1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Setting up 500 KTA Propane Dehydrogenation unit integrated with Polypropylene Unit | (b)Name of the Company / Organisation | GAIL INDIA LIMITED | (c)Registered Address | GAIL INDIA LIMITED,GAIL JUBILEE TOWER,PLOT NO B-35-36 SECTOR-1,NOIDA,UP,,Gautam Buddha Nagar,Uttar Pradesh-201301 | (d)Legal Status of the Company | Central PSU | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | MISSULA V S Murthy | (b)Designation (Owner/ Partner/ CEO) | ChiefManager | (c)Address | GAIL INDIA LIMITED,GAIL JUBILEE TOWER,PLOT NO B-35-36 SECTOR-1,NOIDA,UP,,Gautam Buddha Nagar,Gautam Buddha Nagar,Uttar Pradesh-201301 | (d)Pin code | 201301 | (e)E-mail | mvsmurthy@gail.co.in | (f)STD Code. | 120(f)Telephone No. | 2446400 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(c) Petro-chemical complexes (industries based on processing of
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/MH/IND2/69404/2017 | (d)Master Proposal Number(Single Window) | SW/134386/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | A-1, Usar Industrial Area | (b)Pincode | 402203 | (c)Bounded Latitudes (North) | | From | | Degree | 183541 | Minutes | | Second | | From | | Degree | 183632 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 725740 | Minutes | | Second | | From | | Degree | 725847 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | E43G14 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 83 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 10 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Maharashtra | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Raigad | Alibag | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/464/2017-IA-II(I) | (b)Date of Apply of TOR | 15 Sep 2017 | (c)Date of Issue of TOR / Standard ToR | 26 Oct 2017 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 21 Jun 2019 | Distance of Public Hearing Venue from the Proposed Project : | 3 |
| Ganesh Mangal Karyalaya, Sahan Bypass Road, Alibag Roha Road, Sahan | State : | Maharashtra | District : | Raigad | Tehsil : | Alibag | Village : | Sahan |
| 500 | Employment to Project Affected Persons (PAP), Land Compensation to PAP, Employment to Locals, Employment after imparting training / Skill development program, CSR, Insurance to Nearby Villagers | Others | Additional District Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Propane Dehydrogenation and Polypropylene Units | Polypropylene production | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Polypropylene | 500000 | Tons per Annum | | Road | | (2.) | C4 LPG | 25000 | Tons per Annum | | Others | ROAD/ PIPELINE | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 07 Jan 2020 | (iv)Valid Upto | 31 Aug 2020 | (v)File No. | 2001000585 | (vi)Application No. | 0000075720 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 6707.67 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 10.25 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 20.77 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 1.38 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 601000 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 601000 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Propane | 601000 | Tons per Annum | | JNPT | Others | Pipeline | 58 | Linkage | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 15 Dec 2017 To 15 Mar 2018 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 35 | 22 | 32.5 | 60 | (2.) | NOx | | Micro Gram per Meter Cube | 17.8 | 13.0 | 16.5 | 80 | (3.) | PM10 | | Micro Gram per Meter Cube | 73 | 52 | 67.8 | 100 | (4.) | SO2 | | Micro Gram per Meter Cube | 15.7 | 10.5 | 14.7 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TDS | | | mg/l | | 416 | 269 | 500 | 2000 | (2.) | TSS | | | mg/l | | 4 | 4 | 15 | 20 | (3.) | Total Hardness | | | mg/l | | 195 | 110 | 200 | 600 | (4.) | Chlorides | | | mg/l | | 107 | 21 | 250 | 1000 | (5.) | Heavy Metals | | Lead | mg/l | | 0.00 | 0.00 | 0.01 | 0.01 | (6.) | pH | | | NA | | 7.75 | 7.42 | 6.5 | 8.5 | (7.) | Fluoride | | | mg/l | | 0.5 | 0.01 | 1.0 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 8.2 | 7.3 | C | (2.) | COD | | mg/l | | 360 | 245 | C | (3.) | DO | | mg/l | | 3.7 | 2.7 | C | (4.) | BOD | | mg/l | | 154 | 27 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 42.7 | 40.4 | 45 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 52.1 | 50.2 | 55 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 134 | 56 | (2.) | K(Potassium) | Kilogram per hectare | | 364 | 175 | (3.) | pH | | | 6.77 | 6.25 | (4.) | P(Phosphorus) | Kilogram per hectare | | 23 | 7.18 | (5.) | Electric Conductivity | Others | µmhos/cm | 460 | 51.3 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 5 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 5 To 2 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | MIDC | 11520 | 23 | Copy of Permission Letter | Pipeline | | Others | Pipeline from MIDC | NO/EE(Alibag)/B14566/of2019 | 28 Mar 2019 | 15600 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Cooling tower blowdown | 2112 | 2112 | RO based recycle plant | Reuse within the Plant & Recycling | | 2112 | | (2.) | Process units | 360 | 360 | Effluent treatment plant+RO based recycle plant | Reuse within the Plant & Recycling | | 360 | | (3.) | Sewage water | 192 | 192 | Sewage treatment plant | Green Belt Renewal Plant | | 192 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 2664 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 2664 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Spent catalysts/ Adsorbents | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 537.5 | Tons | 80 | Road | | Authorized Recyclers | | (2.) | Inert grain/ Alumina balls | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 15 | Tons | 80 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | Support balls | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 20 | Tons | 80 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | NOx | | Microgram per Meter Cube | 16.5 | 4 | 1.55 | 18.06 | 80 | (2.) | PM10 | | Microgram per Meter Cube | 67.8 | 0 | 0 | 67.9 | 100 | (3.) | SO2 | | Microgram per Meter Cube | 14.7 | 4 | 0.13 | 14.84 | 80 | (4.) | PM2.5 | | Microgram per Meter Cube | 32.5 | 0 | 0 | 32.6 | 60 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Reactor Charge Heater | Fuel Gas | 55 | 1.8 | SO2 | | 0.36 | (2.) | Reactor Charge Heater | Fuel Gas | 55 | 1.8 | NOx | | 4.17 | (3.) | Air Heater | Fuel Gas | 70 | 6 | SO2 | | 1.0 | (4.) | Air Heater | Fuel Gas | 70 | 6 | NOx | | 20.28 | (5.) | Utility Boiler | Fuel Gas | 60 | 1.3 | SO2 | | 0.30 | (6.) | Utility Boiler | Fuel Gas | 60 | 1.3 | NOx | | 3.33 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 156000 | (b)Source | State Grid | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1 | (e)Stack Height (in m) | 10 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 130 | Total Land (ha.) | 130 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 130 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Other than Industrial landuse | 0 | Total (ha.) | 130 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 87 | | (2.) | Green belt | | 43 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | NO | 0 | Not Applicable | (2.) | WLS | No | 0 | Not Applicable | (3.) | NPA | No | 0 | Not Applicable | (4.) | ESAs | No | 0 | Not Applicable | (5.) | ESZs | No | 0 | Not Applicable | (6.) | Corridors | No | 0 | Not Applicable | (7.) | Wildlife Corridors | No | 0 | Not Applicable | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | No | 0 | Not Applicable | (2.) | Forest | | Bherse RF | 2.5 | Open jungle | (3.) | Defence Installations | | No | 0 | Not Applicable | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 130 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Not Applicable | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Kundalika River | (ii)Direction of Water Bodies in Buffer Area | South | (iii)Distance of Water Bodies in Buffer Area | 7 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 230 | (c)Temporary Employment- During Construction | 2500 | (d)Temporary Employment- During Operation | 100 | (e)No. of working days | 333 | (f)Total Manpower | 2830 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 43 | (b)Percentage of Total Project Area | 33.08 | (c)No. of Plants to be Planted | 64500 | (d)Funds Allocated for Plantation | 25000000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Employment Generation | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA 0041 | (ii)Name of the EIA Consultant | Engineers India Limited | (iii)Address | Engineers India Limited, Research & Development Complex, Sector-16 (on NH48), Gurgaon | (iv)Mobile No. | 9818669575 | (v)Landline No. | 0124380203 | (vi)Email Id | jk.joshi@eil.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 18 May 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | (i) On perusal it is noted that the Ministry has earlier granted EC, however PP has not uploaded the certified compliance report of RO MoEFCC.
