Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Shree Renuka Sugars Limited., Expansion of distillery for manufacture of ethanol under EBP programe and expanding distillery capacity from 120 KLD to 500 KLD
(b)Name of the Company / Organisation SHREE RENUKA SUGARS LTD
(c)Registered Address R.S. No. 367/1, Munoli Village, Saundatti Taluk, Belgaum District.,,Belgaum,Karnataka-591117
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Govind Misale
(b)Designation (Owner/ Partner/ CEO) vice president
(c)Address Unit I, RS no. 367/1, Munoli Village, Soundatti Taluk,,Saundatti,Belgaum,Karnataka-591117
(d)Pin code 591117
(e)E-mail govind.misale@renukasugars.com
(f)STD Code. 8330(f)Telephone No. 278700
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity
(b)Category B2
   Reason for Applying at Ministry Other
   Other Reason for Applying at Ministry Applicability as per MoEF Notification No. S.O. 345(E) dated 17 January 2019 under EBP programe
(c)Proposal Number IA/KA/IND2/134412/2018
(d)Master Proposal Number(Single Window) SW/134404/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey R.S.No.367/1 Munoli Village, Saundatti Talu
(b)Pincode 591117
(c)Bounded Latitudes (North)
From
Degree 15.858129
Minutes
Second
From
Degree 15.858183
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 75.1041
Minutes
Second
From
Degree 75.1067
Minutes
Second
(e)Survey of India Topo Sheet No. D43D1
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 622
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/08/2002-IAII(I)
(c)Date of Issue of TOR 17 Nov 2018
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 01 Feb 2020
(c)Date of Issue of EC 28 Dec 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As per Notification S.O. 345(E) dated 17 January 2
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bangalore
(iii)Letter No. EP/SEIAA/12.1/99/KAR
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Feb 7 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Expansion of distillery120380500Kilo Litre per Day(KLD)Road
(2.)Captive power plant01818Mega Watt(MW)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Captive power plant018 MW18 MWto produce power from steam generation from incinerator boiler
(2.)Distillery plant120 KLD380 KLD500 KLDTo manufacture ethanol under EBP programe
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 04 Aug 2016
(iv)Valid Upto 30 Jun 2021
(v)File No. AWH-300705
(vi)Application No. PCB ID 10312
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 380
(b) Funds Allocated for Environment Management (Capital) (in Crores) 12.45
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 4
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 3.5
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1456
(b)Existing quantity of raw material/fuel 460
(c)Total quantity of raw material/fuel 1916
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Molasses as raw material for distillery632280Tons per AnnumSugar factory of SRSLPipe Conveyor0.1 OthersOwn facilityCopy of Linkage
(2.)Sugarcane Juice537900Kilo Litre per DaySugar factory of SRSLPipe Conveyor0.1 OthersOwn facilityCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Jan 2018 To 31 Mar 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube91.6768.2491.64100
(2.)PM2.5Micro Gram per Meter Cube58.2832.2357.0760
(3.)SO2Micro Gram per Meter Cube5.344.284.7980
(4.)NOxMicro Gram per Meter Cube10.639.0910.5980
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.556.56.58.5
(2.)Chloridesmg/l177272501000
(3.)Heavy MetalsIronmg/l2.750.111
(4.)TSSmg/l0000
(5.)TDSmg/l8602305002000
(6.)Fluoridemg/l0.840.2711.5
(7.)Total Hardnessmg/l465121200600
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l7.56.5C
(2.)CODmg/l1210C
(3.)BODmg/l42C
(4.)pHmg/l8.26.77C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))74.149.975
(2.)Leq(Night)A-weighted decibels(dB(A))694870
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.226.46
(2.)P(Phosphorus)Kilogram per hectare10275
(3.)K(Potassium)Kilogram per hectare15599
(4.)Electric ConductivityOthersdS/m0.40.1
(5.)N(Nitrogen)Kilogram per hectare11583
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 25 To 300
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 30 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface25631.4Copy of Permission LetterPipelineJack WellID 18 MPS 9927 May 1999400
(2.)Surface25633.5Copy of Permission LetterPipelineJack WellID 18 MPS 9904 Dec 20194000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic5460Soak pit and septic tankOtherssoak pit054
(2.)Distillation25813000MEE and Incineration boilerReuse within the Plant & Recycling2581
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2635
(b)Total Discharged Water (Kilolitre per Day) 54
