 | 91 | | (2.) | 75 % | 2185 | 2001 | | (3.) | 90 % | 3230 | 2007 | | | (c) Machine Availability (in percent) | 0 | (d) Cost of Electricity Generation (in INR) | 0 | (e) Internal Rate of Return (in percent) | 0 | (f) Year of achievement of Internal Rate of Return | 0 |
| 7. | Catchment Area Treatment Plan | Copy of Catchment Plan | 8. | Muck Management Plan | (a)Muck Management Plan | Copy of Muck Management Plan | (b) Total Excavation Muck (in cubic meter) | 3952500 | (c) Utilized for Construction (in cubic meter) | 1185750 | (d) No. of Muck Disposal sites | 0 | (e) Total Muck Disposal Area (in hectare) | 0 |
| 9. | Fishery Development and Management Plan | (a)Fishery Development and Management Plan | Copy of Fishery Development and Management Plan | (b) No. of Fish Species | 28 | (c) Name of the umbrella Fish Species (Scientific Name) | Hypselobarbus pulchellus |
| 10. | Status of Environmental Flow | S. No. | Season | Average Inflow (in cumec) | Percent of Flow |
---|
(1.) | Lean | 50 | 25 | (2.) | Monsoon | 200 | 36.4 | (3.) | Non-Lean Non-Monsoon | 200 | 36.4 | |
| 11. | Free Flow Stretch (in km) | 5 | 12. | Approval of Central Water Commission | No |
| 13. | Approval of Central Electricity Authority | No |
| 14. | Details of Coffer Dam (Upstream) | Yes | (a) Quantity of the material (in cubic meter). | 0 | (b) Length of the dam (in meter) | 0 | (c) Decommissioning Plan | Copy of Decommissioning Plan |
| 15. | Details of Coffer Dam (Downstream) | None |
| |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | 1821 | (ii)Name of the EIA Consultant | Environemntal Health and Safety Consultants Privat | (iii)Address | 174 new No. 13/2 14th E CROSS INDUSTRIAL TOWN AGRAHARA DASARAHALLI BANGALORE | (iv)Mobile No. | 9448094164 | (v)Landline No. | 0802301620 | (vi)Email Id | ehscblr1974@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | River Valley and Hydroelectric Projects | (ix)Validity of Accreditation | 22 Apr 2021 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Submission of compliance to oberservations sought from EAC during the meeting held on 27.01.2020 | 26 May 2020 | 2. | NA | EAC opined that instant proposal involving
flood irrigation shall be revised. EAC after detailed deliberation deferred the proposal for want of
following information:
Print
|
|
|
|