(ii) Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents. Also issues raised during public hearing, response by the project proponent, action plan with budgetary allocation has not been submitted. Kindly upload the requisite documents. Form 2 (S.no. 7.1)
(iii) Action Plan with budgetary provisions and time lines on the issues raised during PH has not uploaded in Form 2. Kindly upload the action plan in S.No. 7.1 of Form 2 alongwith other requisite details.
(iv) PP mentioned zero incremental value for PM10 & PM2.5. Air Quality Impact Prediction mentioned (18.1 of form 2) is inadequate kindly correct it.
(v) All old CTOs not uploaded to verify the violation, if any done by PP.
(vi) Effluent treatment mechanism with plan for Zero Liquid Discharge needs to be submitted.
(vii) Proposed Green belt development programe along-with time line and budgetary allocation needs to be provided
(viii) Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted (13.1 of form 2)
(ix) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Report. The EIA/EMP Report shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submitted the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. | 24 Mar 2020 | 2. | NA | The correction have been made as per the instruction received | 15 Apr 2020 | 3. | NA | 1. Please read the earlier EDS sought by the Ministry. The matter was again examined and noted that PP has not revised the Form 2 and not uploaded the requisite information.
2. It is pertain to mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action.
3. It is also mentioned that after acceptance the Form 2 and EIA/EMP report can not be revise. Therefore, PP/Consultant is again requested to kindly do needful. | 22 Apr 2020 | 4. | NA | 1. Please read the earlier EDS sought by the Ministry. The matter was again examined and noted that PP has not revised the Form 2 and not uploaded the requisite information.
2. It is pertain to mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action.
3. It is also mentioned that after acceptance the Form 2 and EIA/EMP report can not be revise. Therefore, PP/Consultant is again requested to kindly do needful. | 22 Apr 2020 | 5. | NA | 1. Please read the earlier EDS sought by the Ministry. The matter was again examined and noted that PP has not revised the Form 2 and not uploaded the requisite information.
2. It is pertain to mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal necessary action.
3. It is also mentioned that after acceptance the Form 2 and EIA/EMP report can not be revise. Therefore, PP/Consultant is again requested to kindly do needful. | 22 Apr 2020 | 6. | NA | The correction have been made as per the instruction received | 23 Apr 2020 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | We are submitting replies to ADS as desired by EAC. Kindly consider our proposal for environmental clearance. | 06 Jul 2020 | 2. | NA |
The EAC during deliberations noted that the proposed project for production of Polypropylene through Propane Dehydrogenation (PDH) unit is new technology to the nation. The Committee noted that the fresh water requirement and effluent management proposed requires revision. The Committee also showed its displeasure over the poor presentation of the socio-economic status of the region.
The Committee after detailed deliberations desired for additional information/inputs in respect of the following:
(i). Public hearing issues, action plan along with budget provisions.
(ii). Revised water balance with improvement in evaporation loss.
(iii). Plan for ZLD along with MEE/modern technology.
(iv). Plan for need based health programme.
(v). Socio-economic status report of the study area
(vi). Detailed CER plan along with action plan for drinking water facility for the people.
(vii). Provision for employment to the local people.
(viii). In view of several recent chemical accidents occurred in various parts of the country, the risk studies need to be carried out basedon the following protocolusing 3 D modelling which incorporates dispersion of vertical component vital for developing&placing accident prevention programin place:
• Material Safety Data Sheet (MSDS/MDS)
• Hazard Identification, Consequence analysis in terms of effect / threat zone distances.
• Risk need to be carried out for Small, Medium, Larger and Catastrophic ruptures /leak and to be modeled as representative cases.Frequency/ Probability of leak per year.
• Risk needs to be quantified interms of Individual Risk Contours
• Societal risk
• F-N curves to assess against risk acceptance criteria (HSE,UK etc.).
(ix). Plan for installation of solar power and utilization in the plant
(x). Details of wildlife sanctuary/ESA within 10 km of the project site.
The proposal was therefore deferred for the needful. | 29 Jun 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | MISSULA V S Murthy | Designation | ChiefManager | Name of Company (Applicant Name should not be given here) | GAIL INDIA LIMITED | Address | GAIL INDIA LIMITED,GAIL JUBILEE TOWER,PLOT NO B-35-36 SECTOR-1,NOIDA,UP |
|