Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Basantpur Tapin Coking coal washery
(b)Name of the Company / Organisation Central Coalfields Limited
(c)Registered Address DARBHANGA HOUSE, CCL, RANCHI,,Ranchi,Jharkhand-834029
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sanjeev Kumar
(b)Designation (Owner/ Partner/ CEO) Nodal Officer
(c)Address Basantpur-Tapin Washery, Village-Basantpur, Post- Kedla, District- Ramgarh, Jharkhand-825325,,Patratu,Ramgarh,Jharkhand-825325
(d)Pin code 825325
(e)E-mail btwashery@gmail.com
(f)STD Code. 6546(f)Telephone No. 232630
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity2(a) Coal washeries
Minor Activity
(b)Category A
(c)Proposal Number IA/JH/CMIN/77450/2018
(d)Master Proposal Number(Single Window) SW/133921/2019
(e)EAC concerned (for category A Projects only) Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 23,24, 25,26,27,28,29,30 31,32, 33 etc.
(b)Pincode 825325
(c)Bounded Latitudes (North)
From
Degree 23.82
Minutes
Second
From
Degree 23.83
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 85.56
Minutes
Second
From
Degree 85.567
Minutes
Second
(e)Survey of India Topo Sheet No. F45B9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 356
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 600
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Jharkhand
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)JharkhandRamgarhNo Data
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11015/97/2018-IA-II(M)
(b)Date of Apply of TOR 01 Sep 2018
(c)Date of Issue of TOR / Standard ToR 07 Oct 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 Sep 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :09 Oct 2019
Distance of Public Hearing Venue from the Proposed Project :0.5
Shiv Mandir in Basantpur Village, Post-Kedla Dist- Ramgarh
State :Jharkhand
District :Ramgarh
Tehsil :No Data
Village :Basantpur
250ssues regarding pollution control measures, ground water, surface water, employment generation, CSR activities, plantation etc raisedOthersAdditional Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Washery4 MTPA in an area of 32.03 HaThis washery is proposed on BOO Basis.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Rejects1496000Tons per AnnumRoad
(2.)Washed Coal (Clean)1516000Tons per AnnumRoad,Rail
(3.)Washed Coal (Power)988000Tons per AnnumRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 360
(b) Funds Allocated for Environment Management (Capital) (in Crores) 6.85
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 5.40
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.086
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 4000000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 4000000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Raw coal350000Tons per AnnumTapin South OCPRoad12 LinkageCopy of Linkage
(2.)Raw coal1420000Tons per AnnumTapin North OCPRoad15 LinkageCopy of Linkage
(3.)Raw coal1430000Tons per AnnumParej East OCPRoad9 LinkageCopy of Linkage
(4.)Raw coal800000Tons per AnnumJharkhand OCPRoad8 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 18 Mar 2019 To 03 Jun 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube69.430.769.13300
(2.)NOxMicro Gram per Meter Cube9.96.29.7120
(3.)PM2.5Micro Gram per Meter Cube43.720.543.3460
(4.)SO2Micro Gram per Meter Cube24.811.224.7120
    14.2.     No. of Ground Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)OtherscolorOthersHazen11515
(2.)OthersAlkalinity as CaCO3mg/l4228200600
(3.)OthersCopper (As Cu)mg/l0.010.010.051.5
(4.)OthersCopper (As Cu)mg/l0.010.010.051.5
(5.)OthersDetergentmg/l0.050.050.21
(6.)OthersNitratemg/l3.883.234545
(7.)OthersCopper (As Cu)mg/l0.010.010.051.5
(8.)OthersMercury (As Hg)mg/l0.000.000.000.00
(9.)pHOthers-6.646.616.68.5
(10.)TSSmg/l0000
(11.)Total Hardnessmg/l6452200600
(12.)Chloridesmg/l6.895.912501000
(13.)Heavy MetalsFemg/l2.760.10.30.3
(14.)OthersOdourOthers-0000
(15.)OthersPhenolic Compoundsmg/l0.000.000.000.00
(16.)OthersPhenolic Compoundsmg/l0.000.000.000.00
(17.)OthersPhenolic Compoundsmg/l0.000.000.000.00
(18.)OthersResidual Chlorinemg/l0.050.050.21
(19.)OthersCynidemg/l0.010.010.050.05
(20.)OthersAluminum (As Al)mg/l0.000.000.030.2
(21.)OthersCadmium (As Cd)mg/l0.000.000.000.00
(22.)OthersTurbidityOthersNTU0.10.115
(23.)OthersCopper (As Cu)mg/l0.010.010.051.5
(24.)OthersLead (As Pb)mg/l0.310.280.010.01
(25.)OthersManganese (As Mg)mg/l0.050.050.10.3
(26.)OthersSelenium (As Se)mg/l0.000.000.010.01
(27.)OthersFeacal ColiformOthersMPN/100 mL0000
(28.)TDSmg/l2662465002000
(29.)Fluoridemg/l0.390.3211.5
(30.)OthersTemperatureOthersDegree centigrade25.925.93737
(31.)OthersTasteOthers-0000
(32.)OthersCalcium as Camg/l14.4213.3275200
(33.)OthersCalcium as Camg/l14.4213.3275200
(34.)OthersSulphatemg/l11.579.83200400
(35.)OthersHexavalent Chromium as Cr+6mg/l0.010.0100
(36.)OthersArsenic (As As)mg/l0.050.030.010.05
(37.)OthersBoron (As B)mg/l0.10.10.51
(38.)OthersCopper (As Cu)mg/l0.010.010.051.5
(39.)OthersCopper (As Cu)mg/l0.010.010.051.5
(40.)OthersCopper (As Cu)mg/l0.010.010.051.5
(41.)OthersCopper (As Cu)mg/l0.010.010.051.5
(42.)OthersZinc (As Zn)mg/l0.20.2515
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l00C
(2.)OthersTemperature°COthers°C33.429.5C
(3.)pHOthers-7.597.48C
(4.)OthersSulphatemg/l124.2120.5C
(5.)OthersCalcium as Camg/l65.764.92C
(6.)OthersCadmium (as Cd)mg/l0.000.00C
(7.)OthersArsenic (as As)mg/l0.010.01C
(8.)OthersMercury (as Hg)mg/l0.010.01C
(9.)OthersZinc (as Zn)mg/l0.20.2C
(10.)OthersCynidemg/l0.010.01C
(11.)OthersTotal ColiformOthersMPN/100ml00C
(12.)OthersColorOthersCU11C
