Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) mawlong limestone mines
(b)Name of the Company / Organisation K SINGH WANN AND SONS
(c)Registered Address Village Ichamati, P.O. Ichamati, Via Shella,,,East Khasi Hills,Meghalaya-793112
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Khlur Singh Wann
(b)Designation (Owner/ Partner/ CEO) Proprietor
(c)Address Village Ichamati,P.O.Ichamati, Via Shella,,Shella Bholaganj,East Khasi Hills,Meghalaya-793112
(d)Pin code 793112
(e)E-mail ksinghwann1@gmail.com
(f)STD Code. 33(f)Telephone No. 24611037
(g)Fax No. 24611037
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/ML/MIN/77659/2018
(d)Master Proposal Number(Single Window) SW/127882/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. MSS R 90 91
(b)Pincode 793112
(c)Bounded Latitudes (North)
From
Degree 251046.90
Minutes
Second
From
Degree 251048.51
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 914151.30
Minutes
Second
From
Degree 914151.55
Minutes
Second
(e)Survey of India Topo Sheet No. 78O12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 180
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4.5
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Meghalaya
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MeghalayaEast Khasi HillsShella Bholaganj
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11015/146/2018-IA-II(M)
(b)Date of Apply of TOR 22 Oct 2018
(c)Date of Issue of TOR / Standard ToR 11 Dec 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :14 Jun 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :17 Jul 2019
Distance of Public Hearing Venue from the Proposed Project :1
Panchyat Bhawan Parisar
State :Madhya Pradesh
District :Panna
Tehsil :Pawai
Village :Devra
222Action Plan And Budget Pertins To Issues Raised During The Public During S.No. Name & Address (Shri) Raised issues Action Plan Budget 1 Smt Monika Tiwari Sarpanch Village- Devra (MP) We are thanOthersADM
(2.)
Date of Advertisement :08 Aug 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :16 Aug 2019
Distance of Public Hearing Venue from the Proposed Project :1.5
Ichamati village
State :Meghalaya
District :East Khasi Hills
Tehsil :Shella Bholaganj
Village :Ichamati
22overall development of the area with employment opportunity for the locals. Other social issues were raised and the locals are convinced that with the mining project their livelihood shall be betterDeputy Commissioner
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)4.56 Hectares of mining area4.56 hect
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)4.56 hect120001Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? Obtained
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 19 Feb 2018
(iv)Valid Upto 31 Mar 2019
(v)File No. MPCB/TB-66/2004/2015-16/31
(vi)Application No. MPCB/TB-66/2004/2015-16/31
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 4.5
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.13
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.061
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.06
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 180
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 180
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HSD180Kilo Litre per Dayn.a.Road1.5 Open MarketCopy of Linkage
(2.)HSD180Kilo Litre per DaynaRoad1.5 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 23 Oct 2018 To 21 Jan 2019
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 07
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube32103160
(2.)SO2Micro Gram per Meter Cube62.9480
(3.)PM10Micro Gram per Meter Cube853075100
(4.)NOxMicro Gram per Meter Cube3463080
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)OthersTotal ColiformOthersMPN/100ML00000000
(2.)Chloridesmg/l13.594.85250250
(3.)TDSmg/l10466500500
(4.)pHNA6.85.86.58.5
(5.)Fluoridemg/l0.640.4311
(6.)Othersnitratemg/l2.02.04545
(7.)OthersIronmg/l1.70.690.300.30
(8.)TSSNA00000000
(9.)Total Hardnessmg/l80.0828.03300300
    14.3.     No. of Surface Water monitoring locations : 04
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.177.40C
(2.)OthersTDSmg/l14438C
(3.)DOmg/l6.206.00C
(4.)BODmg/l21C
(5.)CODmg/l2.11.2C
(6.)OthersCHLORIDEmg/l20.394.85C
    14.4.     No. of Ambient Noise monitoring locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))61.950.085
(2.)Leq(Night)A-weighted decibels(dB(A))47.143.385
    14.5.     No. of Soil Sample Monitored locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.567.56
(2.)N(Nitrogen)Kilogram per hectare238.34238.34
(3.)P(Phosphorus)Kilogram per hectare9.459.45
(4.)K(Potassium)Kilogram per hectare95.4095.40
(5.)Electric ConductivityMillisiemens per Centimetre289289
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 36.30 To 37.20
