Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Expansion of the Steel Plant by installation of Pellet Plant with Grinding Facility (2x0.85 MTPA), Sponge Iron Plant (1x350 TPD Kiln), Induction Furnaces (3x25 T), Capacity revision from 600
(b)Name of the Company / Organisation BRAVO SPONGE IRON PRIVATE LIMITED
(c)Registered Address 41A, A.J.C Bose Road, Diamond Prestige Building, 8th Floor, Room No. 801, Kolkata-700017, West Bengal,,Kolkata,West Bengal-700017
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Deepak Kumar Agarwal
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address 41A, A.J.C. Bose Road, Diamond Prestige Building, 8th Floor, Room No. 801, Kolkata-700017, West Bengal,,,Kolkata,West Bengal-700017
(d)Pin code 700017
(e)E-mail cmdsipl1@gmail.com
(f)STD Code. 33(f)Telephone No. 66255252
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/IND/125425/2015
(d)Master Proposal Number(Single Window) SW/125419/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Mahuda J L No. 84
(b)Pincode 723145
(c)Bounded Latitudes (North)
From
Degree 23.546808
Minutes
Second
From
Degree 23.552545
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 86.542489
Minutes
Second
From
Degree 86.549793
Minutes
Second
(e)Survey of India Topo Sheet No. -
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 190
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area .
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/758/2009-IA.II(I)
(c)Date of Issue of TOR 03 Dec 2015
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 07 Dec 2019
(c)Date of Issue of EC 05 Nov 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
NIL
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhubaneswar
(iii)Letter No. 102-577/16/EPE
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 20 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Pellet0.017000001700000Tons per Annum(TPA)Road,Rail
(2.)Billets6007501350OthersTPDRoad,Rail
(3.)Rolling Mill0.010001000OthersTPDRoad,Rail
(4.)Power18725OthersMWOthersPower Transmission
(5.)Producer Gas0.04800048000OthersNm3 per hourOthersPipelines
(6.)Sponge Iron395350745OthersTPDRoad,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Sponge Iron Plant3x100 TPD + 1x95 TPD1x350 TPD3x100 TPD + 1x95 TPD + 1x350 TPD-
(2.)Induction Furnace4x15 T3x25 T4x15 T + 3x25 T-
(3.)Rolling Mill0.01000 TPD1000 TPD-
(4.)Captive Power Plant18 MW (8 MW WHRB + 10 MW AFBC)7 MW (WHRB)25 MW (15 MW WHRB + 10 MW AFBC)-
(5.)Pellet Plant-2x0.85 MTPA2x0.85 MTPA-
(6.)Producer Gas Plant0.012x4000 Nm3/hr12x4000 Nm3/hr-
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 28 Jun 2018
(iv)Valid Upto 31 Dec 2021
(v)File No. 507-as-co-5/10/0135
(vi)Application No. C00000000197599
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 475
(b) Funds Allocated for Environment Management (Capital) (in Crores) 27
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.81
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 2.7
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel .
(b)Existing quantity of raw material/fuel .
(c)Total quantity of raw material/fuel NaN
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal496993Tons per Annum-Road,Rail. Open MarketCopy of Linkage
(2.)Iron Ore fines1793400Tons per Annum-Road,Rail. Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube4518.60
(2.)PM10Micro Gram per Meter Cube9550.100
(3.)SO2Micro Gram per Meter Cube184.80
(4.)NOxMicro Gram per Meter Cube3810.80
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.46.7..
(2.)Total Hardnessmg/l176108..
(3.)Chloridesmg/l14068..
(4.)Fluoridemg/l0.550.28..
(5.)TDSmg/l515289..
(6.)Heavy MetalsFemg/l0.660.28..
(7.)TSSmg/l....
    14.3.     No. of Surface Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA6.8.C
(2.)DOmg/l6.8.C
(3.)CODmg/l..C
(4.)OthersFemg/l0.22.C
(5.)BODmg/l3.C
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))55.145.2.
(2.)Leq(Day)A-weighted decibels(dB(A))69.955.7.
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityMillisiemens per Centimetre261247
(2.)pH6.45.9
(3.)P(Phosphorus)Kilogram per hectare23.322.6
(4.)N(Nitrogen)Kilogram per hectare422410
(5.)K(Potassium)Kilogram per hectare274262
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 6 To 8
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 4
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface160712Copy of Permission LetterPipelineOthersFloating BargeWBIDC/WATER/I&W/2015-16/188502 Dec 20162500
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial237237-Reuse within the Plant & Recycling,Green Belt Renewal Plant237
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 237
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 237
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)DolocharIndustrial Waste25000Tons.RoadOthersTo be used in FBC Boiler
(2.)IF Slag & DustIndustrial Waste33500Tons.RoadOthersLand filling & Road Construction
(3.)TarIndustrial Waste3564Tons.RoadOthersTo be disposed as per MoEF&CC Guideline
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube20.70.85.80826.50980
(2.)PM10Microgram per Meter Cube69.30.56.06175.361100
(3.)PM2.5Microgram per Meter Cube.....
