Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Development of the existing Puducherry Minor Port by carrying out capital dredging and construction of a pile supported bridge between drainage channel and navigational channel under "Sagarmala" schem
(b)Name of the Company / Organisation PORT DEPARTMENT
(c)Registered Address No.1, Rue Dumas Puducherry,,Pondicherry,Puducherry-605001
(d)Legal Status of the Company State Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Shanmugasundaram V
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address No.1, Rue Dumas, Puducherry,,Ariankuppam Commune Panchayat,Pondicherry,Puducherry-605001
(d)Pin code 605001
(e)E-mail portpondicheery@gmail.com
(f)STD Code. 413(f)Telephone No. 23371141
(g)Fax No. 2338092
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(e) Ports, Harbours
Minor Activity
(b)Category A
(c)Proposal Number IA/PY/MIS/87021/2018
(d)Master Proposal Number(Single Window) SW/124796/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Resurvey No. 402, Uppalam village, Puducherry
(b)Pincode 605001
(c)Bounded Latitudes (North)
From
Degree 371760.97
Minutes
Second
From
Degree 372970.03
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 1316238.56
Minutes
Second
From
Degree 1316739.98
Minutes
Second
(e)Survey of India Topo Sheet No. 58M/13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 0.9
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 50
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Puducherry
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)PuducherryPondicherryAriankuppam Commune Panchayat
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 10-8/2019-IA-III
(c)Date of Apply of TOR 29 Nov 2018
(d)Date of Issue of TOR / Standard ToR 19 Feb 2019
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :03 Jul 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :02 Aug 2019
Distance of Public Hearing Venue from the Proposed Project :1
Puducheery Old Port Area, Port Department, Rue Dumas Street, Puducheery
State :Puducherry
District :Pondicherry
Tehsil :Pondicherry Taluk
Village :Uppalam
153Continuous closure of mouth of port. Preventive measures shall be taken up to make the port round the clock active.Shall be ensured that there is no disturbance to mangroves.Welfare measures for fisheDistrict Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)DredgingDredging of port basin and channel to - 5 m depthNo change in existing cargo handling capacity
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Capital and Maintenance dredging0.88OthersMillion meter cubeOthersDredger
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 44
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.44
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.75
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1200
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1200
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)fuel for dredger1200OthersKilo literopen marketRoad3 Open MarketCopy of Linkage
(2.)Reinforcement Steel280Tons per Annumopen marketRoad10 Open MarketCopy of Linkage
(3.)CONSTRUCTION MATERIAL925Otherscubic meteropen marketRoad10 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 04 Mar 2019 To 30 Sep 2019
(b)Season Three-Sesions
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube53.634.250.58100
(2.)PM2.5Micro Gram per Meter Cube21.510.219.860
(3.)SO2Micro Gram per Meter Cube13.15.810.980
(4.)NOxMicro Gram per Meter Cube23.414.821.8480
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA6.96.116.58.5
(2.)TSSmg/l6.70.700
(3.)Chloridesmg/l326641000250
(4.)Total Hardnessmg/l416152600200
(5.)TDSmg/l7002982000500
(6.)Fluoridemg/l0.940.291.51.0
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.536.85A
(2.)BODmg/l122A
(3.)CODmg/l283.4A
(4.)DOmg/l6.15.1A
    14.4.     No. of Ambient Noise monitoring locations : 4
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))54.245.855
(2.)Leq(Night)A-weighted decibels(dB(A))433445
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.124.61
(2.)N(Nitrogen)Milligram per Kilogram11258.6
(3.)P(Phosphorus)Milligram per Kilogram21.19.7
(4.)K(Potassium)Milliequivalents per 100 Gram0.080.02
(5.)Electric ConductivityOthersmicrosiemens/cm34748
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersPublic Health Department, Puducherry152Copy of Permission LettermodeOthersPipeline/tanker supplyOthersPipeline/tanker supplyNo.1340/PW/PHD/EE/F.No/2019-2023 May 201915
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic wastewater50Public health sewerage systemOthersPublic Sewerage05
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 5
(b)Total Discharged Water (Kilolitre per Day) 5
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal Solid WasteMunicipal Solid Waste182.5Tons9RoadSanitary Landfills
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube44.340.50.4544.8100
(2.)NOxMicrogram per Meter Cube19.220.51.821.0380
(3.)PM2.5Microgram per Meter Cube16.670.50.2516.9360
(4.)SO2Microgram per Meter Cube8.840.51.09.8580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)No stack emission- Not applicable000PM100
(2.)No stack emission- Not applicable000SO20
(3.)No stack emission - not applicable000NOx0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 315
(b)Source Government of Puducherry Electricity Department
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) NO usage of DG SET is contemplated.
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 60.7
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 60.7
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 6831.04
(b)Waste/Barren Land (ha.) 347.96
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1211.45
(e)Settlements (ha.) 5209.06
(f)Industrial (ha.) 103.91
(g)Forest (ha.) 0
(h)Mangroves (ha.) 81.89
(i)Marine Area (ha.) 15815.82
(j)Others (ha.) : scrub land, wet land, saltpan area etc 1798.15
    Total (ha.) 31399.280000000002
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersExisting Pondicherry port60.7No additional land is required for this project.
