Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Project for manufacturing of Carbon Black & Power Generation (Green Power) by M/s. Madura Carbon (India) Ltd.
(b)Name of the Company / Organisation MADURA CARBON INDIA LTD
(c)Registered Address Survey No. 3705 to 3710, 3712, 3713, 3715, 3717, 3718, 3720, 3722 to 3724, 3726, 3727, 3730, 3733 to 3740, 3742, 3743, 4049, 4084 to 4090, 4095, 4105, 4107, 4108, 4110, 4112, 4133 to 4135, 4301, 4317, 5134, 5220 to 5222, 5226, 5227, 5236, 5264, Villa,,Valsad,Gujarat-396155
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Vipan Kalra
(b)Designation (Owner/ Partner/ CEO) CMD
(c)Address 1, Janki Centre, Off-Veera Desai Road, Andheri west, Mumbai-400053,,Andheri,Mumbai City,Maharashtra-400053
(d)Pin code 400053
(e)E-mail vipankalra@hotmail.com
(f)STD Code. 22(f)Telephone No. 26730890
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(e) Petrochemical based processing (processes other than cracking &
Minor Activity1(d) Thermal Power Plants
(b)Category A
(c)Proposal Number IA/GJ/IND2/76156/2018
(d)Master Proposal Number(Single Window) SW/134901/2020
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey no. 3705, 3708, 3719, 3725, 3738, 4108, 411
(b)Pincode 396155
(c)Bounded Latitudes (North)
From
Degree 20.298489
Minutes
Second
From
Degree 20.305154
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.837415
Minutes
Second
From
Degree 72.840181
Minutes
Second
(e)Survey of India Topo Sheet No. F43S11, F43S15, F43S16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 41
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratValsadUmbergaon
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/266/2018-IA-II(I)
(b)Date of Apply of TOR 05 Mar 2019
(c)Date of Issue of TOR / Standard ToR 06 Apr 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :17 Jun 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :19 Jul 2019
Distance of Public Hearing Venue from the Proposed Project :0
Survey no. 3705, 3708, 3719, 3725, 3738, 4108, 4110, 4318, Village: Fansa (Karajgam), Taluka: Umbergaon, Dist.: Valsad, Gujarat
State :Gujarat
District :Valsad
Tehsil :Umbergaon
Village :Fansa (Karajgam)
374A summarized table showing salient points highlighting issues raised by the participants & issues raised by the concerned persons having plausible stake in Environment and responded by the representatDistrict Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Plant230000 TPAProduction Capacity
(2.)Plant45 MWPower Generation (Green Power)
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Carbon Black230000Tons per AnnumRoad
(2.)Power Generation (Green Power)45Mega Watt(MW)Otherspower distribution system
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 440
(b) Funds Allocated for Environment Management (Capital) (in Crores) 86.5
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 6.6
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 26.45
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 411010
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 411010
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Feed Stock363400Tons per AnnumIndian Market & ImportedRoad300 Open MarketCopy of Linkage
(2.)Potassium Nitrate690Tons per AnnumLocal TradersRoad300 Open MarketCopy of Linkage
(3.)FUEL- FURNACE OIL46000Tons per AnnumLocal TradersRoad300 Open MarketCopy of Linkage
(4.)Molasses920Tons per AnnumLocal TradersRoad300 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 02 Oct 2018 To 28 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube896089100
(2.)OthersCOMili Gram per Meter Cube1.180.111.184
(3.)PM2.5Micro Gram per Meter Cube44164460
(4.)SO2Micro Gram per Meter Cube2292280
(5.)NOxMicro Gram per Meter Cube26102680
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.827.518.50
(2.)TSSmg/l0000
(3.)Fluoridemg/l0.60.111.5
(4.)OthersTotal Alkalinitymg/l274206200600
(5.)TDSmg/l6174845002000
(6.)Total Hardnessmg/l296218200600
(7.)Chloridesmg/l95632501000
(8.)Heavy MetalsIronmg/l0.30.10.30
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.31.3E
(2.)CODmg/l11214A
(3.)BODmg/l325E
(4.)pHNA8.167.6A
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))69.942.875-50
(2.)Leq(Night)A-weighted decibels(dB(A))62.937.470-40
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.887.25
(2.)P(Phosphorus)Milligram per Kilogram2822
(3.)N(Nitrogen)Milligram per Kilogram130127
(4.)K(Potassium)Milligram per Kilogram10390
(5.)Electric ConductivityMillisiemens per Centimetre1.321.20
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 15 To 30
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface25250.80Copy of Permission LetterCanalOthersDamanganga Canal Distry.DCDD-3/PB-2/Madura Carbon/203120 Jun 20192900
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial585585ETP, RO & MEEReuse within the Plant & Recycling,OthersLosses54639
(2.)Domestic4545STPGreen Belt Renewal Plant,OthersLoss441
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 630
(b)Total Discharged Water (Kilolitre per Day) 40
(c)Total Reused Water (Kilolitre per Day) 590
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)50Tons300RoadTreatment, Storage and Disposal Facility(TSDF)
(2.)Sludge from APCMHazardous Waste (as per Hazardous and Other Waste Management rules 2016)43625Tons300RoadOthersSell to cement/ gypsum board manufacturers.