(13.)OthersChloridemg/l36.532.52C
(14.)OthersFluoridemg/l124121C
(15.)OthersMagnesium as Mgmg/l54.453.5C
(16.)OthersManganese (as Mn)mg/l0.50.5C
(17.)OthersTotal Dissolved Solidsmg/l864759C
(18.)OthersHexavalent Chromium as Cr+6mg/l0.010.01C
(19.)OthersCopper (as Cu)mg/l0.40.4C
(20.)OthersTotal Suspended Solidsmg/l2621C
(21.)OthersNitratemg/l2.742.56C
(22.)OthersOil & Greasemg/l11C
(23.)OthersTotal Hardness CaCO3mg/l388388C
(24.)OthersLead (as Pb)mg/l0.010.01C
(25.)OthersIRONmg/l3.331.32C
(26.)OthersSelenium (as Se)mg/l0.000.00C
(27.)DOmg/l2.742.56C
(28.)BODmg/l42.4C
(29.)OthersOdourOthers-00C
(30.)OthersPhenolic Compoundsmg/l0.000.00C
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))72.948.975
(2.)Leq(Night)A-weighted decibels(dB(A))66.940.170
    14.5.     No. of Soil Sample Monitored locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram44.628.56
(2.)Electric ConductivityOthersµS/cm4742.59
(3.)K(Potassium)Kilogram per hectare183.26118.26
(4.)pHOthers-7.816.34
(5.)P(Phosphorus)Kilogram per hectare2.052.02
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10.2 To 3.0
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 7.93 To 1.78
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater5553.75Copy of Permission LetterPipelineOthersPumping21-4/642/JH/IND/202001 Apr 2020730
(2.)Surface1753.75Copy of Permission LetterPipelineOthersOld quarry/PondD/KW/PO/BTW/20-21/62517 Jul 2020730
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Washery985610000Effluent Treatment and water recovery from washed coal (Clean and Power) and rejects. All discharged water 9856 cum per day is reused includes 9576 cum per day actually reuse and water lost due to evaporation and other losses as 280 cum per day.Reuse within the Plant & Recycling,Green Belt Renewal Plant9856
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 9856
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 9856
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)rejectOthersreject5000Tons0RoadOthersSale
(2.)Burnt OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)20Kilolitre12RoadAuthorized Recyclers
(3.)BatteryHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.2Tons5RoadAuthorized Recyclers
(4.)Oily Waste CottonHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2Tons5RoadOthersBurning and landfills
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube23.50.240.1823.6980
(2.)PM2.5Microgram per Meter Cube29.30.241.7031.0160
(3.)PM10Microgram per Meter Cube39.70.245.6445.35100
(4.)NOxMicrogram per Meter Cube9.30.243.8413.1580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)nilnil00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 8000
(b)Source Basantpur Substation
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 32.03
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0.44
    Total Land (ha.) 32.47
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 30.93
(b)Waste/Barren Land (ha.) 0.70
(c)Grazing/ Community Land (ha.) 0.40
(d)Surface Water Bodies (ha.) 0.00
(e)Settlements (ha.) 0.00
(f)Industrial (ha.) 0.00
(g)Forest (ha.) 0.00
(h)Mangroves (ha.) 0.00
(i)Marine Area (ha.) 0.00
(j)Others (ha.) : 0 0.00
    Total (ha.) 32.0300
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant14.19
(2.)Green belt9.39
(3.)OthersSlurry Pond, Reject dumping yard8.45
Total (ha.) 32.03
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsNA10No ESZs Within 10 KM
(2.)Critically Polluted AreaNA10No Critically Polluted Area Within 10 KM
(3.)NPANA10No NPA Within 10 KM
(4.)ESAsNA10No ESAs Within 10 KM
(5.)CorridorsNA10No Corridors within 10 KM
(6.)Wildlife CorridorsNA10No Wildlife Cooridors Within 10 KM
(7.)WLSNA10No WLS Within 10 KM
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA10No Forest
(2.)Archaeological SitesNA10No Archaeological Sites within 10 km
(3.)Defence InstallationsNA10Defence Installation within 10 km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 32.03
(b)Land yet to be acquired(Ha) 0.00
(c)Status of Land acquisition if not acquired 0.00
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species PEACOCK (PEAFOWL)
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 32 Lakhs
(iii)Period of Implementation 5
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Chutua Nalla
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 0.6
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 30
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 20
(d)Temporary Employment- During Operation 50
(e)No. of working days 330
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Total Area of Green Belt 9.39
(b)Percentage of Total Project Area 28.92
(c)No. of Plants to be Planted 70800
(d)Funds Allocated for Plantation 8139690
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalThe washery will produce environment friendly clean coal to minimize the pollution levels. It will reduce volume of coal transportation which will reduce pollution.
(2.)FinancialThe washery will produce metullurgical grade coal to be used in steel plants thus resulting in saving to national exchequer by reduction in imports.
(3.)SocialThis project will create employment opportunities both for skilled and semi skilled persons in the area. Business opportunity in secondary & Tertiary sectors will increase. The proposed washery project will also bring about enhanced socio-economic benefits to local population due to expenditure in CSR activities.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)Not Applicable as it is washeryMajor
2.
Mine Capacity in ROM (Run of Mine) 0
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. CS/BM/483/2020/153