(4.)SO2Microgram per Meter Cube8.40.85.80814.20980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Induction FurnaceElectric301.5PM100.7
(2.)WHRBWaste Heat from DRI452.2PM100.8
(3.)Pellet PlantProducer Gas502.5PM101.93
(4.)Pellet PlantProducer Gas502.5PM101.93
(5.)Induction FurnaceElectricity301.5PM100.7
(6.)Induction FurnaceElectric301.5PM100.7
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 43600
(b)Source DVC & CPP
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) .
(e)Stack Height (in m) .
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0.0
(b)Private Land (ha.) 31.73
(c)Government Land (ha.) 0.0
(d)Revenue Land (ha.) 0.0
(e)Other Land (ha.) 0.0
    Total Land (ha.) 31.73
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) .
(b)Waste/Barren Land (ha.) .
(c)Grazing/ Community Land (ha.) .
(d)Surface Water Bodies (ha.) .
(e)Settlements (ha.) .
(f)Industrial (ha.) 31.73
(g)Forest (ha.) .
(h)Mangroves (ha.) .
(i)Marine Area (ha.) .
(j)Others (ha.) : - .
    Total (ha.) NaN
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant19.73-
(2.)Township0.0-
(3.)Green belt10.4-
(4.)Ash Pond0.0-
(5.)Quarry Area0.0-
(6.)OB Dump Area0.0-
(7.)Safety Zone0.0-
(8.)Tailing Pond0.0-
(9.)LandFill0.0-
(10.)Water Reservoir1.6-
(11.)Desalination Plant0.0-
(12.)Area for Solid Waste Management0.0-
(13.)Built Up Area0.0-
Total (ha.) 31.73
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNone.-
(2.)NPANone.-
(3.)ESAsNone.-
(4.)ESZsNone.-
(5.)CorridorsNone.-
(6.)Wildlife CorridorsNone.-
(7.)Critically Polluted AreaNone.-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone.-
(2.)Archaeological SitesNone.-
(3.)Defence InstallationsNone.-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0.0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 31.73
(b)Land yet to be acquired(Ha) 0.0
(c)Status of Land acquisition if not acquired 0.0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0.0
(b)No. of Households 0.0
(c)No. of PDFs (Project Displaced Families) 0.0
(d)No. of PAFs (Project Affected Families) 0.0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0.0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Damodar River
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 9.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0.0
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 0.0
(d)Temporary Employment- During Operation 900
(e)No. of working days 365
(f)Total Manpower 1000
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt3.27.210.4
(2.)Percentage of Total Project Area..NaN
(3.)No. of Plants..NaN
(4.)Funds Allocated..NaN
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment & Local Development
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1011/010
(ii)Name of the EIA Consultant Envirotech East Pvt. Ltd.
(iii)Address Bengal Ambuja Commercial Complex UN F13, 1050/1, Survey Park, Kolkata-700 075
(iv)Mobile No. 9331026867
(v)Landline No. 0332443812
(vi)Email Id eeplkol@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 13 Mar 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAProposal is returned due to the following: i. Closure report on the observed non-compliance reported in the RO report dated 28/10/2019 shall be furnished. ii. Implementation status of the existing environmental clearances shall be submitted. iii. Social impact assessment has not been carried out as per the prescribed ToR. iv. Hazard Identification and Risk Assessment (HIRA) has not been adequately prepared in respect of qualitative and quantitative assessment along with Emergency Response Plan. Hence, HIRA shall be carried out and report shall be furnished. v. Engineering drawing layout shall be furnished along with legends. 18 Nov 2019
2.NAThe correction have been made as per the instruction received 07 Dec 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS Reply submission. 16 Jul 2020
2.NADeferred the consideration of the proposal  19 May 2020
3. ADS Reply LetterNA 16 Apr 2020
4.NA

Proposal deferred for want of additional information

09 Jan 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDeepak Kumar Agarwal
DesignationDirector
Name of Company (Applicant Name should not be given here)BRAVO SPONGE IRON PRIVATE LIMITED
Address41A, A.J.C Bose Road, Diamond Prestige Building, 8th Floor, Room No. 801, Kolkata-700017, West Bengal
Print