(3.)Scrubber Bleed LiquorHazardous Waste (as per Hazardous and Other Waste Management rules 2016)21900Kilolitre0Othersinhouse pipeOthersTreatment in In-house ETP.
(4.)MEE SaltHazardous Waste (as per Hazardous and Other Waste Management rules 2016)150Tons300RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Oily Cotton WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2Tons100RoadTreatment, Storage and Disposal Facility(TSDF)
(6.)Spent Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)100Kilolitre300RoadAuthorized RecyclersSale to registered reprocessor/ recycler
(7.)Discarded ContainersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5Tons300RoadOthersSale to registered recycler
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube89.002.831.8090.81100
(2.)PM2.5Microgram per Meter Cube44.002.831.8045.8160
(3.)SO2Microgram per Meter Cube22.002.836.0928.1080
(4.)NOxMicrogram per Meter Cube263.611.8627.8780
(5.)Others(Specify)COMicrogram per Meter Cube1180.000.7729.161209.174000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boiler-112 TPH+Boiler-72 TPHOffgas1103.2OthersPM, SO2, NOx, COPM-3.90g/s, SO2-21.36g/s, NOx-8.72g/s, CO-19.56g/s
(2.)Dryer Combustor + Vapour Bag Collector (Line-1))Offgas602OthersPM, SO2, NOxPM-1.62g/s, SO2-4.80g/s, NOx-0.99g/s
(3.)Dryer Combustor+Vapour Bag Collector (Line-2)Offgas602OthersPM, SO2, NOxPM-1.08g/s, SO2-3.20g/s, NOx-0.66g/s
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 13000
(b)Source Inhouse PP & DGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1000 kVA
(e)Stack Height (in m) 35
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 9.4499
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 9.4499
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 10277
(b)Waste/Barren Land (ha.) 8537
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 916
(e)Settlements (ha.) 1477
(f)Industrial (ha.) 916
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 4093
(j)Others (ha.) : Floodplains, Roads, Railways, Open Spaces, Quarrie 5221
    Total (ha.) 31437
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant3.17
(2.)Green belt2.48
(3.)OthersOpen Area (Roads, Drains, Space)3.80
Total (ha.) 9.45
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaGIDC Vapi8None
(2.)ESZsNone0None within 10 km study area
(3.)NPANone0None within 10 km study area
(4.)CorridorsNone0None within 10 km study area
(5.)Wildlife CorridorsNone0None within 10 km study area
(6.)WLSNone0None within 10 km study area
(7.)ESAsNone0None within 10 km study area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological Sitesnone0None within study area
(2.)ForestPatches of reserved forest0.8Distance map obtained from forest department
(3.)Defence Installationsnone0No within study area
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 9.45
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Panthera paradus, Pavo cristatus, Varnus bengalensis & Indirana leithii
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 0
(iii)Period of Implementation As per conservation plan
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area River Darotha
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 760
(c)Temporary Employment- During Construction 300
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 1060
32.
Green Belt in Ha:
(a)Total Area of Green Belt 2.48
(b)Percentage of Total Project Area 26.24
(c)No. of Plants to be Planted 5000
(d)Funds Allocated for Plantation 3000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialDevelopment of the social structure & improvement of the quality of life in the surrounding area due to growth in the economic conditions and Rs. 6.6 Cr. will be allocated for next 10 years for CER activities.
(2.)FinancialGeneration of direct employment opportunities. Approximately 760 people will be employed from the proposed project which will result growth in the economic conditions.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1518/RA012
(ii)Name of the EIA Consultant M/s. Precitech Laboratories Pvt. Ltd.
(iii)Address C5/27, 1st floor, Bhanujyot complex,GIDC char rasta, Vapi, Gujarat.
(iv)Mobile No. 9925008673
(v)Landline No. 0260
(vi)Email Id rhb@precitechlab.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 05 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVipan Kalra
DesignationCMD
Name of Company (Applicant Name should not be given here)MADURA CARBON INDIA LTD
AddressSurvey No. 3705, 3708, 3719, 3725, 3738, 4108, 4110, 4318, Village- Karanj, Taluka- Umbergaon, Dist.- Valsad, Gujarat