(b)Date of Approval 25 Feb 2020
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department CCL BOARD
(e)Approved Mining Lease Area 32.03
(f)Approved Capacity 4
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 0.00
(b)Mineable Reserves (Million Ton) 0.00
(c)Extractable Reserves(Million Ton) 0.00
(d)Percent(%) of Extraction 0.00
(e)Grade of Coal /Ore /Mineral 0.00
(f)Stripping Ratio 0 : 0
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) NA
(i)Mining Method Opencast
(j)Life of Mine (Years) 18
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area Yes
(c)No. of crushers 3
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)11000 CRUSHING OF -1000MM SIZE COAL DOWN TO -200MM SIZEIN PRIMARY TWIN SHAFT SIZER
(2.)21000 CRUSHING OF -200MM SIZE COAL DOWN TO -50MM SIZE IN SECONDARY TWIN SHAFT SIZER
(3.)31000 CRUSHING OF +13MM SIZE FRACTION DOWN TO 13MM IN TERTIARY CRUSHER AND MIXING WITH -13MM SIZE FRACTION,
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 32.03
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof CBA aquired SO 2082 30.06.1981 & SO 981(E) dtd. 22
(c)Whether Lease Deed Executed ? No
(i)Reason thereof CBA aquired SO 2082 30.06.1981 & SO 981(E) dtd. 22
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof CBA aquired SO 2082 30.06.1981 & SO 981(E) dtd. 22
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
(v)No. of year back fill up
(b) Details of Internal Dumps:
(i)No. of Internal Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare)
(b)Depth (in meter)
(c)Volume (in Million Cubic meter)
12.
Details of Quarry:
(a)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 0
13.
Details of Transportation:
(a)In Pit/Underground to Surface 0
(b)Surface to Siding/Loading Rail and Road
(c)Transportation / Conveyor Details -
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND30.93030.93
(2.)FOREST LAND000
(3.)WASTE LAND0.7000.7
(4.)GRAZING LAND0.4000.4
(5.)SURFACE WATER BODIES000
(6.)SETTLEMENTS000
TOTAL32.03032.03
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY0000
(2.)VIRGIN AREA0000
(3.)TOP SOIL STORAGE0000
(4.)GREEN BELT280028
(5.)BUILT UP AREA (COLONY/OFFICE)0022
(6.)Otherroad etc002.032.03
(7.)ROADS0000
(8.)EXTERNAL OB DUMPS0000
(9.)INTERNAL OB DUMPS0000
TOTAL2804.03032.03
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 0
(d)Safety Zone(in hectare) 0
(e)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 0
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 0
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)202000400
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA0092
(ii)Name of the EIA Consultant CENTRAL MINE PLANNING AND DESIGN INSTITUTE LIMITED
(iii)Address Central Mine Planning and Design Institute Limited, Gondwana Place, Kanke Road, Ranchi, Jharkhand
(iv)Mobile No. 8987788960
(v)Landline No. 0651223005
(vi)Email Id gmenv.cmpdi@coalindia.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 01 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPls clarify or justify the reason for the following points a. Area of the project as mentioned in ToR granted by Ministry and proposal submitted in Form #2 Sr. No. 8.1 and in EIA Report is not similar. b. Pdf copy of application of CGWA clearance is enclosed in surface water permission. c. Details of distance of GLC is not filled in Form # 2 d. Overall plan of utilization of washery rejects with quantity shall be provided e. Data of effluent Analytical Result at table 3.3.4 (EIA Report) is mentioned as BOD-4 mg/l & COD-10 mg/l which is too lower for any treated effluent from washery plant f. As per guidelines, Ambient Air Quality/ Baseline data collected shall be measured within 10 km of buffer zone and monitoring stations should be selected considering the representation of all buffer zone. However in this case, distance of monitoring ranges from 0.1 km to 0.24 km which clearly does not represent the buffer zone. Also, Bokaro river lies in 10 km buffer zone. Why surface water quality of bokaro river was taken for analysis. g. Wild life conservation plan for presence of schedule- I species (all species) with fund allocated as approved by PCCF h. As per ToR, Ground water permission from CGWA has to be obtained. i. Environmental Impact Assessment for transportation of washed coal/rejects is not included in EIA Report j. Water Balance Diagram with quantity of usage at each points should be submitted. k. Incorrect details filled in Form#2 on PARIVESH Portal regarding Water Requirement at Sr. No. 15- Water Quantity required is 555 & 175 however details in EIA report and ToR granted varies. Also, uints are not mentioned about quantity a. Quantity of wastewater generated is 9856 kl/day wherein in EIA Report it is 600 m3/hr. b. Form # 2 Sr. No. 18.1- Baseline concentration entered is not matching with PM10/PM2.5 data given in EIA/EMP. Kindly correct the above mentioned deficiencies in the Report and upload the correct documents so that the proposal can be appraised before the EAC. PP/Consultant has to upload the correct information. 22 May 2020
2.NAThe correction have been made as per the instruction received 31 Jul 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterThe ADS have been raised inadvertently and as such it may be considered accodingly by MoEF&CC. 09 Feb 2021
2.NAthe proposal has been deferred by EAC due to shortcomings in EIA-EMP report. Please refer minutes of meeting for full compliance of observation of EAC. 09 Feb 2021
3. ADS Reply LetterRespected Sir, The compliance in respect of the information sought by EAC is being submitted herewith for consideration please. 08 Jan 2021
4.NA