Total (ha.) 60.7
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNot Applicable0No critically polluted area within 10km radius of project site
(2.)WLSOussudu Wildlife Sanctuary9.6-
(3.)ESAsMangroves in Ariyankuppam River0.15-
(4.)Wildlife CorridorsNot Applicable0-
(5.)NPANot Applicable0-
(6.)ESZsNot Applicable0-
(7.)CorridorsNot Applicable0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNo Forest Area0-
(2.)Defence InstallationsNo Defense Installations0-
(3.)Archaeological SitesArikamedu1.9-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 60.7
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Does not arise.
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Ariyankuppam River
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Chunnambar river
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 3
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 50
(e)No. of working days 300
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.735
(b)Percentage of Total Project Area 1.21
(c)No. of Plants to be Planted 1000
(d)Funds Allocated for Plantation 400000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details
S. No.Item Details
1.
Project Details:
(a)CRZ Classification IV
(b)Location Type Low and Medium Eroding Coast
(c)Details of Mangroves Land Involved, if Any Mangroves in Ariyankuppam river
(d)Area of Mangroves Land (hectare) 81.89
(e)EIA (Terrestrial) Studies Carried Out
(i)Summary Details of EIA (Terrestrial) Studies Terrestrial environment is healthy.
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Terrestrial) 04 Mar 2019
(iv)Period of Study To (EIA Terrestrial) 30 Sep 2019
(f)EIA (Marine) Studies Carried Out
(i)Summary Details of EIA (Marine) Studies Open sea water quality observed to be normal
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Marine) 04 Mar 2019
(iv)Period of Study to (EIA Marine) 30 Sep 2019
(g)Disaster Management Plan/National Oil Spill Disaster Contigency Plan Yes, covered in the EIA report
2.
Description of the Project Under Consideration:
(a)Type of Project Others
(i)Agency Name for Preparing CRZ Maps Institute of Remote Sensing Anna University, Chenn
(ii)Please Specify with salient features Capital dredging
(iii)Uploaded relevent Document Copy of relevent Document
3.
Distance of Project (in meters) from ltl/htl to be stated :
(a)Clause of CRZ Notification Under which the Project is a Permissible/Regulated Activity IV
(b)Whether CRZ Map Indicating HTL,LTL Demarcation in 1:4000 Scale Prepared? Yes
(i)Distance of Project (in meters) from HTL to be Stated 22.5
(ii)Uploaded Maps(Shape File) Copy of Maps
(iii)Distance of Project(in meters) from LTL to be Stated 22.5
(iv)Uploaded Maps(Shape File) Copy of Maps
(c)Whether Project Layout Superimposed on CRZ Map 1:4000 Scale ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(d)Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(e)Whether CRZ Map Indicating CRZ-I,II,III and IV Including Other Notified ESAs Prepared Yes
(i)Uploaded Maps (kml File) Copy of Maps
(f)NOC from State Pollution Control Boards Obtained No
(g)Details of Rain Water Harvesting System
4.
Recommendation of State Coastal Zone Management Authority:
(a)Copy of CZMA Copy of CZMA
(b)State the Conditions Imposed Monitoring of shoreline change
(c)Social and Environmental Issues and Mitigations Measures Suggested Including but not Limited to R&R, Water, Air, Hazardous Wastes, Ecological aspects, etc. (Brief Details to be Provided) shoreline change
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? Yes
(b)Upload Shoreline Study Copy of Shoreline stuudy
(c)Type of Cargo General,bulk,break bulk,liquid and container cargo
(d)Quantity of Cargo 0.4
(e)Control Measures of Cargo No dirty cargo shall be handled.
(f)Dust Control Measures Water sprinkling in the port area
(g)Quantum 365
(h)Quantity of Dredging (Cubic meter per day) 2411
(i)Type of Dredging Capital
(j)Disposal of Dredge Material Dredge spoil from the mouth portion will be dispos
(k)Details of Outfall Diffusers Not Applicable
(l)No. of Dilution Expected 0
(m)Distance at which the Outlet will Reach Ambient Parameters 0
(n)Details of Monitoring at Outfall Not Applicable
(o)Copy of NoC from PCB in case of Marine Disposal Copy of NoC
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking Existing earmarked parking facilities will be util
5.
Energy Saving Measures:
(a)Source/Mode No energy saving measures proposed
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area No impact to existing water body and drainage patt
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/SA90
(ii)Name of the EIA Consultant Indomer Coastal Hydraulics (P) Ltd.
(iii)Address Indomer: 63, Gandhi road, Alwarthirunagar, Chennai, 600087
(iv)Mobile No. 9940141650
(v)Landline No. 0442486248
(vi)Email Id ocean@indomer.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 12 Sep 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantShanmugasundaram V
DesignationDirector
Name of Company (Applicant Name should not be given here)PORT DEPARTMENT
AddressNo.1, Rue Dumas Puducherry
Print