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 37.50 To 39.10
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface2900 Not Appliacble modeOthersjeepOthersmined out sumpNA26 Nov 201931
(2.)GroundWater21.5 Not Appliacble modeOthersjeepTube WellNA26 Nov 201931
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)3 nos latrines0.010.10septic tank followed by soak pitOthersseptic tank/soak pit0.0100
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0.01
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0.01
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)filtersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5Tons0.1RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)Others(Specify)NoxMicrogram per Meter Cube348.250.0234.1280
(2.)SO2Microgram per Meter Cube68.280.086.1880
(3.)NOxMicrogram per Meter Cube348.250.0234.1280
(4.)PM10Microgram per Meter Cube718.257.178.11100
(5.)PM2.5Microgram per Meter Cube268.252.728.7160
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)00000000PM1000
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 50
(b)Source DG set
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 50kva
(e)Stack Height (in m) 0.8
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 00
(b)Private Land (ha.) 4.56
(c)Government Land (ha.) 00
(d)Revenue Land (ha.) 00
(e)Other Land (ha.) 00
    Total Land (ha.) 4.56
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 00
(b)Waste/Barren Land (ha.) 00
(c)Grazing/ Community Land (ha.) 00
(d)Surface Water Bodies (ha.) 00
(e)Settlements (ha.) 00
(f)Industrial (ha.) 00
(g)Forest (ha.) 00
(h)Mangroves (ha.) 00
(i)Marine Area (ha.) 00
(j)Others (ha.) : VIRGIN LAND 4.56
    Total (ha.) 4.56
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area2.74
(2.)OthersTOP SOIL STORAGE0.16
(3.)Green belt0.52
(4.)Built Up Area0.5
(5.)OB Dump Area0.64
Total (ha.) 4.56
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Wildlife Corridorsna00na
(2.)Critically Polluted Areana00na
(3.)NPAna00na
(4.)ESAsna00na
(5.)WLSna00na
(6.)ESZsna00na
(7.)Corridorsna00na
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Othersmawsmai waterfallsmawsmai waterfalls6NA
(2.)ForestTyma dense mixed jungle6.8NA
(3.)Archaeological SitesMawsmai cave6.25NA
(4.)Defence InstallationsBSF BORDER OUTPOST AND BSF H.Q3NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.56
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired 00
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in INR) (in Lacs) 00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area shella river
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 7.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction
(b)Permanent Employment-During Operation
(c)Temporary Employment- During Construction
(d)Temporary Employment- During Operation
(e)No. of working days
(f)Total Manpower
32.
Green Belt in Ha:
(a)Total Area of Green Belt
(b)Percentage of Total Project Area
(c)No. of Plants to be Planted
(d)Funds Allocated for Plantation
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmentalplantation of local species thereby increasing greenery
(2.)SocialDirect local employment of 21 persons and indirect employment of 80 persons ; renovation of school, clubs, roads etc.; distribution of sports material to local schools etc
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)LIMESTONEMajor
(2.)LIMESTONEMajor
2.
Mine Capacity in ROM (Run of Mine) 120001
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. IBM/GHY/MEG/EKH/LST-4
(b)Date of Approval 04 May 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 4.56
(f)Approved Capacity 120001
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 0.22
(b)Mineable Reserves (Million Ton) 0.18
(c)Extractable Reserves(Million Ton) 0.17
(d)Percent(%) of Extraction 80
(e)Grade of Coal /Ore /Mineral 54
(f)Stripping Ratio 1 : 0.0006
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 6
(i)Mining Method Opencast
(j)Life of Mine (Years) 1.76
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 4.56
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 22 Dec 2017
(iii)Validity of LOI 20
(iv)Reference No. of LOI MG.10/2014/198
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 4.56
(iii)Validity of the lease deed From : 14 Dec 2005 To : 13 Dec 2025
(iv)Date of Execution of Mining Lese 13 Mar 2006
(v)Reference Number MG.10/2004/62
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof NA
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 0.41
(iii)Height (in meter) 4
(iv)Quantity (in Million Cubic meter) 0.02
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.00128
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.00128
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 00
11.
