Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Fengel Crop Sciences (Unit –II)
(b)Name of the Company / Organisation FENGEL CROP SCIENCES(UNIT-II)
(c)Registered Address Survey no. 65/2, Village: Shemala, Tehsil: Gondal, District: Rajkot,,Rajkot,Gujarat-360311
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Chetanbhai Chhaganbhai Bhut
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Pratiksha, 18/11 Bhojraj Para, Gondal,,Gondal,Rajkot,Gujarat-360311
(d)Pin code 360311
(e)E-mail lab.fengelcrop@gmail.com
(f)STD Code. 2825(f)Telephone No. 223007
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/98969/2019
(d)Master Proposal Number(Single Window) SW/133401/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey No. 65/2
(b)Pincode 360311
(c)Bounded Latitudes (North)
From
Degree 22.03220
Minutes
Second
From
Degree 22.03282
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 70.7923
Minutes
Second
From
Degree 70.7939
Minutes
Second
(e)Survey of India Topo Sheet No. F42K16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 156
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 00
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratRajkotGondal
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/81/2019-IA-II(I)
(b)Date of Apply of TOR 12 Mar 2019
(c)Date of Issue of TOR / Standard ToR 13 Apr 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 Oct 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :08 Nov 2019
Distance of Public Hearing Venue from the Proposed Project :00
At Project Site of M/s. Fengel Crop Sciences (Unit-II), Survey No. 65/2
State :Gujarat
District :Rajkot
Tehsil :Gondal
Village :Shemla
45Priority to local employment, proper management of generated waste and effluent. Detailed Issue raised during the public hearing has already addressed along with budgetary provision & timelines in TabOthersResident Additional Collector and Additional District Magistrate-Rajkot
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)SS Vessel1.0 KL x 2 nos., 4.0 KL x 2 nos.
(2.)Vacuum Ejector2 nos.
(3.)Boiler2 TPH x 1 no.
(4.)Cooling Tower300 TR x 1 no.
(5.)Tray Dryer500 KG/cycle x 1 no.
(6.)Brine Chilling Unit50 TR x 1 no.
(7.)SS Reactor6.3 KL x 2 nos., 5.0 KL x 1 no.
(8.)SS Column0.6/9 m x 1 no.
(9.)Centrifuge48" x 1 no.
(10.)Fluidized bed dryer200 KG/hr x 1 no.
(11.)Condensers15 m3 x 3 nos., 10 m3 x 3 nos, 5 m3 x 3 nos.
(12.)D.G. set250 KVA x 1 no.
(13.)Tray Dryer500 KG/cycle x 1 no.
(14.)SFD200 kg/hrs x 1 no.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Azoxystrobin / Thiamethoxam / Acetamiprid / Imidacloprid / Chlorpyrifos300OthersMTPMRoad
(2.)Bio Pesticide / Bio Fertilizer100OthersMTPMRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 3.5
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.2
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.07
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.0
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 19340
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 19340
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)As per attached file19340Tons per AnnumLocal MarketRoad250 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 08
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube27.914.924.2180
(2.)PM10Micro Gram per Meter Cube74.752.669.62100
(3.)PM2.5Micro Gram per Meter Cube46.229.641.4660
(4.)SO2Micro Gram per Meter Cube25.812.421.4580
    14.2.     No. of Ground Water monitoring locations : 08
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l393297300600
(2.)Fluoridemg/l0.750.541.01.5
(3.)pHOtherspH Unit7.77.28.58.5
(4.)TSSmg/l1550000
(5.)TDSmg/l13319765002000
(6.)Chloridesmg/l6564922501000
    14.3.     No. of Surface Water monitoring locations : 02
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.26.0A
(2.)BODmg/l96A
(3.)CODmg/l2010A
(4.)pHOtherspH Unit7.637.52A
    14.4.     No. of Ambient Noise monitoring locations : 09
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))42.140.570
(2.)Leq(Day)A-weighted decibels(dB(A))54.351.875
    14.5.     No. of Soil Sample Monitored locations : 08
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOtherspH unit7.97.5
(2.)K(Potassium)Milligram per Kilogram326167
(3.)Electric ConductivityMillisiemens per Centimetre1.501.35
(4.)N(Nitrogen)Milligram per Kilogram191124
(5.)P(Phosphorus)Milligram per Kilogram5811
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 50 To 70
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 20
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater3200Copy of Permission LetterPipelineOthersBore well21-4/5573/GJ/IND/201923 Dec 201932
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic4.04.0Soak PitOthersSoak Pit04.0
(2.)Industrial3240ETP-RO-MEEOthersReuse in Utility302
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 36
(b)Total Discharged Water (Kilolitre per Day) 6
(c)Total Reused Water (Kilolitre per Day) 30
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Discarded ContainersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons100RoadAuthorized Recyclers
(2.)ETP sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)180Tons170RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Salt from MEEHazardous Waste (as per Hazardous and Other Waste Management rules 2016)132Tons170RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)Organic ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1260Tons170RoadOthersCHWIF or Co-processing at cement plant
(5.)Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1980Tons170RoadOthersCHWIF or Co-processing at cement plant
(6.)Discarded Liners/BagsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)6Tons25RoadAuthorized Recyclers
(7.)Used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.5Kilolitre25RoadOthersSelling to Registered Reprocess
(8.)Used CatalystHazardous Waste (as per Hazardous and Other Waste Management rules 2016)6Tons55RoadOthersby back to supplier for regeneration
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube19.831.410.4920.3280
(2.)PM10Microgram per Meter Cube64.051.411.4665.51100
(3.)SO2Microgram per Meter Cube16.981.410.4517.4480
(4.)PM2.5Microgram per Meter Cube37.381.411.4638.8560
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)D G set (250 KVA)HSD - 56 Liter / hr110.22OthersPM, SO2, NOx65 mg/Nm3, 30 mg/Nm3, 40 mg/Nm3
(2.)Spin flash Dryer (200 Kg/Hr)--110.30OthersPM15 mg/Nm3
(3.)Boiler - 2 Nos. (2 TPH each)Agro Briquetts - 5 TPD OR Furnace Oil - 2.0 KLD300.45OthersPM, SO2, NOx105 mg/Nm3, 40 mg/Nm3, 30 mg/Nm3
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 250
(b)Source PGVCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) DG Set (250 KVA, 1 No.)