The EAC found several inconsistencies in the proposal & submission given by project proponent w.r.t traffic management, flora fauna, pollution mitigation measures, etc. Therefore, after deliberation, EAC deferred the proposal for want following information: 

        i.            Explore the possibility of laying conveyor belt for transportation of coal from nearest mine. PP shall provide the plan for reduction of number of trucks for transportation of coal and fleet to be redesigned.

      ii.            PP shall submit plan for utilization of water only from mine and no ground water shall be used.

    iii.            Plan of utilisation of washery rejects with MoU with FBC boilers/power plants as per the MoEF&CC notification.

    iv.            Impact of washery on nearby agricultural land and flora-fauna. Proper flora management plan needs to be prepared.

       v.            Proper Air pollution mitigation measures at site with installation of Continuous Ambient Air Quality Station during operation of project.

    vi.            Adherence to the compliance to Issues raised during Public Consultation with the timeline and budgetary provision.

  vii.            Fund allotment for greenbelt is too less and more fund should be allotted for developing peripheral plantation.

viii.            Distance of Chutuwa nallah/stream near washery and impact due to washery operations shall be presented.

    ix.            Land of dumping of rejects shall be reduced to keep the rejects only for 2 months and accordingly greenbelt land should be increased.

       x.            PP shall rework on the layout of washery so that coal storage area, crushing units and rejects storage area shall not be near the villages.

 

The proposal was deferred on above lines for compliance by project proponent

14 Oct 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSanjeev Kumar
DesignationNodal Officer
Name of Company (Applicant Name should not be given here)Central Coalfields Limited
AddressDARBHANGA HOUSE, CCL, RANCHI
Print