(c)Total Reused Water (Kilolitre per Day) 2581
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)16.8Tons200RoadAuthorized Recyclers
(2.)Boiler ashBottom Ash2160Tons200RoadOtherspress mud and given to farmers
(3.)ETP sludge from ETPOthersETP waste60Tons1RoadOtherscomposting
(4.)yeast sludgeIndustrial Waste18Tons1RoadOtherscomposting
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube57.93100.2558.2060
(2.)PM10Microgram per Meter Cube91.670.10.4292.1100
(3.)NOxMicrogram per Meter Cube10.630.16.321780
(4.)SO2Microgram per Meter Cube5.5100.96.580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boiler 65 TPHConcentrated spent wash and coal or baggase853.23PM10150
(2.)Boiler 65 TPHconcentrated spent wash and coal853.23PM10150
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 18000
(b)Source Captive Power generation from Incineration boilers
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) Ni
(e)Stack Height (in m) 85
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 42.16
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 42.16
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 16318.98
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 2596.41
(e)Settlements (ha.) 999.36
(f)Industrial (ha.) 42.16
(g)Forest (ha.) 8257.77
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 28214.68
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area22.13Total ground coverage area
(2.)Green belt14.34
(3.)OthersHard paved area (including internal roads)5.6
Total (ha.) 42.07
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0No Critically polluted areas within 10km
(2.)ESAsNA0No ESAs area within 10 km radius
(3.)Wildlife CorridorsNA0No wildlife corridors within 10 km radius
(4.)WLSNA0No WLS areas within 10 km radius
(5.)NPANA0No NPA area within 10 km
(6.)ESZsNA0No EZs areas within 10 km radius
(7.)CorridorsNA0No Corridors within 10 Km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA3Reserved forest open scrub from north west to south east
(2.)Archaeological SitesNA0No Archaeologicaal sites within 10km
(3.)Defence InstallationsNA0No Archaeologicaal sites within 10km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 42.16
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 100
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt35.44035.44
(2.)Percentage of Total Project Area34034
(3.)Funds Allocated8020100
(4.)No. of Plants2100020021200
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Socialmanpower generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1992/IA0051
(ii)Name of the EIA Consultant Samrakshan
(iii)Address SwastikManandi Arcade,F-4, 1st Floor,S.C. Road, Sheshadripuram,(Opp. Sheshadripuram Police Station),      Bangalore- 560 020, INDIA Phone : 080-23460102
(iv)Mobile No. 9845381819
(v)Landline No. 0802346010
(vi)Email Id samrakshanblr@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 24 Jul 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) In S. No. 6 of Form 2, details of EC mentioned NIL, however it is case of expansion. Kindly upload the EC in this section as per form-2. (ii) All old CTOs not uploaded to verify the violation, if any done by PP. (iii) Please upload the certificate of MOPNG as per MoEFCC notification dated 17.01.2019 (vii) The Period of Base Line Data Collection has been submitted during January to March however it should be ether December –February, March to May and October – December (viii) In S. No. 2 of Form 2, the Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency has not been submitted. (iv) In view of the above, PP/Consultant are requested to revise the application and accordingly revise the Form 2 alongwith Report. The Reports shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submit the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. 07 Jan 2020
2.NAThe correction have been made as per the instruction received 01 Feb 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterOur proposal for expansion of distillery capacity, for manufacture of ethanol, from 120 KLD to 500 KLD and addition of captive power plant of 18 MW under EBP programme was appraised by EAC in its 18th meeting on 13.04.2020. EAC had made certain observations. We are herewith uploading point-wise compliance/response to the EAC observations. We request you to kindly consider our proposal for recommendation for issue of Environmental Clearance. 01 Sep 2020
2.NA

                                          

24 Apr 2020

Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantGovind Misale
Designationvice president
Name of Company (Applicant Name should not be given here)SHREE RENUKA SUGARS LTD
AddressR.S. No. 367/1, Munoli Village, Saundatti Taluk, Belgaum District.
Print