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 00
(b)Private Land (ha.) 1.1962
(c)Government Land (ha.) 00
(d)Revenue Land (ha.) 00
(e)Other Land (ha.) 00
    Total Land (ha.) 1.1962
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 21426.4
(b)Waste/Barren Land (ha.) 5726.8
(c)Grazing/ Community Land (ha.) 00
(d)Surface Water Bodies (ha.) 542.3
(e)Settlements (ha.) 00
(f)Industrial (ha.) 00
(g)Forest (ha.) 00
(h)Mangroves (ha.) 00
(i)Marine Area (ha.) 00
(j)Others (ha.) : Built Up 3761.6
    Total (ha.) 31457.1
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.12
(2.)Green belt0.40
(3.)OthersRoad, parking, open area0.52
(4.)Built Up Area0.16Admin, Canteen, Storage area, ETP, Utility
Total (ha.) 1.2
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNone within 10 km00None within 10 km
(2.)NPANone within 10 km00None within 10 km
(3.)ESZsNone within 10 km00None within 10 km
(4.)CorridorsNone within 10 km00None within 10 km
(5.)Wildlife CorridorsNone within 10 km00None within 10 km
(6.)ESAsNone within 10 km00None within 10 km
(7.)Critically Polluted AreaNone within 10 km00None within 10 km
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone within 10 km00None within 10 km
(2.)Defence InstallationsNone within 10 km00None within 10 km
(3.)ForestNone within 10 km00None within 10 km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.2
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired 1.2
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 000
(e)Funds Allocated for R&R(in INR) (in Lacs) 00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Veri Pond
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Soliya Pond
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 7.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 00
(b)Permanent Employment-During Operation 45
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 00
(e)No. of working days 26
(f)Total Manpower 50
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.40
(b)Percentage of Total Project Area 33.44
(c)No. of Plants to be Planted 900
(d)Funds Allocated for Plantation 300000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0084
(ii)Name of the EIA Consultant San Envirotech Pvt. Ltd., Ahmedabad
(iii)Address 401/402/423/424/324, Medicine Market, Opp. Shefali Centre, Paldi Cross Road, Ahmedabad
(iv)Mobile No. 9825007201
(v)Landline No. 0792658307
(vi)Email Id mahendra.sepl@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 16 Mar 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA(i) In S. No. 7.1 of Form 2, the correspondence letter from MS, SPCB on PH has not been uploaded. Also issues raised during the public hearing has not been addressed. The details of action plan on the issues raised during PH along with budgetary provisions & timelines needs to be submitted. (ii) In S. No. 2 of Form 2, the Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency has not been submitted. (iii) EIA report to be revised as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006. (iv) All old CTOs not uploaded to verify the violation, if any done by PP. (v) In view of the above, PP/Consultant are requested to revise the application for grant of EC and accordingly revise the Form 2 alongwith EIA/EMP Reports. The EIA/EMP Reports shall match with the information as filled in Form 2. On examination it is observed that the Consultant has not adequately submit the application as per the provisions of the EIA Notification, 2006. Consultant has to read the documents before uploading the information in Form 2 /EIA/EMP report. 07 Jan 2020
2.NAThe correction have been made as per the instruction received 01 Feb 2020
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe are uploading herewith clarification of points raised by honorable EAC and Final EIA report with required correction. 16 May 2020
2. ADS Reply LetterWe are uploading herewith clarification of points raised by honorable EAC and Final EIA report with required correction. 16 May 2020
3.NA

The EAC, after detailed deliberations decided to defer the proposal for want of requisite information as under and have asked the PP to revise the Report alongwith following clarification/information:-

24 Apr 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantChetanbhai Chhaganbhai Bhut
DesignationPartner
Name of Company (Applicant Name should not be given here)FENGEL CROP SCIENCES(UNIT-II)
AddressSurvey no. 65/2, Village: Shemala, Tehsil: Gondal, District: Rajkot
Print