Details of Final Mine Void:
(a)Area (in Hectare) 3.05
(b)Depth (in meter) 15
(c)Volume (in Million Cubic meter) 0.46
12.
Details of Quarry:
(a)Final Void of 1.5 (hectare) at a Depth of 3.5 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 3.08
13.
Details of Transportation:
(a)In Pit/Underground to Surface DUMPERS
(b)Surface to Siding/Loading DUMPERS
(c)Transportation / Conveyor Details DUMPERS
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND0019201920
(2.)OTHERS(Specify)Mineralised land4.56445.44450
(3.)SURFACE WATER BODIES00750750
(4.)SETTLEMENTS00145145
(5.)FOREST LAND001650016500
(6.)WASTE LAND0021552155
(7.)GRAZING LAND00000
TOTAL4.5621915.4421920
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)TOP SOIL STORAGE00000.1600.16
(2.)Otherretaining wall garland drain00000.2200.22
(3.)EXCAVATION/QUARRY002.744002.744
(4.)EXTERNAL OB DUMPS0000000
(5.)ROADS00000.3840.384
(6.)GREEN BELT0.52000000.52
(7.)INTERNAL OB DUMPS0.4100000.41
(8.)BUILT UP AREA (COLONY/OFFICE)00000.1220.122
(9.)VIRGIN AREA0000000
TOTAL0.932.7440.88604.56
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 00
(b)Internal Dump(in hectare) 0.41
(c)Quarry(in hectare) 00
(d)Safety Zone(in hectare) 00
(e)Final Void of 00 (hectare) at a Depth of 5 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 00
(h)Total afforestation plant (in hectare) 1025
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)0000001200010000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ?
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ?
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document?
(i)Accreditation No.
(ii)Name of the EIA Consultant
(iii)Address
(iv)Mobile No.
(v)Landline No.
(vi)Email Id
(vii)Category of Accreditation
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterThe Additional details as sought for are attached in the attach document module are I. Letter to the APCCF Wildlife and Chief Wildlife Warden Meghalaya regarding submission of Conservation Plan is at page 1 of the attach document and II. A copy of letter dated 28th August, 2020 from the APCCF Wildlife and Chief Wildlife Warden Meghalaya at page 2 of the attached document. 26 Nov 2020
2. ADS Reply LetterThe Additional details as sought for are attached in the attach document module are I. Letter to the APCCF Wildlife and Chief Wildlife Warden Meghalaya regarding submission of Conservation Plan is at page 1 of the attach document and II. A copy of letter dated 28th August, 2020 from the APCCF Wildlife and Chief Wildlife Warden Meghalaya at page 2 of the attached document. 26 Nov 2020
3. ADS Reply LetterThe Additional details as sought for are attached in the attach document module are I. Letter to the APCCF Wildlife and Chief Wildlife Warden Meghalaya regarding submission of Conservation Plan is at page 1 of the attach document and II. A copy of letter dated 28th August, 2020 from the APCCF Wildlife and Chief Wildlife Warden Meghalaya at page 2 of the attached document. 26 Nov 2020
4. ADS Reply LetterThe Additional details as sought for are attached in the attach document module are I. Letter to the APCCF Wildlife and Chief Wildlife Warden Meghalaya regarding submission of Conservation Plan is at page 1 of the attach document and II. A copy of letter dated 28th August, 2020 from the APCCF Wildlife and Chief Wildlife Warden Meghalaya at page 2 of the attached document. 26 Nov 2020
5.NAI. A copy of letter dated 28th August, 2020 not found, pl. provide copy of letter dated 28th August, 2020. II. Proof of submission for Schedule -I species conservation plan. 17 Nov 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKhlur Singh Wann
DesignationProprietor
Name of Company (Applicant Name should not be given here)K SINGH WANN AND SONS
AddressVillage Ichamati, P.O. Ichamati, Via Shella,
Print